SUPREME COURT OF INDIA
Chairman and M.D., N.T.P.C. Ltd.
Vs
M/s. Reshmi Constructions, Builders & Contractors
Civil Appeal No. 2754 of 2002
(S. B. Sinha and
V.N.Khare)
05/01/2004
V.N. KHARE, J.
1. This appeal which arises out of a judgment and order dated 23.11.2001 passed
by the High Court of Kerala at Ernakulam revolves round the question as to
whether an arbitration clause in a contract agreement survives despite
purported satisfaction thereof.
2. The parties to this appeal entered into an agreement for a project at
Kayamkulam. Upon completion of the work the respondent herein submitted final
bill which was allegedly not accepted by the appellant, whereafter they
themselves prepared the final bill and forwarded the same along with a printed
format being a "No Demand Certificate". The said "No Demand
Certificate" was signed by the respondent herein which is in the following
terms:
NO DEMAND CERTIFICATE
Name of package :
Earth filling in Temporary Township Part-II
Letter of award :
LOA No. KYM/CS/89/022/NIT-005/LOA-065 dated 19.3.90
Name of the Contractor :
Reshmi Construction, T.C. 4/1298, Keston Road, Kowdiar P.O. - Trivandrum -3
1. This is to certify that we have received all payment in full and final
settlement of the supplied and services rendered and/ or all work performed by
us in respect of the above referred LOA/Contract and we have no other claims
whatsoever final or otherwise outstanding against NTPC. We further confirm that
we shall have no claim/demands in future in respect of this contract of
whatsoever nature, final or otherwise."
2. We would now request you to please release our security deposit contract
performance Guarantee."
3. However, on the same day a letter dated 20.12.1990 was written by the
respondent to the appellant stating:
"We have completed the aforementioned work in the Kayamkulam Super
Thermal Power Project's temporary township area at Nangiarkulangara by the end
of November 1990 itself. We had submitted a pre-final bill in November itself
but the authorities denied the bill and insisted final bill. But when the
alleged final bill was prepared the authorities insisted that a "No Demand
Certificate" should be executed by us in favour of the Corporation. They
served us with a printed specimen of the document and insisted that it should
be typed in our own letterhead and submitted to the N.T.P.C. We refused to
submit such a document.
But the authorities of NTPC threatened that unless and until we execute the
said document in favour of the Corporation, the N.T.P.C. would not effect
payment of our bill. More than six lakhs or Rupees is pending for payment vide
the alleged final bill. We have incurred huge losses in the execution of the
work purely due to the latches and lapses of the corporation. More over lakhs
and lakhs of rupees has to be paid to our Bankers, creditors suppliers,
workers, truck owners etc. etc. Under such a situation we have no other way
other than budging to the coercion of the authorities of NTPC Ltd. to get
whatever they give merely for the necessity of our survival. We have to comply
with the instructions of authorities of NTPC Ltd. out of our helplessness in
order to receive payment. Hence this letter. *
The certificates, undertakings, etc. as aforesaid have been executed without
prejudice to our rights and claims whatsoever on account or the alleged final
bill.
The money invested in the work comprises loans from the Federal Bank Ltd.,
private financiers, etc. as well the Firm's own funds. Those additional sums
raised by loans have to be paid to the Bank, financiers, etc. hence under
duress, coercion and under undue influence we are signing the bill and execute
such documents as aforesaid to receive payment. Under such coercive
circumstances the alleged final bill cannot be constructed as final bill. We
are signing the alleged final bill under coercion, under undue influence and
under protest only without prejudice to our rights and claims whatsoever. There
is no accord and satisfaction between the contracting parties. $
You are therefore, requested to kindly pass the final bill incorporating all
the measurements of the items such as sinkage, in and under water execution of
works, compensation for suspension of works, reimbursement of cost escalation
due to price hike of petroleum products, cost of idling, enhanced rates for
quantities executed beyond the contractual period, market rate for excess
quantities, extra additional items etc. besides the losses and damages by way
of idling of tools and plants, workmen, staff, establishment costs, capital
outlay, interest etc. as per actuals. We hope and request that your goodself
may do the needful in the matter."
* (Emphasis supplied)
4. The respondent thereafter invoked the arbitration clause by reason of a
letter through his advocate dated 21.12.91 wherein the claims under several
heads as enumerated in clause (a) to (p) thereof. Therein a request was made to
refer all the disputes and differences to a sole arbitrator for adjudication
with a direction to make and publish the award within the statutory period.
5. The appellant herein thereafter discussed the matter at the company level
and in its proceedings it was recorded:
"4.0 In case of M/s. Reshmi Constructions, Trivandrum Kerala (1(C)
above) and M/s. C.S. Prakash, 1(d) above) of Porumbavoor, Kerala, the total
payment for the works done were effect, the final bills have been settled
without protest and the no-dues certificates in the standard proforma have been
submitted by the contractors.
5.0 To seek legal opinion in the matter, we have approached Mr. B.S. Krishnan,
a leading advocate from Cochin. On detailed study of the claims of the agencies
and considering legal conditions, the advocate has advised us to appoint
arbitrator/s nominated by CMD of NTPC, immediately. According our advocate has
written suitable replies to the contractor's advocate Shri NT John, of
Trivandrum, informing them that they will hear from NTPC regarding appointment
of an arbitrator in terms of the contract conditions.
6.0 Submitted to appoint arbitrator/s for the four contract packages at para
1.0 above, please."
*
6. The appellant thereafter by its letter dated 13th February, 1992 replied
thereto stating:
"My client acting upon the notice, though defective, takes it that all
your claims are disputed ones and hence are to be resolved by Arbitration. $
Please note that the reference to arbitration does not mean that there is
admission that the disputes are arbitrable. Many of the claims raised are
beyond the terms of the contract and the Arbitrator will have not jurisdiction
to deal with them. This is a matter which has to be taken to later and not at
the stage of appointment of an Arbitrator.
As appointing authority, my client refrains from commenting upon in any
manner, on the merits or otherwise of the disputes which your notice has set
out.
$
It may be noticed that your client has already taken the final bill and has
issued 'no dues' certificate. This is not merely accord and satisfaction, but
bringing the contract to an end.
Your client will hear from my client as regards the appointment of the
Arbitrator in terms of the contract conditions shortly." *
(Emphasis supplied)
*
7. A purported correction in the said notice was issued by the advocate of the appellant
stating:
Sub: Correction in the notice is issued by way of Reply notice is signed on
behalf of M/s. Rashmi Constructions, Trivandrum - reg.
Ref: My Regd. Notice No. P3-G1/92/582 dt. 13.2.92.
Under instructions from my clients, the Chairman & Managing Director,
National Thermal Power Corporation Ltd. NTPC Bhavan, New Delhi-110 003, I issue
the following notice:
In the reply notice issued by me under reference number cited above, it was
stated that the notice issued by you on behalf of your clients M/s. Rashmi
Constructions, Trivandrum was returned since it was not signed by you and that
the notice is sent back as the same was signed on your behalf by your client.
On scrutiny I find that the notice is returned by you after the same is signed
by you and not by your client on your behalf. In paragraph 2 of the reply
notice, I stated that the notice is defective. It was so stated because of the
mistaken impression that the notice is signed by your client and not by you. I
stated that the mistake is in advert at and the same is regretted. I would like
to bring to your notice one more fact which was omitted to be stated in the
reply notice sent earlier. I have already stated that your client has issued
'no dues' certificate. The final bill is accepted by your client without any
protest. This is further followed up by your client receiving the security
deposit released on 21.1.92; that is after the expiry of the stipulated period
reckoned from the date when the contract came to an end.
In all other respects the reply notice earlier sent stands."
*
8. The respondent herein filed an application under Section 20 of the Arbitration Act, 1940 before the Hon'ble Subordinate
Judge's Court Mavelikkara and in terms of a judgment and order dated 30.6.1994
the said application was dismissed. Aggrieved the respondent herein preferred
an appeal before the High Court of Kerala which was allowed by reason of the
impugned order.
9. Mr. Bhatt, the learned counsel appearing on behalf of the appellant urged
that as the contract itself came to an end upon execution of the 'No Demand
Certificate" and together with the same the arbitration clause also
perished. In support of the said contention, reliance has been placed on M/s.
P.K. Ramaiah and Company vs. Chairman & Managing Director, National Thermal
Power Corpn. ) and Nathani Steels Ltd. vs. Associate Constructions 8).
10. Mr. Bhatt further urged that as in its application under Section 20 of the
Arbitration Act, the respondent did not raise a plea that they had been coerced
to submit the "No Demand Certificate", the High Court committed a
manifest error in passing the impugned judgment.
11. The learned counsel appearing on behalf of the respondent, on the other
hand, submitted that in the facts and circumstances of the case neither any new
contract has come into being nor there was any accord and satisfaction of the
contract agreement.
12. The learned counsel appearing on behalf of the respondent also contended
that despite coming to an end of the contract, the arbitration clause survives
and all questions arising out of or in relation to the execution of the
contract are referable to arbitration. Reliance in this connection has been
placed on Damodar Valley vs. K.K. Kar , M/s. Bharat Heavy Electricals
Limited vs. M/s. Amar Nath Bhan Prakash ), Union of India and Another vs.
M/s. L.K. Ahuja and Co. ) and Jayesh Engineering Works vs. New India
Assurance Co. Ltd. 2000 (10) SCC 178).
13. On the arguments of learned counsel for the parties, the questions that
arise for our consideration are:
i) Whether after the contract comes to an end by completion of the contract
work and acceptance of the final bill in full and final satisfaction and after
issuing a No Demand Certificate by the contractor, can any party to the contract
raise any dispute for reference to arbitration?
ii) Whether in view of the letter dated 20.12.1990 sent by the respondent
contractor the arbitration clause contained in the agreement can be invoked?
iii) Whether the arbitration clause in the agreement has perished with the
contract?
14. In this context it is relevant to refer the arbitration clause contained in
the agreement which runs as under:
"56. Except where otherwise provided for in the contract all questions
and disputes relating to the meaning of the specifications, designs, drawing
and instructions herein before mentioned and as to the quality of workmanship
or materials used on the work or as to any other question, claim, right, matter
or thing whatsoever in any arising out of or relating to the contract, designs
drawing, specifications, estimates, instructions, orders or these conditions or
otherwise concerning the works; or the execution or failure to execute the same
whether arising during the progress of the work or after the completion or
abandonment thereof shall be referred to the sole arbitration or the General
Manager of National Thermal Power Corporation Ltd; and if the General Manager
is unable or unwilling to act: to the sole arbitration of some other person
appointed by the Chairman and Managing Director; National Thermal Power
Corporation Ltd. willing to act as such arbitrator. There will be no objection
if the arbitrator so appointed is an employee of National Thermal Power
Corporation Ltd. and that he had to deal with the matters to which the contract
relates and that in the course his duties as such he had expressed views on all
or any of the matters in dispute or difference. The arbitrator to whom the
matter is originally referred being transferred or vacating his office or being
unable to act for any reason as aforesaid should act as arbitrator and if for
any reason, that is not possible; the matter is not to be referred to
arbitration at all.
Subject as aforesaid the provision of the Arbitration Act,
1940 or any statutory modification or re-enactment thereof and the rules
made thereunder and for the time being in force shall apply to the arbitration
proceeding under this clause. *
It is a term of the contract that the party invoking arbitration shall
specify the disputes or disputes to be referred to arbitration under this
clause together with the amount or amounts claimed in respect of each such
dispute.
The arbitrator(s) may from time to time with consent of the parties enlarge the
time, for making and publishing the award.
The work under the Contract shall, if reasonable possible, continue during the
arbitration proceedings and no payment due or payable to the Contractor shall
be withheld on account of such proceedings.
The Arbitrator shall be deemed to have entered on the reference on the date he
issues notice to both the parties fixing the date of the first hearing.
The Arbitrator shall give a separate award in respect of each dispute or
difference referred to him.
The venue of arbitration shall be such place as may be fixed by the Arbitrator
in his sole discretion.
The award of the arbitrator shall be final, conclusive and binding on the all
parties to this contract.
The cost of arbitration shall be borne by the parties to the dispute, as may be
decided by the arbitrator(s).
In the event of disputes or differences arising between one public sector
enterprise and a Govt. Department or between two public sector enterprises the
above stipulations shall not apply, the provisions of B.P.E. Office Memorandum
No. BPE/GL-001/76/MAN/2 (110-75-BPE (GM-1) dated Ist January 1976 or its
amendments for arbitration shall be applicable." *
15. Clause 52 of the agreement reads as follows:
"52. The final bill shall be submitted by the contractor within three
months of physical completion of the works. No further claims shall be made by
the contractor after submission of the final bill and these shall be deemed to
have been waived and extinguished. Payment of those items of the bill in
respect of which there is no dispute and of items in dispute, for quantities
and at rates as approved by Engineer-in-Charge, shall be made within the period
specified hereunder, the period being reckoned from the date of receipt of the
bill by the Engineer-in-Charge: *
(a) Contract amount the exceeding Rs. 5 lakhs - Four months.
(b) Contract Amount exceeding Rs. 5 lakhs - Six months.
After payment of the amount of the final bills payable as aforesaid has been
made, the Contractor may if he so desires, reconsider his position in respect
of the disputes portion of the final bill and if he fails to do so within 90
days, his disputing claim shall be dealt with as provided in contract." $
* (Emphasis supplied)
16. The issues are required to be determined having regard to the facts as
which arise for consideration whether by reason of the act of the parties the
old contract was substituted by a new contract. Only in the event a new
contract came into being, the arbitration agreement cannot be invoked.
#
17. In Damodar Valley Corporation vs. K.K. Kar ), this Court held:
"It appears to us that the question whether there has been a full and
final settlement of a claim under the contract is itself a dispute arising
'upon' or 'in relation to' or 'in connection with' the contract. These words
are wise enough to cover the dispute sought to be referred." *
18. Normally, an accorded and satisfaction by itself would not affect the
arbitration clause but if the dispute is that the contract itself does not
subsist, the question of invoking the arbitration clause may not arise. But in
the event it be held that the contract survives, recourse to the arbitration
clause may be taken. # (See Union of India vs. Kishorilal Gupta ) and
Majhati Jute Mills vs. Khvalirsa ).
19. In Bharat Heavy Electricals Limited (supra) this Court observed that
whether there was discharge of the contract by accord and satisfaction or not
in a dispute arising out of a contract and is liable to be referred to
arbitration.
20. Yet again in L.K. Ahuja (supra) Sabyasachi Mukharji, J., as the learned
Chief Justice then was, laid down the ingredients of Section 20 of the
Arbitration Act stating:
6. It appears that these questions were discussed in the decision of the
Calcutta High Court in Jiwnani Engineering Works Pvt. Ltd. vs. Union of India
(AIR 1978 Cal 228) where on of us. (Sabyasachi Mukharji, J.) was a party and
which held after discussing all these authorities that the question whether the
claim sought to be raised was barred by limitation or not, was not relevant for
an order under Section 20 of the Act. Therefore, there are to aspects. One is
whether the claim made in the arbitration in barred by limitation under the
relevant provisions of the Limitation Act and secondly, whether the claim made
for application under Section 20 is barred. In order to be a valid claim for
reference under Section 20 of the Arbitration Act, 1940,
is is necessary that there should be an arbitration agreement and secondly
differences must arise to which the agreement in question applied and, thirdly,
that must be within time as stipulated in Section 20 of the Act. *
21. It was held that having regard to the fact that the existence of an
arbitration agreement was not denied and there had been an assertion of claim
and denial thereof, the matter would be arbitrable. It was observed:
In order to be entitled to ask for a reference under Section 20 of the Act,
there must be an entitlement to money and a difference or dispute in respect of
the same. It is true that on completion of the work, right to get payment would
normally arise and it is also true that on settlement of the final bill, the
right to get further payment get weakened but the claim subsists and whether it
does subsist, is a matter which is arbitrable. $ *
(Emphasis supplied)
22. This aspect of the matter has also been considered in Jayesh Engineering
Works (supra) wherein following L.K. Ahuja (supra) it was held:
"Whether any amount is due to be paid and how far the claim made by the
appellant is tenable are matters to be considered by the arbitrator. In fact,
whether the contract has been fully worked out and whether the payments have
been made in full and final settlement are questions to be considered by the
arbitrator when there is a dispute regarding the same." *
23. In M/s. P.K. Ramaiash and Company (supra) the amount was received
unconditionally. The full and final satisfaction was acknowledged by a separate
receipt in writing. In that situation the following finding was recorded:
"Thus there is accord and satisfaction by final settlement of the
claims. The subsequent allegation of coercion is an afterthought and a devise
to get over the settlement of the dispute, acceptance of the payment and
receipt voluntarily given." *
24. We, however, may observe that the quotation from Russell on Arbitration may
not be apt inasmuch as at the stage of reference what would be a good defence
is not a matter to be taken into consideration.
25. Yet again, in Nathani Steels Ltd. (supra) the disputes and differences were
amicably settled by and between the parties and in that view of the matter it
was held that unless and until the statement is set aside, the arbitration
clause cannot be invoked. Such is not the position here.
26. The appellant herein did not raise a question that there has been a novation
of contract. The conduct of the parties as evidenced in their letters, as
noticed hereinafter, clearly go to show that no only the final bill submitted
by the respondent was received but another final bill was prepared with a
printed format that a "No Demand Certificate" has been executed as
other final bill would not be paid. The respondent herein, as noticed
hereinbefore, categorically stated in its letter dated 20.12.1990 that as to
under what circumstances they were compelled to sign the said printed letter.
It appears from the appendix appended to the judgment of the learned Trial
Judge that the said letter was filed even before the trial court. It is,
therefore, not a case whether the respondent's assertion of 'under influence or
coercion" can be said to have been taken by way of an afterthought.
27. Even when rights and obligations of the parties are worked out the contract
does not come to an end inter alia for the purpose of determination of the
disputes arising thereunder, and, thus, the arbitration agreement can be
invoked. Although it may not be strictly in place but we cannot shut out eyes
to the ground reality that in the cases where a contractor has made huge
investment, he cannot afford not to take from the employment the amount under
the bills, for various reasons which may include discharge of his liability
towards the banks, financial institutions and other persons. In such a
situation, the public sector undertakings would have an upper hand. They would
not ordinarily release the money unless a 'No Demand Certificate' is signed.
Each case, therefore, is required to be considered on its own facts.
28. Further, necessitas non habet legem is an old age maxim which means
necessity knows no law. A person may sometimes have to succumb to the pressure
of other party to the bargain who is on a stronger position.
29. We may, however, hasten to add that such a case has to be made out and
proved before the Arbitrator for obtaining an award. #
30. At this stage, the Court, however, will only be concerned, with the
question whether triable issues have been raised which are required to be
determined by the Arbitrators. #
31. Circumstances leading to passing an order by the courts of law directing
the parties to get their disputes determined by domestic tribunal selected by
them having regard to the correspondences exchanged between the solicitors came
up for consideration in Goodman vs. Winchester and Alton Rly 1984 Indlaw CA 115 wherein it was held:
"As I have already recounted, the plaintiff's solicitor may have had in
mind that if there were an arbitration clause various matters could be sorted
out cheaply and quickly under it. There is no evidence, in my judgment, that
when he drafted the terms of the arbitration clause he had in mind that it would
not apply to a repudiation of the contract by the defendants. He is a
solicitor, he is clearly an experienced solicitor; and he should have
appreciated (and I feel certain he did) that the arbitration clause which he
drafted, and which was accepted by the defendants, would cover every aspect of
the contract, including repudiation. But, apart altogether from what the
plaintiff's solicitor had in mind, there is no evidence at all as to what the
defendant company had in mind when it agreed to accept the arbitration clause,
and it was wrong, in my judgment, for the Judge to say that neither party had
in mind that it would apply to the summary dismissal of the plaintiff. It
follows, therefore, that at the very beginning of his judgment the judge
misdirected himself as to the construction of the arbitration clause and what
it was mended to deal with."
*
32. Even correspondences marked as without prejudice may have to be interpreted
differently in different situations.
33. What would be the effect of without prejudice offer has been considered in
Cutts vs. Head and Another 1983 Indlaw CA 8)
wherein Oliver L.J. speaking for the Court of Appeals held:
"In the end, I think that the question of what meaning is given to the
words 'without prejudice" is a matter of interpretation which is capable
of variation according to usage in the profession. It seems to be that, no
issue of public policy being involved, it would be wrong to say that the words
were given a meaning in 1889 which is immutable ever after, bearing in mind
that the precise question with which we are concerned in this case did not
arise in Walker vs. Wilsher, 23 Q.B.D. 335, and the court did not deal with it.
I think that the wise body of practice which undoubtedly exists must be treated
as indicating that the meaning to be given to the words is altered if the offer
contains the reservation relating to the use of the offer in relation to
costs." *
34. Yet again in Rush & Tompkins Ltd. vs. Greater London Council and
Another 1987 Indlaw CA 85:
"The rule which gives the protection of privilege to 'without
prejudice' correspondence 'depends partly on public policy, namely the need to
facilities compromise, and partly on 'implied agreement' as Parker LJ stated in
South Shropshire DC vs. Amos (1987) 1 All ER 340 at 343, (1986) 1 WLR 1271 at
1277. The nature of the implied agreement must depend on the meaning which is
conventionally attached to the phrase 'without prejudice'. The classic
definition of the phrase is contained in the judgment of Lindley LJ in Walker
vs. Wilsher (1889) 23 QBD 335 at 337:
"What is the meaning of the words 'without prejudice'? I think they mean
without prejudice to the position of the Writer of the letter if the terms he
proposes are not accepted. It the terms proposed in the letter are accepted a
complete contract is established, and the letter, although written without
prejudice, operates to alter the old state of things and to establish a new
one."
Although this definition was not necessary for the facts of that particular case
and was therefore strictly obiter, it was expressly approved by this court in
Tomlin vs. Standard Telephones and Cables Ltd. (1969) 3 All ER 201 at 204, 205,
(1969) 1 WLR 1378 at 1383, 1385 per Danckwerts LJ and Ormrod J. (Although he
dissented in the result, on this point Ormrod J agreed with the majority.) The
definition was further cited with approval by both Oliver and Fox LJJ in this
court in Cutts vs. Head (1984) 1 All ER 597) at 603, 610, (1984) Ch. 290 at
303, 313. In our judgment, it may be taken as an accurate statement f the
meaning of 'without prejudice' if that phrase be used without more. It is open
to the parties to the correspondence to give the phrase a somewhat different
meaning, e.g. where they reserve the right to bring an offer made 'without
prejudice' to the attention of the court on the question of costs if the offer
be not accepted (See Cutts vs. Head) but subject to any such modification as
may be agreed between the parties, that is the meaning of the phrase. In
particular, subject to any such modification, the parties must be taken to have
intended and agreed that the privilege will cease if and when the negotiations
'without prejudice' come to fruition in a conclude agreement". *
35. Meaning the words 'without prejudice' come up for consideration before this
Court in Superintendent (Tech. I) Central Excise, I.D.D. Jabalpur and others
vs. Pratap Rai ) wherein it has been held:
"The Appellate Collector has clearly used the words 'without
prejudice" which also indicate that the order of the Collector was not
final and irrevocable. The term "without prejudice" has been defined
in Black's Law Dictionary as follows:
Where an offer or admission is made 'without prejudice' or a motion is defined
or a bill in equity dismissed 'without prejudice', it is meant as a declaration
that no rights or privileges of the party concerned are to be considered as
thereby waived or lost, except in so far as may be expressly conceded or
decided. See, also Dismissal Without Prejudice.
Similarly, in Wharton's Law Lexicon the author while interpreting the term
'without prejudice' observed as follows:
The words import an understanding that if the negotiation fails, nothing that
has passed shall be taken advantage of thereafter; so, if a defendant offers,
'without prejudice' to pay half the claim, the plaintiff must not only rely on
the offer as an admission of his having a right to some payment.
The rule is that nothing written or said 'without prejudice' can be considered
at the trial without the consent of both parties - not even by a Judge in
determining whether or not there is good cause for depriving a successful
litigant of costs - The word is also frequently used without the foregoing
implications in statutes and inter partes to exclude or save transactions, act
and rights from the consequences of a stated proposition and so as to mean 'not
affecting', 'saving' or 'excepting'.
In short, therefore, the implication of the term 'without prejudice' means (1)
that the cause or the matter has not been decided on merits, (2) that fresh
proceedings according to law were not barred."
*
36. The appellant has in its letter dated 20th December, 1990 has used the term
'without prejudice'. It has explained the situation under which the amount
under the 'No Demand Certificate' had to be signed. The question may have to be
considered from that angle. Furthermore, the question as to whether the
respondent has waived its contractual right to receive the amount or is
otherwise estoppel from pleading otherwise will itself be a fact which has to
be determined by the arbitral tribunal).
37. In Halsbury's Law of England, 4th Edition, Vol. 16 (Reissue) para 957 at
page 844 it is stated:
"On the principle that a person may not appropriate and reprobate a
special species of estoppel has arisen. The principles that a person may not
approbate and reprobate express two propositions:
(1) That the person in question, having a choice between to courses of conduct
is to be treated as having made an election from which he cannot resile.
(2) That he will be regarded, in general at any rate, as having so elected
unless he had taken a benefit under or arising out of the course of conduct,
which he has first pursued and with which his subsequent conduct is
inconsistent." *
38. In American Jurisprudence, 2nd Edition, Volume 28, 1966, Page 677-680 it is
stated:
"Estoppel by the acceptance of benefits: Estoppel is frequently based
upon the acceptance and retention, by one having knowledge or notice of the
facts, of benefits from a transaction, contract, instrument, regulation which
he might have rejected or contested. This doctrine is obviously a branch of the
rule against assuming inconsistent positions.
As a general principles, one who knowingly accepts the benefits of a contract
or conveyance is estopped to deny the validity or binding effect on him of such
contract or conveyance.
This rule has to be applied to do equity and must not be applied in such a
manner as to violate the principles of right and good conscience."
*
39. The fact situation in the present case, would lead to the conclusion
that the arbitration agreement subsists because;
(i) Disputes as regard final bill arose prior to its acceptance thereof in view
the fact that the same was prepared by the respondent but was not agreed upon
in its entirety by the appellant herein;
(ii) The appellant has not pleaded that upon submission of the final bill by
the respondent herein any negotiation or settlement took place as a result
whereof the final bill, as prepared by the appellant, was accepted by the
respondent unequivocally and without any reservation therefor; #
(iii) The respondent herein immediately after receiving the payment of the
final bill, lodged its protest and reiterated its claims.
(iv) Interpretation and/ or application of clause 52 of the agreement would
constitute a dispute which would fall for consideration of the arbitrator.
(v) The effect of the correspondences between the parties would have to be
determined by the arbitrator, particularly as regard the claim of the
respondent that the final bill was accepted by it without prejudice.
(vi) The appellant never made out a case that any novation of the contract
agreement took place or the contract agreement was substituted by a new
agreement. Only in the event, a case of creation of new agreement is made out
the question of challenging the same by the respondent would have arisen.
(vii) The conduct of the appellant would show that on receipt of the notice of
the respondent through its advocate dated 21.12.1991 the same was not rejected
outright but existence of disputes was accepted and the matter was sought to be
referred to the arbitration.
(viii) Only when the clarificatory letter was issued the plea of settlement of
final bill was raised.
(ix) The finding of the High Court that a prima facie in the sense that there
are triable issues before the Arbitrator so as to invoke the provisions of
Section 20 of the Arbitration Act, 1940 cannot be
said to be perverse or unreasonable so as to warrant interference in exercise
of extraordinary jurisdiction under Article 136 of the Constitution of India.
(x) The jurisdiction of the arbitrator under the 1940 Act although emanates
from the reference, it is trite, that in a given situation the arbitrator can
determine all questions of law and fact including the construction of the
contract agreement. (See Pure Helium India Pvt. Ltd. vs. Oil and Natural Gas
Commission reported in 2003(8) SCALE 553).
(xi) The cases cited by the learned counsel for the appellant (P.K. Ramaiah and
Company (supra) and Nathani Steels (supra) would show that the decisions
therein were rendered having regard to the finding of fact that the contract
agreement containing the arbitrator clause was substituted by another
agreement. Such a question has to be considered and determined in each
individual case having regard to the fact situation obtaining therein. #
40. For the reasons aforementioned, we are of the opinion that there is no
infirmity in the impugned judgment. This appeal is, therefore, dismissed. # No
costs.