(SUPREME COURT OF INDIA)
Bareilly Development Authority
Vs
Vrinda Gujarati and Others
HON'BLE JUSTICE S. R. BABU, HON'BLE JUSTICE A. S. LAKSHMANAN AND
26/02/2004
Appeal (Civil) 3706 of 1998
JUDGMENT
DR. AR. LAKSHMANAN J
This appeal is directed against the judgment and order dated 14.5.1996 passed
by the High Court of Judicature at Allahabad in Civil Misc. Writ Petition No.
36735 of 1995. The appellant-Bareilly Development Authority ( hereinafter
referred to as "the BDA") was set up by the State of U.P. by
Notification dated 19.4.1977 issued under Section 3 of the U.P. Urban Planning
and Development Act, 1973. The BDA issued an advertisement calling for
applicants to apply for allotment of flats to be constructed by it in the
Priyadarshani Nagar Yojna of Bareilly under the Pushpanjali Scheme and the
Kusumanjali Scheme. The appellant also issued a Brochure giving the terms and
conditions under which the said applicants could apply for and be allotted the
flats under the said Scheme. The estimated cost of the said flats was also
given in the said Brochure and it was clearly mentioned that the final costing
will be done later and the costing of the flats was subject to the right of the
appellant to amend the same. The Brochure also did not contain any prescribed
date or time period for either construction of the flats or the delivery of
possession.
The respondents in this appeal applied for allotment of flats in Kusumanjali
Scheme. As per the Brochure, 52 flats under the Scheme were to be of 57.10 Sq.
Mtrs. (614.39 Sq. Ft.) and were to cost as follows:-
Ground Floor - Rs.2, 10, 000.00
First Floor - Rs.2, 00, 000.00
Second Floor - Rs.1, 90, 000.00
Third Floor - Rs.1, 80, 000.00
Respondents 1-5 registered themselves for the flats in Kusumanjali Scheme and
also paid the required registration fee. The construction of the flats was
started and thereafter, there was some dispute between the BDA and its
contractor and the construction was delayed for nearly one and a half year and
finally the construction was re-started though only two floors instead of
original four were built in the Kusumanjali Scheme and thus only 22 flats were
built out of 52 originally intended. After the draw of lots, the respondents
were issued allotment letters indicating therein in Clause 2 that the price of
the flat was still an estimated one and that the final costing would be done
after completion on the basis of the actual costs and would be informed
thereafter to the allottee which would be payable by them. Clause 2 of the
Allotment Letter (Annexure-B) reads as under: "The estimated cost of the
flat is Rs.2, 10, 000/-. The final cost would be intimated to you on the basis
of actual costing after the completion of the Scheme, which would be payable by
you."
A Final Costing Committee was set up by the BDA consisting of the Secretary,
the Chief Accounts Officer and the Executive Engineer of the BDA and the
Committee, after due deliberation, recommended that on the basis of the actual
cost of each flat, the price had to be enhanced (in the case of flats on the
ground floor, for example, increasing from Rs.2, 10, 000/- to Rs.2, 81, 100/-).
The Committee also recommended that the allottees be given additional time to
deposit the enhanced amount of the price as the said allottees had already
deposited their respective quarterly instalments. It has further recommended
that in case the allottees fail to deposit the said amount in the time
prescribed, interest @ 18% be charged from them. The respondents were duly informed
by individual notices by the appellant about the final costing of the said
flats and also that they were required to deposit within 15 days of the receipt
of the said notice the balance amount of price of the flat as well as the
proposed lease rent. The respondents filed objections to the said increase in
price. The said representations were rejected by the appellant on
21.10.1993(Annexure-D). When the flats were ready for delivery of possession,
in view of the reluctance shown by the respondents in paying the enhanced
amount, the BDA offered the option to the respondents to either file an
undertaking by way of affidavit that they would pay the enhanced amounts or to
take back their deposit sums with interest. All the respondents filed their
undertakings by way of affidavits dated 19.5.1994 and undertook unconditionally
to be bound by the final costing of the flats by the BDA and also to pay the
enhanced amount. The affidavit reads thus:-
AFFIDAVIT
I, Shrimati Vrinda Gujarati, Wife of Shri B.K. Das, am the resident of 330,
Madhobadi, Bareilly and I hereby on oath state as following:
1. That the decision taken in future by the Bareilly Development Authority
regarding the increase in the cost of the Flat No.9-A (Ground Floor),
Kusumanjali Scheme, Priyadarshani Nagar, Bareilly allotted to me would be
binding on me.
2. That the deponent is ready to deposit the entire amount of the increase in
cost.
Sd/-
Varinda
On 19.6.1993 to 13.7.1994, the BDA delivered possession of the said flats on
various dates to the respondents. The respondents, after taking possession of
their respective premises and after filing the above undertakings once again
made representation to the appellant against the final costing of the said
flats. The BDA, in the meantime, sent another notice to the respondents to pay
the enhanced unpaid amounts of the costs with 18% interest or else legal action
would be taken against them. Since the respondents failed to pay the said
amount in spite of repeated demands, the BDA initiated recovery proceedings
against the respondents under the U.P. Zamindari Abolition and Land Reforms
Act, 1950 and recovery certificates were issued against the respondents by the
Tahsildar, Bareilly. Being aggrieved, the respondents filed C.M.W.P. No.36735
of 1995 before the High Court of Judicature at Allahabad challenging
enhancement in the final cost of the flats and praying, inter alia, that the
recovery proceedings against the respondents initiated by the BDA for recovery
of the unpaid amounts be quashed. The High Court stayed the recovery
proceedings provided the respondents deposited Rs.45, 000/- on or before
31.1.1996. Before the High Court, the BDA placed the Chart showing the details
of the reasons for enhancement of the price. (Annexure-N). The High Court by its
judgment and order dated 14.5.1996 allowed the writ petition filed by the
respondents herein and issued further directions to the BDA regarding
adjustment of various amounts against the final price of the flats, though the
High Court did not either strike down the enhanced price or hold it illegal.
Aggrieved by the said judgment, the BDA has preferred this appeal by way of
special leave petition. We heard Shri Bharat Sangal, learned senior counsel
appearing for the BDA and Mr. A.K. Sanghi & Mr. Punit D. Tyagi, learned
counsel appearing for the respondents. Learned counsel appearing for the
appellant made the following submissions:
(i) There has been no application of mind by the High Court to the terms and
conditions of the contract entered into between the BDA and the respondents and
the High Court has ignored totally the law in regard to such cases as laid down
by this Court.
(ii) The High Court failed to appreciate that Clause 2 of the Brochure of May,
1990 produced by the BDA for the concerned scheme in which the said respondents
applied for and obtained the concerned flats, clearly provided that the cost of
each flat given in the said Brochure was only an estimated and actual cost
would be intimated later at the time of allotment.
(iii) The High Court failed to appreciate that in Clause 15 of the Brochure it
was clearly stated that the BDA reserves the right to amend any term or
condition of the Scheme till the time of allotment and such amendment shall be
binding on the allottees.
(iv) It was contended that the revised cost of the said flats, necessitated by
the increase in size of the flat as well as the increase in each flat's share
in cost of the land due to reduction in number of flats built, were informed to
the respondents, they accepted the increased cost and also filed undertakings
by way of affidavits affirming their decisions to abide by the increase and pay
the required enhanced amount.
(v) The High Court has failed to appreciate that Clause 13 of the Brochure only
provides that the possession would be given to the allottee only after the full
amount has been deposited and it cannot be interpreted to mean that the
possession would be given immediately after the allotment is made. The
direction issued by the High Court regarding the payment of interest by the
authority to the respondents is baseless and issued without any reason. It was
submitted that the High Court has erred in holding that the appellant is not
entitled to any interest on the amounts unpaid to it by the concerned respondents
for the period between 20.12.1995, date of the interim order and 14.5.1996, the
date of the final judgment. In this regard, it was submitted that the High
Court has failed to appreciate that by the interim order dated 20.12.1995, the
High Court had only stayed the recovery proceedings against the said
respondents for non-payment of balance amount, and it cannot be said that the
said order has also stayed the liability of the said respondents to pay the
said amount. It was further submitted that the High Court has not struck down
the enhanced cost announced by the appellant nor has it held that the appellant
is not entitled to recover the unpaid amounts from the respondents and it has
only directed that certain adjustments on account of interest payable to the
respondents and difference in registration fee be adjusted from the final
price.
(vi) The High Court has failed to appreciate that there was no challenge made
to the terms of the Brochure by the respondents at any stage and thus there
could be no interference with the said terms and conditions by the High Court
and in that regard, the High Court has exceeded its jurisdiction by doing so.
It was further submitted that the judgment and order of the High Court is also
bad as it has exceeded its jurisdiction by granting compensation to the
respondents. Per contra, Mr. A.K. Sanghi, learned counsel appearing for the
respondents, submitted that the appellant being a statutory body is under
obligation to provide flats to the respondents, who belong to the Middle Income
Group and other citizens of a reasonable and just price.
The High Court, therefore, was perfectly justified in law in holding that the
enhancement sought to be recovered from the respondents is arbitrary and
without basis whatsoever.
A reading of the terms and conditions of the Brochure would show that the same
were one sided and were rightly held by the High Court to be unconscionable
because the BDA has a duty to construct and allot flats to the poor citizens
who are unable to construct houses on their own. It was further contended that
the terms and conditions of the contract as well as the undertaking given by
the respondents are not voluntary and that the respondents who are weaker
sections of the society were forced to give undertakings which were
unforceable.
We have gone through the relevant records, the undertakings and the affidavits
given by the respondents and the Chart of Escalation and the judgment of the
High Court.
Before proceeding further, it is beneficial to reproduce the Chart of
Escalation which is as follows: Chart of Escalation
1. Estimated area = 614 Sq.ft.
2. Finally constructed area = 702 Sq.ft.
3. Increase in covered area = 88 Sq. ft.
4. Rate of construction per sq. ft. = Rs.342/-
(cost of land included)
5. Increase in construction cost = 342x88= Rs.30, 096/-
6. Cost of land also increased for every purchaser as the construction made was
2 storeyd in place of 4 storeyed
7. Initially purchaser of ground floor had to pay for land = Rs.137/- per Sq.
ft. (This was included in estimated cost of Rs.2, 10, 000/-)
8. After final costing cost of land increased to = Rs.183/- per sq. ft.
9. Increase in cost of land = Rs.46/- per sq. ft.
10. Total increase in cost of land = Rs.32, 292/- for every purchaser of ground
floor
11. Increase in cost of other facilities such as parking, water, sewer etc. =
Rs.8, 500/-
12. Total increase = (Rs.30, 0096+Rs.32.292+ Rs.8, 500 ) Rs.70, 888/- Details
of increased area
1. One more toilet was constructed.
2. In place of two common passages, three common passages were constructed.
3. Bigger Verandah was made.
Total increase in covered area = 88 Sq. ft.
It is seen from the above Chart that the finally constructed area is 702 Sq.
ft. and the increase in the covering area is 88 sq. ft. The BDA has claimed
only the increase in construction cost of 88 sq. ft. @ construction per sq. ft.
at Rs. 342/- namely, Rs.342 x 88 = 30, 096/-. According to the BDA, the cost of
the land has also increased for every purchaser as the construction made was
two storeyed in place of four storeyed. Initially the purchaser of the ground
floor had to pay for land Rs.137/- per sq. ft. which was included in the
estimated cost of Rs.2, 10, 000/-. After final costing, the cost of the land is
now increased to Rs.183/- per sq. ft. The increase in cost of the land is Rs.
46/- per sq. ft. and the total increase in the cost of the land for every
purchaser of ground floor is Rs. 32, 292/-. It is also an admitted fact that
the BDA had provided the other facilities such as parking, water, sewer etc.
and the increase in cost of these facilities is Rs.8, 500/-.
Thus the total increase of construction cost, cost of the land and the other
facilities come to Rs.70, 888/-. The details of the increased area has also
been very clearly spelt out which includes one more toilet, in place of two
common passages, three common passages were constructed and a bigger Verandah
was made and the area covered by these items comes to 88 sq. ft. We have
already referred to the allotment letter, undertaking by way of affidavit and
Chart of Escalation etc. and as per the above undertaking, the BDA is entitled
to collect the enhanced price from the allottees. Once the respondents owe
money to the appellant, it is fully in the competence of the Authority to
recover the same. The parties to this action are bound by the terms of the
contract. This Court in its judgment in the case of Bareilly Development
Authority & Anr.vs. Ajai Pal Singh & Ors. , has clearly held
that the authority or its agent after entering into the field of ordinary
contract acts purely in its executive capacity. Thereafter, the relations are
no longer governed by the constitutional provisions but by the legally valid
contract which determines the rights and obligations of the parties inter se.
At page 124 of the judgment, this Court has also held that once the respondents
have given their written consent accepting the changed and varied terms and
conditions, they cannot be permitted to contend that the authority has gone
back on its original terms and conditions to their detriment. This Court
further held that once the respondents have entered into the realm of concluded
contract pure and simple with the authority they cannot step out of the terms
of the contract unless some statute steps in and confers some special statutory
obligations on the authority in the contractual field.
The above view was endorsed by this Court in its judgment in Indore Development
Authority vs. Sadhana Agarwal (Smt.) & Ors., 5.
This Court in paragraph 9 of this judgment held as under: "But taking
all facts and circumstances into consideration, this Court said that it cannot
be held that there was misstatement or incorrect statement or any fraudulent
concealment, in the brochure published by the Authority. It was also said that
the respondents cannot be heard to say that the Authority had arbitrarily and
unreasonably changed the terms and conditions of the brochure to the prejudice
of the respondents. In that connection, it was pointed out that the most of the
respondents had accepted the changed and varied terms. Thereafter they were not
justified in seeking any direction from the Court to allot such flats on the
original terms and conditions. *
This Court further in paragraph 10 of the judgment held as under: "So
far the facts of the present case are concerned, it is an admitted position
that in the proforma attached to the application for registration, the
appellant said that the price mentioned by them was a probable and estimated
cost, the definite price shall be intimated at the time of the allotment.
Thereafter, the appellant had been informing the respondents and others who had
got themselves registered, from time to time regarding the escalation in the
cost of the flat. One of the reasons for the rise of the price for the LIG Flat
from Rs.60, 000 to Rs.1, 16, 000 appears to be the increase in are of the flat
itself from 500 ft. to 714.94 Sq. fgt. From 1982 to 1984, possession of the
flats could not be delivered because of the dispute pending in the Court which
also contributed to the increase in the cost of the flat.
Admittedly, the respondents came in possession of the flats in the year 1984, .
In the facts and circumstances of the case, we are satisfied that no
interference was called for by the High Court." *
We are, therefore, of the opinion that only obligation on the BDA was to
provide the houses in question on the contractual price and in that regard the
judgment of this Court in L.I.C. of India & Anr.vs. Consumer Education
& Research Centre & Ors., (1995) 5 SCC 482 was cited. The above
judgment has no relevance with the present case.
It was denied by the BDA that the respondents have paid full amount towards the
cost of the flats as alleged. The enhancement in the cost was due to actual
increase in the cost of the flat as detailed in the chart annexed as Annexure-N
which formed part of the supplementary affidavit filed before this Court. Such
enhancement, in our opinion, was in accordance with clauses 2 and 15 of the
Brochure of May, 1990 and the said enhancement was also in accordance with
clause 2 of the allotment letters dated 10.12.1991 issued to various
applicants. The said enhancement was clearly accepted by the respondents by
their various affidavits of undertakings filed on 19.4.1994 and other
respective dates before the BDA. The respondents after undertaking to pay the
enhanced amount and after taking possession of the flats on that ground cannot
be allowed to raise frivolous contentions to avoid payment to the appellant. # At
the time of hearing, this Court on 11.4.1997 passed an order directing the
counsel appearing on behalf of the BDA to find out whether there is a proposal
or likelihood of two more storeyes being added to the flats that have been
constructed. Counsel for the BDA submitted before the Court that the Scheme
originally was to build four storeyed buildings but now only two storeyed
building has been built. As a result, the entire cost of the flats has rateably
been distributed among the occupiers of the two storeys building instead of
larger number of occupiers of the four storeys building as was originally
envisaged. This is another reason for the enhancement in the cost of the flat.
This Court in the case of Delhi Development Authority vs. Pushpendra Kumar
Jain, 2, which was cited before the High
Court, has misinterpreted the said decision. In that case in paragraph 7 at
page 497 of the judgment, this Court held that there was no material produced
before any Court in the said matter to show that there was any delay in
allotment of the flats in the said case due to inefficiency on the part of the
authority and further that as there was no period prescribed in the Scheme for
the allotment hence it could not be said that there was any inordinate delay.
In the present case also, there was no period prescribed for allotment and in
any case, the flats in question were allotted within two years from the
issuance of the Brochure and there cannot be said to be any inordinate delay.
The High Court also has not given any finding that the final costing of the
flats concerned was wrong or unreasonable. The High Court has only held that
there is unreasonable delay in delivery of possession and hence, directed to
pay the interest @ 18% for the delayed period from the date of the allotment to
the date of the delivery of the possession.
The BDA Housing Scheme provides that no interest is payable on instalments
under Self Financing Scheme. However, the Scheme provides that if the amounts
payable to the BDA are not paid within the prescribed time limit, penal
interest at the rate of 18% per annum shall be payable along with payable
amounts. At the time of hearing, learned counsel made an appeal to the Court to
reduce the rate of interest from 18% to 6% on the ground that the allottees
under the Scheme in question belonged to Middle Income Group and, therefore,
they would not be in a position to pay the interest. In our view, once the
liability of the respondents to pay the balance amount remaining unpaid out of
the final cost of the flat is not struck down and remains in existence, the
appellant cannot be asked to forego the interest for the period, or any part
thereof, for which the said amounts remain unpaid. The High Court is not right
in creating double jeopardy for the BDA directing it to pay interest to the
respondents while at the same time to direct the respondents not to pay
interest on the unpaid amounts. However, taking note of the financial status of
the respondents and in the peculiar facts and circumstances of the case, we
direct the respondents to pay simple interest @ 9% on the enhanced price of the
flats. The enhanced price of the flats shall be paid in six monthly equal
instalments together with accrued interest payable on diminishing balance on or
before the 10th of every succeeding month commencing from April 2004. If the
respondents commit any two defaults in the payment of instalments on the
enhance price, the interest @ 18% shall be recovered from them by the BDA. The
amounts deposited by the respondents as per the interim order, if any, will be
given credit to. # According to the Brochure, the Housing Scheme is a Self
Financing Scheme wherein the allottees were to pay the cost of the flats in
quarterly instalments. The parties are bound by the terms of the contract in
regard to the payment of the original cost of the flats as per the agreement.
For the foregoing reasons, the present appeal filed by the BDA deserves to
be allowed. The judgment and order of the High Court dated 14.5.1996 in CMWP
No. 36735/95 is set aside. But however, we make no order as to costs. #