SUPREME COURT OF INDIA
National Aluminium Co. Ltd.
Vs.
Gerald Metals Sa
C.A.No.1427 of 2004
(N.Santosh Hegde and B. P. Singh JJ.)
27.02.2004
JUDGMENT
Santosh Hegde, J.
1. Heard learned counsel for the parties.
2. Leave granted.
3. This appeal arises out of a dispute between the parties to this appeal which
under an agreement between the parties has to be referred to arbitration as
contemplated under Clause 26 of the agreement between the parties.
4. Pending disposal of the said dispute by the arbitrators the respondent
herein moved an application under section 9(d) of the Arbitration and
Conciliation Act, 1996 praying for the grant of ex parte injunction
restraining the appellant herein from transferring or alienating the earmarked
alumina lying in the appellant's Silos in Vishakapatnam Port area to any party
other than the respondent herein.
5. The said application was opposed by the appellant herein on various legal
and factual grounds including the maintainability of the application as also
the jurisdiction of the trial court to make any interim order under the said
provision of the Act.
6. The trial court after hearing the parties however considered it appropriate
to make the following interim order:
"In the result, the application is allowed and the respondent shall allow
the despatch of cargo to the petitioner immediately on payment of original
price to the respondent, and on providing bank guarantee for the difference of
price agreed between the petitioner and the respondent and the price on which
Alumna is being sold in the international market at the latest, and the
security shall lie with the court and the party that wins in arbitral
proceedings shall take it after disposal of arbitral proceedings basing on the
direction given therein. The petitioner is ordered accordingly."
7. An appeal filed by the respondent against the said order of the trial court under section 37 of the 1996 Act before the High Court of Judicature Andhra Pradesh at Hyderabad came to be rejected. While doing so the High Court slightly modified the order of the trial court in the following terms:
"1) The Gerald Metals shall be permitted to lift 33,300 MT 5% of
Alumnia on payment of agreed rates,
2) That in addition to agreed rates, the Gerald Metals shall also give a bank
guarantee of an amount which is the difference between the agreed rate and the
rate of US $ 430 per MT of Alumina in favour of NALCO. The bank guarantee shall
be furnished before the Registrar (Judicial) of this Court to avoid delay in
the matter who shall transmit it to NALCO.
3) The bank guarantee shall be encashable by NALCO if they succeed in the
arbitration.
4) No order as to costs." *
8. In this appeal various grounds both legal and factual have been raised by
the parties to this appeal in their pleadings as well as the arguments
addressed on behalf of them.
9. We however on facts of this case think it unnecessary to go into those
questions of fact and law even for the purpose of deciding this interlocutory
application filed under section 9(3) of the Act which will ultimately be
subject to the award that may be made in the arbitration proceedings. However
we think it necessary that with a view to protect the interest of both the
parties to make some modifications in the impugned order. We do so because of
the fact that the claim of the respondent herein is yet to be decided by the
arbitrators. However we notice by the impugned order the courts below have
directed the compulsory sale of alumina which according to the appellant is
their property to the respondent which the appellant contends cannot be done at
an interlocutory stage because once their property is sold in the event of they
succeeding before the arbitrator restoration of the property will become
impossible. However we are not inclined to accept this argument because it is
the case of the appellant themselves that they were ready and willing to sell
the subject matter of dispute (the Alumina) for the best price in the market.
Therefore the sale of the said goods by itself would not in any manner cause
irreparable loss to the respondent. On the contrary, if the respondent is not
allowed to purchase the said goods there is a possibility of it suffering
comparatively a greater loss than that may be suffered by the appellant by
directing it to sell the goods to the respondent. We however feel since as of
today the appellant is the owner of the property if the respondent is
interested in purchasing the same then without prejudice to the contentions of
either party the appellant may be paid the value of the goods as was prevailing
on the relevant date. Actually this is the purport of the orders of the two
courts below by the said courts instead of directing payment of the market
value of the goods have only directed the payment for the contractual value of
the goods which is US $ 430 per MT. However the courts below have directed the
respondent to secure the difference in the value of the goods by directing the
respondent to furnish a bank guarantee. While doing so the High Court has fixed
the market value of the goods at US $ 430 and directed the respondent to
furnish a bank guarantee for the difference in the amount between the agreed
rate and the rate of US $ 430 per MT of the goods to be sold by the appellant
to the respondent as per the terms of the agreement.
10. Having heard the arguments of the parties we are of the considered opinion
if the respondent should be permitted to take possession of the goods at an
interim stage which the appellant claims it has no right to, we think the
appellant's interest should also be properly secured which can be done by
calling upon the respondent to pay to the appellant the value of Alumina which
takes possession from the respondent @ US $ 430 per MT before they take
possession of the said goods.
11. There is a serious dispute between the parties in regard to the actual
market value of the goods at the relevant date while the appellant contends
that the same is US $ 460.80 per MT. The respondent contends it is much less
than that since we in this appeal do not want to go into that disputed question
of fact and as an interim arrangement we direct the respondent to pay @ US $
430 per MT of the Alumina to be purchased by the respondents from the appellant
because that is the figure tentatively fixed by the High Court. We further
direct the respondent to furnish a bank guarantee for the balance amount of US
$ 31.80 per MT which the appellant claims to be the market value before taking
delivery of the goods in question.
12. The appellant will file an undertaking in this Court that in the event of
the arbitration award fixing a price less than what is fixed by us or making
the appellant liable to pay any sum that may become liable to pay, assuring
this Court to make due payment, the same shall be paid in terms of the award
within the time to be stipulated in the award if any, within 3 months from the
date of the award with interest, if so awarded.
13. With the above modifications this appeal is disposed of.