SUPREME COURT OF INDIA
Hardesh Ores Private Limited
Vs.
Timblo Minerals Private Limited
C.A.Nos.8586-8587 of 2003
(D.M.Dharmadhikari and Shivaraj V. Patil JJ.)
16.03.2004
JUDGMENT
D.M.Dharmadhikari, J.
1. The dispute in these appeals between the appellant as Iron Ore
raising/purchase contractor and the respondents who claim to have been duly
appointed as new contractors by the mine owner is regarding their rival claims
to exclusively run the Iron Ore mine which is the subject-matter of the suit
instituted by the new contractors.
2. The appellants company (shortly referred to as the old contractor) claims
right to run the mine on the basis of their alleged existent contract with the
mining-lease-owner. According to the appellant, the contract with them was
renewed by acceptance of their offer of renewal and consequent conduct of
permitting them to work the mine on periodical payments of price in accordance
with the original terms of the contract.
3. The case of the contesting respondent Nos. 1 & 2, who are plaintiffs
before the trial court (shortly referred to as the new contractors), is that
the mining-lease-owner has refused to renew the contract with the appellant and
has entered into a fresh contract on payment of higher price with them.
4. The trial court granted an ex parte temporary injunction in favour of the
new contractors. After hearing both the parties at length, the ex parte interim
injunction earlier granted under Order 39 Rules 1 & 2 of the Code of Civil
Procedure was vacated by the trial court.
5. Aggrieved by the order of the trial court refusing to confirm the order of
temporary injunction, the new contractors appealed to the High Court. The High
Court by its impugned order has allowed the appeal and in terms of the prayer
made by the new contractors, has granted temporary injunctions in their favour
without any conditions. The old contractor is, therefore, before us in these
appeals.
6. We have heard all the learned counsel appearing for the parties at great
length.
7. Learned senior counsel appearing for the appellant after referring to
various documents on record and strongly relying on the decision in Gardner
v. Blaxill1 contended that renewal of the contract can be
implied by conduct of the parties. It is further contract, the appellant was
running the mine and making payments for the extraction of the ore to the
mining-lease-owner. The new contractors by offering higher price to the owner
made a surreptitious attempt to take possession of the mine by seeking ex parte
injunction. The appellant had already filed a caveat in the trial court in
anticipation of filing of a suit against them and threat to their rights in the
mine. Ignoring the caveat, the trial court was misled into passing an ex parte
order of temporary injunction without any notice to the appellant. An ex parte
order of temporary injunction on ground of urgency by invoking proviso to Order
39 Rule 3 CPC was obtained when there existed none and in any case no emergent
circumstances confronted the plaintiffs as not to notice the opposite party and
grant opportunity of hearing to it. The trial court in the order grating ex
parte temporary injunction did not record reasons. Hence, the order suffered
incurable infirmity.
8. It is submitted that thus praising misrepresentation and deception, the new
contractors obtained on ex parte order of temporary injunction and being armed
with it, made forcible entry into the mine. The trial court, later on, vacated
the temporary injunction after hearing both the parties. The submission made on
behalf of the appellant is that as the new contractors could not have obtained
a contract in their favour during existence of a renewed contract in favour of
the old contractor, this Court should allow these appeals, vacate the order of
temporary injunction and restore the statute quo ante by permitting the
appellant to take possession of the mine for uninterrupted working.
9. On the other hand, learned counsel appearing for the mining lease owner and
the new contractors submitted that, in terms of the original contract, a
renewal could be made only in writing. Reliance is placed on Provash Chandra
Dalui & Anr. v. Bishwanth Banerjee & Anr. ) and State of U.P.
& Ors. v. Lalji Tandon (dead) Thr. Lrs. The contention advanced is that
after expiry of the term of the contract, under some ad hoc arrangements with
the owner, even if the old contractor might have made some extractions of ore
and paid price that cannot be held to be an act of renewal of the contract. The
mining lease owner by an express notice sent in writing has refuses to renew
and terminated the contract of the old contractor. Therafter, he has entered
into a written contract on higher price with the new contractors. The old
contractor, therefore, has no right in presenti to remain in possession of the
mine and to operate it. According to learned counsel for the new contractors,
there is no counter suit filed by the old contractor to specifically enforce
any alleged agreement of renewal of the contract and such relief cannot be
legally granted in view of the bar contained in clause (c) of sub-section (1)
of Section 154 of the Specific Relief Act which provides that a 'contract in
its nature determinable' is unenforceable.
10. The suit is pending for trial on merits. We would not, therefore, express
any opinion, one way or the other, on the merits of the contentions advanced.
On the basis of three establish principles for grant of temporary injunction
e.g., prima facie case, balance of convenience and irreparable loss, in our
considered, opinion, it woudl not be appropriate to interfere with the order of
the High Court at the present stage of th suit and disturb the working of the
mine by the new contractors who have already commenced operations from June
2003, and, as alleged, entered into business commitments for supply of iron ore
to different parties in and outside India.
11. After considering the comparative merit of the case of either parties and
their rival claims, we have formed an opinion that the High Court ought not to
have granted unconditional order of temporary injunction by ignoring the huge
investments which have been made by the old contractor to operate the mine
under an existing arrangement and alleged renewal of the contract by their
mutual conduct.
12. In the course of hearings, on behalf of the old contractor, learned counsel
has handed over to us in writing the proposed terms and conditions on which it
seeks restoration of possession of the mine and permission to operate the same.
The proposed terms suggested by the appellants have been opposed by the new
contractors and their response in writing has also been placed before us.
Taking tentatively the figures mentioned by the new and old contractors in
their proposed terms and responses submitted orally and in writing indicating
the extention of investments and estimated profits, we consider it appropriate
to modify the impugned order of grant of temporary injunction passed by the
High Court by imposing the following conditions :-
“(1) As a pre-condition for further operating the mine, the new contractors
shall furnish a Bank Grantee or a Solvent Security to the satisfaction of the
Trial Court in the sum of Rupees Five Crores toward the estimated investments
already made by the old contractor in the mine from the year 1984 in
prospecting, developing digging bore holes, removal of rejection, making
benches, putting up infrastructural facilities, acquiring surface rights, to
dump rejects, cost of shifting of school, electrification, research and
development etc. The Bank guarantee or solvent security, as the case may be, to
the satisfaction of the trial court shall be furnished within a period of four
weeks from today.
(2) The new contractors shall, by the end of every month, deposit in the trial
court a sum of Rupees 50/- per metric ton, on the basis of payment slips of
trucks and monthly returns submitted to the statutory mine authorities, on each
quantity of ore extracted and exported by them, in order to reimburse, in the
event of dismissal of the suit, the loss of estimated profit caused to the old
contractor.
(3) The amounts aforementioned to be deposited in respect of the quantities of
Ore extracted and exported shall be kept by the Trial Court, when deposited, in
fixed deposit in a nationalised Bank so that they earn current rate of
interest. The amounts shall be paid on final decision of the suit by the Trial
Court to the party held entitled to it.
(4) At the conclusion of the trail and decision of the suit, the trial Court
shall pass consequential orders for payment of the amount covered by the Bank
Guarantee or solvent security and the amounts periodically deposited for the
ore extracted and exported in the manner directed above.
(5) As admitted by the parties, the quantity of iron ore already extracted
during period of working by the old contractor is stacked at the site in the
mining area. Without going into the dispute of extent of quantity of iron ore
extracted and stacked at site and its value, we direct that the old contractor
shall be allowed to collect and transport the same in accordance with the then
existing terms of the written contract between the old contractor and the
mining-lease-owner. In collecting and transporting the aforementioned quantity
of iron ore, the old contractor shall follow not only the terms of the contract
but also all statutory provisions and rules regulating the extraction and
transportation of minerals. It shall also submit necessary statutory returns
and clear dues, if any, of statutory Authorities in accordance with law. In
order of allow the old contractor to take away the iron ore extracted by it and
stacked at the site, the trial court shall appoint a Commissioner to be
assisted by a statutory mining authority to supervise the work.”
13. Looking to the nature of the dispute, the rival claims and high stakes of
the parties involved in running the mine, we direct the Trial Court to expedite
the trial of the suit and to make all endeavour to decide the same early and in
any event before December 2004.
14. All legal grounds and contentions are left open to the parties to be urged
before the Trial Court. The trial court shall, on the basis of the evidence
produced before it, decide the suit in accordance with law and regardless of
any observations made by the trial court and the High Court in their orders
while disposing of the subject-matter of grant of temporary injunction.
15. The impugned order of the High Court is, thus, modified with the addition
of the conditions mentioned above. The appeals are partly allowed to the above
extent. The costs incurred by the parties shall abide the final result of the
suit.
11960 Indlaw QBD 13