(SUPREME COURT OF INDIA)
M.C. Mehta
Vs
Union of India and others
HON'BLE JUSTICE Y. K. SABHARWAL AND HON'BLE JUSTICE H. K. SEMA
18/03/2004
Interlocutory Application No. 1785 of 2001 (in Interlocutory Application No. 22
and Writ Petition (C) No. 4677 of 1985) (with I.A. Nos. 1806, 1815, 1817-18,
1819, 1822, 1823, 1824, 1825, 1794 and 1795 in I.A. No. 1785 in W.P.(C) Nos.
4677/85, 410/2002, I.A. Nos. 1832, 1835-36, 1838 and 1839-40 in I.A. No. 1785
in I.A. No. 22 in W.P.(C) Nos. 4677/85, 661, 428, 624/2002 and C.P. (C) No.
568/2002 in W.P.(C) No. 428 of 2002)
JUDGMENT
The Order of
the Court is as follows
Hon'ble Justice Y.K. Sabharwal
The main question to be examined in these matters is whether the mining
activity in area upto 5 kilometers from the Delhi-Haryana border on the Haryana
side of the ridge and also in the Aravalli hills causes environment degradation
and what directions are required to be issued. The background in which the
question has come up for consideration may first be noticed.
2. The Haryana Pollution Control Board (HPCB) was directed by orders of this
Court dated 20th November, 1995 to inspect and ascertain the impact of mining
operation on the Badkal Lake a Surajkund - ecologically sensitive area falling
within the State of Haryana. In the report that was submitted, it was stated
that explosives are being used for rock blasting for the purpose of mining;
unscientific mining operation was resulting in lying of overburden materials
(topsoil and murum remain) haphazardly, and deep mining for extracting silica
sand lumps is causing ecological disaster as these mines lie un-reclaimed and
abandoned. It was, inter alia, recommended that the Environmental Management
Plan (EMP) should be prepared by mine lease holders for their mines and actual
mining operation made operative after obtaining approval from the State
Departments of Environment or HPCB; the EMP should be implemented following a
time bound action plan; land reclamation and afforestation programmes shall
also be included in the EMP and must be implemented strictly by the
implementing authorities. The report recommended stoppage of mining activities
within a radius of 5 kms. from Badkal Lake and Surajkund (tourist place). The
Haryana Government, on the basis of the recommendations made in the report,
stopped mining operations within the radius of 5 kms of Badkal Lake and
Surajkund.
3. The mine operators raised objections to the recommendations of stoppage of
mining operations. According to them, pollution, if any, that was generated by
the mining activities cannot go beyond a distance of 1 km. and the stoppage was
wholly unjustified.
NEERI Report and earlier directions
4. By order dated April 12, 1996, the Court sought the expert opinion of
National Environmental Engineering Research Institute (NEERI) on the point
whether the mining operations in the said area are to be stopped in the
interest of environmental protection, pollution control and tourism development
and, if so, whether the limit should be 5 kms. or less. NEERI in its inspection
report dated 20th April, 1996, inter alia, recommended that:
"6.1 Mining (1) Detailed exploratory operations need to be undertaken to
facilitate the estimation of reserves in the region, and for scientific
management of mining operations.
(2) The mine lease-owners need to undertake the mining operations in series,
i.e. mining activities must be completed to full potential in a block before
moving to the next. This will help in reclamation of land in the block in which
mining operations have been completed.
(10) The Environmental Management Plans (EMP) being formulated by the
mine-owners should include land rejuvenation and afforestation programmes and
other measures necessary to protect the quality of the environment and human
health. The mining operations should commence only after the approval of EMPs
by a designated authority. A time-bound action plan needs to be initiated for
the implementation of the measures delineated in the Environmental Management
Plans.
(11) & (12) ....
(13) The question of lifting the ban on mining operations needs to be
considered in conjunction with the implementation of stringent pollution
control; land reclamation, green belt, and other Environmental Management
measures so as to facilitate the availability of construction materials and
employment opportunities for the workers along with the protection of
environment and public health.
(14) It is considered necessary to prepare a Regional Environmental Management
Plan for urgent implementation to enable eco-friendly regional development in
the area." *
5. On consideration of the reports, this Court came to the conclusion that the
mining activities in the vicinity of tourist resorts are bound to cast serious
impact on the local ecology. The mining brings extensive alteration in the
natural land profile of the area. Mined pits and unattended dumps of
overburdened left behind during the mining operations are the irreversible
consequences of the mining operations and rock blasting, movement of heavy
vehicles, movements and operations of mining equipment and machinery cause
considerable pollution in the shape of noise and vibration. The ambient air in
the mining area gets highly polluted by the oust generated by the blasting
operations, vehicular movement, loading/unloading /transportation and the
exhaust gases from equipment and machinery used in the mining operations. It
was directed that in order to preserve environment and control pollution within
the vicinity of two tourist resorts, it is necessary to stop mining activity
within 2 kms. radius of the tourist resorts of Badkal Lake and Surajkund. The
Court further directed the Director, HPCB to enforce all the recommendations of
NEERI contained in para 6.1 of its report so far as the mining operations in
the State of Haryana are concerned. Further, it was directed that failing to
comply with the recommendations may result in the closure of the mining operations
and that the mining leases within the area from 2 kms. to 5 kms. radius shall
not be renewed without obtaining prior no objection certificate from the HPCB
as also from the Central Pollution Control Board (CPCB). Unless both the Boards
grant no objection certificate, the mining leases in the said area shall not be
renewed. (MC. Mehta vs. Union of India and others 2).
Present Issues
8. The aspects to be examined include the compliance of the conditions imposed
by the Pollution Boards while granting no objection certificate for mining and
also compliance of various statutory provisions and notifications as also
obtaining of the requisite clearances and permissions from the concerned
authorities before starting the mining operations.
7. In matters under consideration, the areas of mining fall within the
districts of Faridabad and Gurgaon in the Haryana State.
8. I.A. No. 1785/01 has been filed by the Delhi Ridge Management Board praying
that the Government of Haryana be directed to stop all mining activities and
pumping of ground water in from area upto 5 kms from Delhi-Haryana border in
the Haryana side of the Ridge, inter alia, stating that in the larger interest
of maintaining the ecological balance of the environmental and protecting the
Asola Bhatti Wildlife Sanctuary and the ridge located in Delhi and adjoining
Haryana, it is necessary to stop mining. In the application, it has been
averred that the Asola Bhatti Wildlife Sanctuary is located on the southern
ridge which is one of the oldest mountain ranges of the world and represents
the bio-geographical outer layer of the Aravalli mountain range which is one of
the most protected areas in the country. The sanctuary is significant as it is
instrumental in protecting the green lung of National Capital of Delhi and acts
as a carbon sink for the industrial and vehicular emissions of the country's
capital which is witnessing rapid growth in its pollution level each year. The
ridge, it is averred, is a potential shelter belt against advancing
desertification and has been notified a wildlife sanctuary and reserve forest
by the Government of National Capital Territory of Delhi. Regarding the mining
activities, it is averred that for extraction of Badarpur (Silica sand), there
is large scale mining activity on the Haryana side just adjacent to the
wildlife sanctuary of the ridge which activities threaten the sanctuaries
habitat and also pumping of large quantity of ground water from mining pits. It
was also stated that the ground water level was being depleted as a result of
the mining activity. Further, the query dust that comes out of mining pits is a
serious health hazard for human population living nearby and also the wild
animals inhabiting the sanctuary pointing out that the mining and extraction of
ground water had been banned in National Capital Territory of Delhi and the
ridge being protected as per the order of this Court, it is necessary, that the
ridge on the Haryana side is also protected - that being the extension of the
range, and, therefore, mining, withdrawal of ground water and destruction of
flora, etc. should also be restricted outside Delhi or at least upto 5 kms.
from Delhi-Haryana border towards Haryana.
9. On 6th May, 2002, this Court directed the Chief Secretary, Government of
Haryana to stop, within 48, hours, all mining activities and pumping of ground
water in and from an area upto 5kms. from Delhi-Haryana border in the Haryana
side of the ridge and also in the Aravalli Hills. The question to be considered
is whether the order shall be made absolute or vacated or modified.
10. Our examination of the issues is confined to the effect on ecology of the
mining activity carried on within an area of 5 kms. of Delhi-Haryana Border on
Haryana side in areas falling within the district of Faridabad and Gurgaon and
in Aravalli Hills within Gurgaon District. The question is whether the mining
activity deserves to be absolutely banned or permitted on compliance of
stringent conditions and by monitoring it to prevent the environmental
pollution.
EPCA Visits
11. In terms of the order passed by this Court on 22nd July, 2002,
Environmental Pollution Central Authority (EPCA) was directed to give a report
with regard to environmental in the area preferably after a personal visit to
the area in question without any advance notice. It may be noted that EPCA was
constituted by the Government of India under notification dated 29th January,
1998 issued in exercise of power under Section 3(1) & (3) of the
Environmental (Protection) Act, 1986 (for short, 'the EP Act') Mr. Bhure Lal
was appointed its Chairman. The EPCA was constituted with a view to protect and
improve the quality of environment and preventing, controlling and abetting
environmental pollution. EPCA has also the power to deal with environmental
issues pertaining to National Capital Region which may be referred to it by the
Central Government. The EPCA has jurisdiction over the National Capital Region
as defined in clause (f) of Section 2 of the National
Capital Region Planning Board Act, 1985. The Districts of Gurgaon and
Faridabad are part of the National Capital Region, under Section 2(f) read with
the Schedule of the said Act.
12. The Chairman of the CPCB is a convenor member of EPCA. EPCA made a surprise
visit to the area to see the mining sites. The mining sites visited are located
in the village of Anangpur, Pali, Mohabatabad and Mangar, which fall within the
notified area of 5 km radius from the Delhi border in the Faridabad district.
EPCA also visited mining sites that are located outside the notified zone in
Kot area, EPCA also held consultation with the officials of the Central
Groundwater Board and obtained their opinion on this matter. On August 7, 2002,
members of the EPCA visited the mining sites located within five km radius from
Delhi border. The objectives of the visit, as per EPCA were as follows:
1. Assessment of the level of compliance with the conditions laid down in the
regulatory procedures like the No Objection Certificate (NOC) granted by
authorities to the mine owners;
2. Evidence of land and habitat degradation in and around the mining sites;
3. Evidence of misuse and shortage of ground water in the area;
4. Assessment of the implication of such activities for the local ecology and
drinking water sources in the area.
13. During the visit, prima facie, EPCA found evidence of clear violation of
some of the key conditions of order of this court dated May 10, 1996.
EPCA Ist Report and Recommendations
14. The EPCA gave its report dated 9th August, 2002. It would be useful to reproduce
the said report in extenso as under:
'Anangpur area and its vicinity : EPCA inspected the mining sites owned by
Mohan Ram and Company as well as at least 5 other mining sites in this area,
which EPCA is not clear who owns.
At the time of visit there was no mining taking place. So EPCA members assessed
level of compliance with some of the key conditions laid down in the NOCs.
There was clear evidence of violation of the following condition.
i. The excavated pits should be filled with fly ash or municipal solid waste in
the bottom layers. The top soil should be used as a top layer while filling the
pit. Land reclamation and tree plantation should be done in a planned manner
over the reclaimed mine pits. *
ii. The applicant shall not discharge any effluent or groundwater outside
their lease premises and shall take appropriate measures for rainwater
harvesting and reuse of water so as not to affect adversely the ground water
table of the area. No mining operation shall be carried out in the water table
area.
iii. The green belt proposed in the environmental management plan around the
proposed mining lease area and along the road side shall be developed.
The most serious violation noticed by the EPCA was the continuation of mining
even after reaching the ground water level which has been disallowed by the
regulatory agencies. Photographs taken by EPCA, which show deep mining pits
have turned into large lakes of ground water. In this mining lease area EPCA
members saw extensive and deep water bodies. The water was blue, indicating
that this was groundwater and not surface water runoff collected in the pits.
Even more serious violation noticed was configuration of water pipes laid out
to draw water out of the pits to throw them over hills and let the water flow
out. This is a grave misuse of precious ground water in an area where ground
water is the only source of water for the local population - both urban and
rural.
EPCA members talked to local villagers who complained that water table in the
area has gone down over a period of time and that the village is facing water
shortage. While earlier ground water could be tracked at the depth of 30-35 ft.
now deep bore wells have been dug to get drinking water, in addition, noise and
dust pollution from the mining sites area problem.
Goodwill mine in Pali Village: EPCA found similar violation of conditions and
evidence of mining sites reaching the level of ground water in deep pits and
pipes fitted to drain out water here as well.
During the long drive to various mining sites, EPCA could not see any credible
sign of green belt along the roads. Moreover, one important condition of NOCs
is that 'safe distance should be maintained from the road to overburden dumps
and the mine pits in accordance with the directions / notifications of the
department of environmental, Haryana and bureau of mines". But EPCA
noticed mining sites very close to the roads and also very close to the
ecologically sensitive area of Asola sanctuary near the Goodwill mines. *
Stone crushing sites in Pali : EPCA has inspected the stone crushing sites
in the area. All sites had a lot of material and trucks being loaded. It is
difficult to establish if these are the left over material from the past or
were products from banned sites or from sites from outside the notified area.
EPCA was informed that after the Hon'ble Supreme Court directive of May 2002,
the stone crushers were not being operated, except between the hours of 5 am to
9 am. EPCA was, therefore, unable to verify the working conditions of these
crushers. But it did not find any evidence of afforestation as stipulated by
the NEERI directive or any evidence of dust minimizing equipment.
Mining around Mangar Village. Again the same situation was found around
Anangpur. The villagers interviewed here were caught between the devastation of
the mines, desperate shortage of drinking water and the only livelihood option
that these manual stone quarries provided.
Legal mining in Kot area: As mining is banned along the 5 km radius from the
Delhi border, EPCA also visited some mines that the outside the notified area
to ascertain the state of the environment. In this area, surface mining is
being done and not deep mining. Therefore, as yet, the groundwater reserves are
not being touched in this region. The entire area was like a giant dust field.
We saw no evidence of any afforestation or even dust minimising efforts being
undertaken in the areas that are being mined. We did see one tanker of water,
which was sprinkling the roads, unable to stop the dust from swirling. EPCA
could not see any protection for the workers from dust. As this area will
clearly emerge as a major mining in the future, it is important that the mining
area is properly demarcated and environment management plan implemented to
enable scientific mining to minimize degradation of the environment.
Faridabad-Gurgaon Road: EPCA saw mining alongside the road. Though the mines
were closed because of the Hon'ble Court directive, EPCA saw vast pits and
mining activity in this area. This is the road for the proposed bypass from
Delhi. *
3. The present laws and regulations in the area
We have assessed the current applicable laws and regulations in the area, which
govern land use and mining so as to understand what efforts have been made by
different agencies to ensure compliance.
* In may 1992, parts of the Aravalli range were declared ecologically sensitive
under the Environment (Protection) Act. Under this notification, certain
activities - including all new mining operations, including renewals of mining
leases - are restricted and permission has to be sought from the Ministry of
Environment and Forests. This notification is valid for reserved forests in the
districts of Gurgaon in Haryana and Alwar in Rajasthan.
* In August 1992, the Forest Department of Haryana had issued a notification
under the Punjab Land Preservation Act, 1900, banning the clearing and breaking
up the land not under cultivation, quarrying of stone.... in the Badkal area
without prior permission of the forest department. This ban was for 30 years.
Earlier it had already issued a similar notification for the Pali area for 25
years.
* In 1996, the Hon'ble Supreme Court banned all mining activity within 2 kms of
the Badkal and Surajkund tourist resorts.
* In the same order, it ordered that mining leases within the area from 2 km to
5 km radius shall not be renewed without obtaining no-objection certificated
from the Haryana Pollution Control Board as also the Central Pollution Control
Board (CPCB). It stipulated that 'unless both the boards grant no objection
certificate, the mining leases in the said area shall not be renewed."
* Mining in the 2-5 kms was allowed under condition that there would be strict
adherence to the environmental management plan laid down by the NEERI. It has
to be noted here that the CPCB had in its report to the Hon'ble Court in 1996
stated that the 'deep mining for silica is causing an ecological disaster'.
CPCB has recommended that mining activity 'should be stopped within a radius of
5 kms from Badkal and Surajkund. The subsequent report of NEERI dated
20.4.1996, recommended green belt at 1 km radius all around the boundaries of
the two takes. On this basis, the Hon'ble Court directed that radius be
extended to 2 kms for a green belt and to cushion the impacts of air and noise
pollution. *
* The Hon'ble Court in its order asked the agencies to ensure enforcement of
the recommendations of NEERI. It directed that 'failure to comply with the
recommendations may result in the closure of the mining operations."
4. Compliance and enforcement : absent and missing.
To discuss the future strategy for this area, it would be important to assess
the track-record of the different agencies in ensuring that the previous orders
and directives are enforced and complied with.
1. No mining within 2 kms of Badkal and Surajkund: Probably enforced. But
difficult to assess as the area is hilly.
2. Mining within 2-5 kms should get permission from Haryana Pollution Control
Board and CPCB. The CPCB has issued 2 NOCs, dated December 20, 2001 and May 6,
2002. No further record has been found of NOCs given for mining in this area.
EPCA has not been able to find the NOCs granted by the Haryana Pollution
Control Board.
Compliance with the environmental management plans recommended by NEERI as
directed by the Hon'ble Supreme Court.
*
S.No.
Directive
Enforced or not
1.
200 mts wide green belt along Surajkund and Badkal
Shrubs and wild growth. No real evidence of good afforestation.
2.
100 mts wide green belt outside mining lease boundary
Definitely not done. EPCA did not see afforestation, except for some recent plantation of dying and dead trees in one or two places. The sign boards were more prominent than the trees they were supposed to show.
3.
100 mts. open peripheral area around stone crusher zone with green belt.
Not done.
4.
Green belt on either side of the road between Surajkund and Badkal
We saw large scale construction on this road - from schools to management colleges and housing colonies.
5.
Mining should commence only after the environmental
There is no evidence of an environmental management plan being adhered to in this region.
Adherence to the conditions of the No-objection Certificate granted by CPCB
for mining
*
S. No.
Directive
Enforced or not
1.
Mining to be done with approved mining plan
No evidence
2.
Excavated pit to be filled by fly ash or municipal solid waste in the bottom layers. Overburden should be used in the middle layer. Top soil on top layer and afforestation, layer and afforestation.
EPCA saw no evidence that this recommendation had even been attempted to be followed. All abandoned mines were left open and degraded The entire region was pockmarked with deep and overburdens.
3.
No discharge of effluent or groundwater outside lease premises. Must take measures for rain water harvesting and reuse of water so as not to affect the groundwater table in the areas. No mining operations shall be carried out in the water table area.
Not done. Gross violation. See section on water for details.
4.
Ambient air quality standards to be complied with.
No evidence. Mine was closed.
5.
Noise level at the boundary shall conform with noise standards
No evidence. Mine was closed.
6.
Green belt around lease area and roadside
Not done.
7.
Clearance of groundwater board for the usage of the groundwater will be obtained, for the conservation of groundwater and to ascertain that there will be no impacts on the groundwater table of the area.
No evidence. Groundwater board has not given any clearance that we could ascertain.
From the above it is clear that little or nothing has been done to seriously
with the directives of the Hon'ble Supreme Court as well as to enforce the
regulations and conditions laid down by the authorities for environmental
management of the mining areas.
5. Impact on groundwater reserves.
It has been argued by the Government of Haryana in its IA no. 1785 of 2001 that
the expert committee constitute by it under the Chairmanship of the principal
conservator of forests has submitted that there is a water divide between the
two boundaries of the two states which prevents the flow of water from Delhi
side to Haryana side. It has, therefore, argued that the mining on the Haryana
side is not affecting the water balance in the Delhi side of the ridge. It has
further said that only in four pits the groundwater was pumped regularly and in
two pits occasionally. Therefore, it has argued that little or no impact on
groundwater reserves is possible. *
5.1 Groundwater Board
EPCA requested the Central Ground Water Board (CGWB) for its opinion. The Board
has based its recommendations on the data available with it as well as a field
survey.
The key issues are.
1. On the issue of the ridge providing a water divide between the two states,
the CGWB has maintained that while the surface water divide follows the
Delhi-Haryana border, except in the catchment of Bhuria Nala, 'the surface
water divide may not be the groundwater divide in the strict sense due to
secondary porosity and also flat topped nature of the hills'. It also states
that the Aravalli hills are highly fractured, jointed and weathered making the
major recharge zone for the surrounding areas.
2. On the impact of the groundwater reserves due to mining, the Board has found
that its observation wells have shown an increase in groundwater levels in
Anangpur, Mangar, after the mining has been stopped in May. Therefore, in spite
of monsoon failure and continued abstraction of water, the observation wells
have noted increased water levels just 2 months of the mining being closed.
The groundwater levels in a tube well mentioned in Mewla Maharajpur during mid
July and first week of August showed a rise of 0.18 metres, A higher rise -
0.71 to 0.78 metres was observed in the two tube wells near the Manger mines
and Pali mines in the two months since the mines were closed. This clearly
points to the impact of mining on groundwater reserves.
This fact was also confirmed in the interviews done by EPCA at site.
3. CGWB also notes that contrary to what has been claimed, the mine water is
not being pumped into abandoned pits to recharge the groundwater. Instead the
groundwater pumped is discharged into the surrounding nalas, leading to
'wastage' of groundwater. For instance, in the case of Anangpur mines, the
water was pumped into the Bhuria Nala and in the case of Pali, the groundwater
was discharged into a nala to the Badkal lake and from Manger mine towards
Dhauj lake causing 'enormous losses to groundwater resources of the area".
The mind water is also full of silt, which reduces recharge as well. *
4. Furthermore, CGWB notes that the large surface lakes in the mines are
leading to huge losses of groundwater through evaporation.
5. The Central Ground Water Authority (CGWA) has notified these areas - South
district of NCT Delhi, Faridabad , Ballabhgarh Municipal Corporation area ,
Gurgaon town as water stressed areas and has put regulatory measures on ground
water development in these areas.
Given all this, CGWB concludes that the 'dewartering of mines in the Aravalli
hills has affected groundwater regimes of the mine area as well as buffer zone
resulting in the depletion of ground water resources."
5.2 Compliance with groundwater related regulations
The NOC given by the Central Pollution Control Board, includes an explicit
condition regarding ground water:
That the mine owner will ensure that there is no discharge of effluent of
ground water outside lease premises. They must take measures for rain water
harvesting and reuse of water so as not to affect the groundwater table in the
areas. Most importantly, it stipulates that no mining operations shall be
carried out in the water table area.
This condition has been grossly violated. Even the Haryana government's
affidavit in court accepts that pumping of ground water is taking place, though
it attempts to soften the issue by arguing that it is only being done in a few
cases.
Under this condition, mining is not allowed in the water table area. EPCA saw
deep and extensive pits of mines with vast water bodies. EPCA also saw evidence
of pumps and pipes being used to drain out the ground water so that mining
could continue. Therefore, the miners are mining for silica, but also in the
process, mining and destroying the ground water reserves of the areas.
In times of such water stress and desperation, this water mining is nothing
less than a gross act of wastage of a key resource. This time the stress has
been further aggravated by the failure of monsoon. Notices have been issued in
the nearby housing colonies stating that fall in groundwater table due to lack
of rains is responsible for water shortage in the area this season. This only
indicates how important it is to conserve ground water in the region for long
term sustainability of drinking water sources. Ground water is the only source
of drinking water here." *
15. On the basis of study and visit as well as the report of the Central Ground
Water Board, EPCA made the following recommendations: -
"1. The ban on the mining activities and pumping of ground water in and
from an area upto 5 kms. from the Delhi-Haryana border in the Haryana side of
the ridge and also in the Aravalli Hill must be maintained.
2. Not only must further degradation be halted but, all efforts must be made to
ensure that the local economy is rejuvenated, with the use of plantations and
local water harvesting based opportunities. It is indeed sad to note the plight
of people living in these hills who are caught between losing their water
dependent livelihood and between losing their only desperate livelihood to
break stones in the quarries. It is essential that the Government of Haryana
seriously implements programmes to enhance the land based livelihood of people
- agriculture, animal care and forestry. Local people must not be thrown into
making false choices, which may secure their present but will destroy their
future. Already, all the villages visited by EPCA complained of dire and
desperate shortages of drinking water. Woman talked about long queues before
the taps to collect water. Clearly, water resources of the region are critical
inputs to development and cannot be wasted and destroyed like this. The state
government must come up with strategies to involve local communities in the
future development of this region.
We have been given to understand that under the mining lease, 10 per cent of
the royalty is to be given to local villagers. We have also understood that the
turnover is of the mining operations in this area is substantial - between Rs.
50 lakhs to Rs. 1 crore a day were the gross estimates provided to us. However,
we do not have any estimate of the money that has been given to villagers from
this revenue. But there was little evidence in these poor and destitute
villages that any effort had been made to share the proceeds with them.
3. The Central Ground Water Board must be consulted urgently about what should
be done with the huge standing water in the area. This is a valuable national
resource and the Board should be asked if the water is best conserved by
covering it to stop evaporation or should it be used for recharge and storage
with further water harvesting efforts. *
4. The Ministry of Environment and Forests (MOEF) should be asked to extend
the notification under the Environment (Protection) Act to the Faridabad part
of the Aravalli and ridge as well. Currently, the notification is only for
Gurgaon district. This notification declaring it an ecologically sensitive area
will help to regulate the activities in this region.
5. It is not clear to us if adequate planning for water is being done in the
large scale construction activities being undertaken in this area. This aspect
is outside the purview of this report but needs to be examined carefully.
6. It must also be noted that Gurgaon-Faridabad road is being proposed as the
major bypass for the city of Delhi. The Hon'ble Court will note its directives
on the air pollution case in this regard. It has been said to the court in that
matter that the Government of Haryana is intending to widen the road and bids
have been issued to this effect. Therefore, it is all the more important that
the mining activity along the road must not be allowed. The 5 kms. ban from the
border of Delhi will take care of this requirement.
7. EPCA would also recommend that the mining area outside the 5 kms. area must
be demarcated and regulated. In this context. EPCA would like to draw the
attention of the court to the violations and gross disregard for regulations
found in the present mines. It is not out of place to mention that these mines
are owned by very powerful and highly placed individuals in the establishment.
In a related case the High Court of Punjab and Haryana has directed on
20.4.2001 a CBI enquiry on the basis of a public interest litigation filed by a
journalist. In its order the Hon'ble Court maintained that its examination had
found evidence that illegal mining operations are going on in the area. The
Hon'ble Court also noted the bias of the State Government to shield the
offenders and has said that because there is prima facie evidence of the
involvement of a 'person who holds the high position of the cabinet minister in
the state', the enquiry should be done by CBI. This enquiry is still ongoing. *
During the examination of the case, EPCA was told of other persons involved
in the mining activity who are highly influential and part of the ruling
political parties in the state and Centre.
In this respect, EPCA would recommended that tighter and constant monitoring of
the area must be done by a Central Government agency. To increase
accountability, EPCA would also recommended that the environment management
plan (EMP) for the mining area as well as the conditions of the NOC should be
made a public document. All other subsequent monitoring reports of this region
must be available publicly, preferably on the website of the monitoring
agency."
*
16. With the report, a note given by the Chairmen, Central Ground Water Board
on impact of pumping of ground water from mines and ground water regime in
mining area and its buffer zone in Aravalli hills of NCT Delhi, Faridabad and
Gurgaon Districts of Haryana was also annexed. The said note reads as under:
Based on available data with Central Ground Water Board and a quick survey
in and around mining area in Aravalli hills, following observations are made:--
"1. The area under consideration forms part of Aravalli range from where
mining of silica sand and other construction material was being carried out.
The mining of silica sand was mainly carried out below water table by
dewatering the mines whereas mining for other construction material is carried
out above water table. The major mining areas are Anangpur, Pali, Manger and
Mohabbatabad.
2. The surface water divide in the area approximately follows Delhi-Haryana
boarder except the catchment of Bhuria Nala flowing in Haryana State, which
extends in Asola area of Delhi State also. The formations in the Aravalli hills
are highly fractured, jointed and weathered making it the major recharge zone
for the surrounding areas. The surface water divide may not be ground water
divide in strict sense due to secondary porosity and also flat-topped nature of
the hills.
3. The pumping of ground water during mining of Silica sand affects ground
water regime of surrounding area. During the field visit, it was reported by
local people that during the dewatering of mines there was decline in ground
water levels and reduction in discharge in surrounding wells whereas after
stoppage of pumping the rise in water levels and increase in discharge has been
reported. In few observation wells on down stream side of mines rise in ground
water levels has been observed in Anangpur, Manger and villages after stoppage
of abstraction of ground water from deep mines. The ground water levels in a
tube well monitored in Mewla Maharajpur during mid July 2002 and first week of
August 2002 were 24.39 and 24.57 m. below ground level respectively, showing a
rise of 0.18m. Ground water levels in tube well located at temple near Manger
mine in second week of July 2002 and first week of August, 2002 were 51.70 and
49.99. m. below ground level respectively showing a rise of 0.71 m. Similarly,
ground water level in a tube well at Indernagar in Delhi area near Pali mine in
third week of June 2002 and first week of August 2002 were 59.68 and 58.90 m.
below ground level respectively showing a rise of 0.78 m. The stoppage of
dewatering of mines has resulted in rise of ground water levels in surrounding
areas. *
4. It has been observed that drainage pattern of the area has been modified
due to haphazard mining and dumping of waste material which has bearing on
natural path of ground water flow in the area.
5. It is claimed that abandoned pits act as recharge pits and in some cases the
pumped ground water it put in these pits so there may not be substantial
modification in the conditions of ground water regime. All the ground water
pumped out from Anangpur mine has not been put has not been put into abandoned
adjoining pits resulting in wastage of ground water by discharge into Bhuria
Nala. Observation have indicated that Bhuria Nala which was ephemeral stream
became a perennial stream during mining operations and now flow has stopped
after closure of mining activity. Similarly, pumped out ground water from Pali
mine was being discharged in a easterly flowing nala to Badkal Lane and from
Manger mine in a south westerly flowing nala towards Dhauj lake causing
enormous losses to ground water resources of the area. Further, the pumped out
water cannot be recharged effectively due to its high silt content. In silica
sand mines the water table has been intersected and in presently exposed to the
atmosphere causing huge losses to ground water through evaporation.
6. Studies conducted by Central Ground Water Board have revealed that water
levels in Faridabad new town which falls in buffer zone of mine area have
declined by 1.44 m/year. The decline of ground water level in the towns has
been attributed to over development of ground water for domestic and industrial
uses which is totally dependent on ground water. The pumping out of ground
water for mining of silica sand in recharge zone might have aggravated the
declining trend of ground water levels which otherwise would have contributed
to the buffer zone.
7. Central Ground Water Authority has notified South district of NCT Delhi and
Faridabad and Ballabhgarh Municipal Corporation area and Gurgaon town and
adjoining industrial area in August 2000, October 1998 and December 2000
respectively mainly on consideration of over development of ground water
resources resulting in substantial decline in ground water levels. Regulatory
measures on ground water development have been imposed in these areas. *
8. Therefore, it is observed that dewatering of mines in Aravalli hills has
affected ground water regime of the mine area as well as buffer zone resulting
in depletion of ground water resources." *
17. When the aforesaid report came up for consideration, some of the mines
owners submitted that their mines had not been inspected by Bhure Lal
Committee. Particulars of the mines that were stated to have not been inspected
were filed on 23rd September, 2002. Bhure Lal Committee was requested to carry
out the inspection of the said areas / mines. The Committee was also permitted
to associate such other organizations or persons as it may deem fit and proper
for the purpose of inspection.
EPCA 2nd Report and Recommendations
18. In terms of the aforesaid order, 26 mines were inspected and report dated
21st October, 2002 was submitted. The observations made as a request of
inspection in regard to each mine are as follows:
"The numbers indicated in parenthesis are serial number of mines given
in the list of mines furnished by Kailash Vasudev, senior advocate to the
Hon'ble Supreme Court that was forwarded to EPCA.
1. (no.9)
Name of Mine/ Area: New Anangpur Silica Sand Mines M/s. S.P. Sethi,
Location : Village New Anangpur, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity : 186.52 hec.
Mineral Extracted : Silica Sand Mines
Status of Mining : Above groundwater level
Whether groundwater is extracted: No.
Status of environmental clearances : No clearance given. No environmental
management plan.
This mine is located very close to the Delhi border (in close proximity) to the
Asola sanctuary). EPCA members were shown two pits , which were not being
worked currently . There was no groundwater exploitation seen in these pits.
Only brown stagnant rain water was seen. But what was very clear was that this mining
lease was adjoining the boundary of Delhi. Only recent plantation of sapling
was noticed along the path.
2. (13)
Name of Mine/Area: Anangpur Silica Sand Mines M/s. Mohan Ram and Co. *
Location : Village Anangpur, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity : 175.00 Hec.
Mineral Extracted : Silica Sand Mines.
Status of Mining : Below groundwater level
Whether ground water is extracted: yes
Status of environmental clearances: NOC granted by state pollution control
board for renewal of lease in 1999. No environmental management plan.
This mine has large pits where sand and silica was being extracted. This was a
working mine and had large amount of water in the two pits. EPCA members also
saw a pipe, which was currently unused, meant for pumping out the water from
the pits. The pits were at least 100-150 feet deep and the groundwater had been
clearly exploited for some time. Large amount of overburden were also seen in
the area.
3. (12)
Name of Mine/Area: Anangpur Silica sand mines, M/s. S.P. Sethi, Anangpur.
Location: Village Anangpur Distt. Faridabad.
Total Area of Land on lease / Actual area under mining activity: 489.34 hec.
Mineral Extracted: Silica sand, China, clay, ordinary sand, stone road material
(RM) and masonry stone (MS)
Status of Mining: Below groundwater table
Whether ground water is extracted: Yes.
Status of environmental clearances: No clearance given. No environmental
management plan.
The mining pit here has tuned into a huge groundwater lake, Groundwater is
fully exposed. Extensive overburden could be seen near the pits. It was very
evident that no major efforts were made to create plantation in the area. Some
new and young saplings could be seen along side the paths leading to the pits.
Clearly these were planted very recently.
4. (8)
Name of Mine/Area: Anangpur Silica sand mines, M/s. Rajdhani Minerals
Corporation.
Location : Village Anangpur Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity. 188.47 hec
Mineral Extracted: Silica sand, China clay, ordinary sand, stone RM and MS
Status: seen on closed pit. Did not see any water.
Status of environmental clearances: NOC granted by State Pollution Control
Board. *
4. (7)
Name of Mine/Area: Mewla maharajpur Silica sand mines, M/s. K.C. Ahuja &
Co.
Location: Village Mewla Maharajpur Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity. 162.905 hec.
Mineral Extracted : Silica sand, China clay, ordinary sand, stone road material
(RM) and masonry stone (MS)
Status: surface mining from the rocks
Whether ground water is extracted: No.
Status of environmental clearances: No clearance given. No environmental
management plan.
One pit seen, Mostly stone being quarried. Some water seen. No evidence of tree
plantation seen in the area. But mine pits are adjoining road.
6. (19)
Name of Mine/Area: M/s. Ramkrishna Purni Devi
Location: Village Badkal Distt. Faridabad.
Total Area of Land on lease / Actual area under mining activity : 369.4 hec.
(of this 121 hec. Falls within 2 km of Badkal Tourist Complex where mining has
been banned)
Mineral Extracted : Silica sand, ordinary sand, road metal, masonry stone and
minor mineral
Status: mining above groundwater table
Whether ground water is extracted: No.
Status of environmental clearances: No clearance given. No environmental
management plan.
EPCA members saw one pit located next to the border of Delhi. The mining area
is hard rock and the pit was being worked for stone. The mining site was at the
boundary of Delhi and the Asola sanctuary was seen at a close distance. This
mine is also adjoining the road.
7. (2)
Name of Mine/Area: Mohan Ram & Co. Proprietor Kartar Singh.
Location : Village Pali Distt. Faridabad.
Mineral extracted: Ordinary stone, road metal, masonry stone
Under litigation in High Court of Delhi.
8. (11)
Name of Mine/Area; Pali Silica Sand Mines, M/s. Goodwill Mineral Corporation.
Location : Village Pali, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity : 50.5 hec.
Mineral Extracted : Silica sand, China clay, sand
Status of Mining: Below water table.
Whether ground water is extracted: Yes.
Status of environmental clearances: NOC granted by State Pollution Control
Board in 1999 for renewal of lease. Asked to comply with conditions laid down
by CPCB as well. No environmental management plan as yet. *
A deep pit with extensive water body. Pipes pumps and generators could be
seen at the site. Water is extracted from the pit. Very little plantation could
be seen at the site. The pit is contiguous to other mines in the area and the
extent of groundwater being exploited is massive and the expanse is vast. Some
tress have been planted along the roadside. This mine is adjoining the main Delhi
bypass of Faridabad-Gurgaon, which is being tendered for a four-lane highway.
9. (17)
Name of Mine/Area: M/s. Sheeshpal Singh
Location: Village Pali, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity: 127.95 hec.
Mineral Extracted: Silica, China, clay, sand, quartzite
Status: Below groundwater table.
Whether ground water is extracted: Yes.
Status of environmental clearances: No clearance given. No environmental
management plan.
Large lake of ground water could be seen at the site. The lake apparently
covers a few contiguous mining pits. No efforts to create plantation in the
area except a few young saplings which seemed to have been planted very
recently. Huge overburden could be seen near the pits. This mine is adjoining
the main Delhi bypass of Faridabad-Gurgaon, which is being tendered for a four
lane highway.
10. (20)
Name of Mine/Area: M/s. Ram Chandar
Location : Village Gothra, Mohatabad, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity : 296 hec.
Mineral Extracted : Silica sand, ordinary sand, road metal and masonry stone.
Status: Below groundwater table
Whether ground water is extracted. Yes.
Status of environmental clearances: No clearance given. No environmental management
plan.
Deep mining pits with large water bodies could be seen. The mine is also
contiguous to the other mines so the amount of water that is being exploited is
massive and uncontrolled. Huge amounts of overburden were also seen in the
area. In this mine some efforts have been made to create plantations and the
trees, unlike those seen in other areas, were more mature. This mine is
adjoining the main bypass of Faridabad-Gurgaon, which is being tendered for a
four-lane highway. *
11. (22)
Name of Mine/Area: M/s. Maruti Minerals.
Location : Plot No.1 Village Manger, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity: 63.225 hec.
Mineral Extracted: Silica sand, China clay, ordinary sand, road metal and
masonry stone.
Status: above groundwater.
Whether ground water is extracted: No.
Status of environmental clearances: clearance given. No environmental
management plan.
Observed surface stone mining. No water seen. New lease and so the mines have
not reached ground water levels as yet. But mine ear Delhi bypass of
Faridabad-Gurgaon road.
12A. (1)
Name of Mine/Area: M/s Seven Mines and Minerals Pvt. Ltd.
Location: Plot No. 6, Village Manger, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity : 59.3875 hec.
Mineral Extracted : Ordinary sand, road metal and masonry stone.
Status: Above groundwater table
Whether ground water is extracted: No.
Status of environmental clearances: Clearance given. No environmental
management plan.
Observed surface stone mining. No water seen. New lease and so the mines have
not reached groundwater levels as yet. But mine near Delhi bypass of
Faridabad-Gurgaon Road.
12B.
Name of Mine/Area: M/s. Seven Mines & Minerals Pvt. Ltd.
Location: Plot No. 8, Village Manger, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity: 63.75 hec.
Mineral Extracted: Ordinary sand, road metal and masonry stone.
Status: Above groundwater table
Whether ground water is extracted: No.
Status of environmental clearances: Clearance given. No environmental
management plan.
Observed surface stone mining. No water seen. New lease and so the mines have
not reached groundwater levels as yet. But mine near Delhi bypass of
Faridabad-Gurgaon road.
13. (25)
Name of Mine/Area: M/s. Ashok Minerals industry
Location: Plot No. 7, Village Manger, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity: 67.00 hec.
Status: Above groundwater table
Whether ground water is extracted: No.
Status of environmental clearances: No clearance given. No environmental
management plan. *
Observed surface stone mining. No water seen. New lease and so the mines
have not reached groundwater levels as yet. But mine is on the Delhi bypass of
Faridabad-Gurgaon Road.
14. (23)
Name of Mine/Area: M/s. Jaikrishan Impex Pvt. Ltd.
Location: Plot No. 2 & 3, Village Manger, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity: 44.785 hec and
56.4375 hec.
Mineral Extracted: Stone mining
Status: Below groundwater table
Whether ground water is extracted: Yes.
Status of environmental clearances: No clearance given. No environmental
management plan.
Was shown one pit with small water collection. But at a distance seen another
pit with large amount of groundwater collected. This mine is being worked and
clearly water must have been pumped from the mine. Deep pits seen. But mine is
near Delhi bypass of Faridabad-Gurgaon road.
15. (10)
Name of Mine/Area: M/s. Faridabad Gurgaon Minerals.
Location : Plot No. 5 Village Manger, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity : 33.0375 hec.
Mineral Extracted : Ordinary sand, road metal and masonry stone
Status: Below groundwater table
Whether ground water is extracted: Yes.
Status of environmental clearances: No clearance given. No environmental
management plan.
Exposed groundwater could be seen. This mine was also been worked. Deep pits
seen in this mine.
16. (24)
Name of Mine / Area: M/s. Patram Mines and Minerals Pvt. Ltd.
Location : Plot No. 11, Village Manger, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity : 126.75 hec.
Mineral Extracted: Silica sand and stone
Status: Above groundwater table.
Whether ground water is extracted: No.
Status of environmental clearances: No clearance given. No environmental
management plan.
Stone quarry. No water seen. Some efforts have been made to create plantation.
17. (18)
Name of Mine/Area: M/s. Sheeshpal Singh
Location: Village Pali, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity : 44.48 hec.
Mineral Extracted: Solica/Ord. Sand & stone, road metal and masonry stone *
Status: Above groundwater table
Whether ground water is extracted: No.
Status of environmental clearances: No clearance given. No environmental
management plan.
Recent lease. Mining activity had recently started. New pit seen and as yet
only stone was being quarried.
18. (4)
Name of Mine/Area: Pali Silica Sand Mines, M/s. S.P. Sethi.
Location: Village Pali, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity : 82.20 hec.
Mineral Extracted: Silica/Ord. Sand, china clay stone (road metal and masonry)
Status: Below groundwater table
Whether ground water is extracted: Yes.
Status of environmental clearances: NOC given by State Pollution Control Board
in 1999 for renewal of lease. No environmental management plan.
Pit with little water seen. Being worked. Large amount of overburden was seen
close to mine. 1 hec of plantation created near mine.
19.(3)
Name of Mine/Area: Pali Silica Sand Mines, M/s. P.K. Sethi
Location: Pali, Distt. Faridabad.
Total Area of Land on Lease/ Actual area under mining activity : 162 hec.
Mineral Extracted : Sand china clay, stone (road and masonry)
Status: Above groundwater table
Whether ground water is extracted: No.
Status of environmental clearances: No clearance given. No environmental
management plan.
Pit with no water seen. Being worked. Large amount of overburden was seen close
to time.
20. (5)
Name of Mine/Area: Pali Silica Sand Mines, M/s. Lucky Minerals.
Location : Village Pali, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity: 261.36 hec.
Mineral Extracted: Sand, China clay stone (road metal and masonry)
Status: Above groundwater table
Whether ground water is extracted: No.
Status of environmental clearances: No clearance given. No environmental
management plan.
Pit with no water seen. Being worked. Large amount of overburden was seen close
to mine. Nominal plantation seen. But area with lessee is very large over - 261
ha - and no idea if other mines in the area have reached water levels.
21. (6)
Name of Mine/Area: Mohabatabad Silica sand mines, M/s. P.K. Sethi. *
Location: Village Mohtabad, Distt. Faridabad.
Total Area of Land on lease/Actual area under mining activity: 399.59 hec.
Mineral Extracted: Sand, china clay, stone (road metal and masonry)
Status: Above groundwater table
Whether ground water is extracted: No.
Status of environmental clearances: No clearance given. No environmental
management plan.
Shown pit where stone is being quarried. But area with lessee is very large
over - almost 400 hec. - and no idea if other mines in the area have reached water
level as yet.
22. (14)
Name of Mine / Area : M/s. Tejvir Singh and Co.
Location : Village Bandhwari, Distt. Gurgaon.
Total Area of Land on lease/ Actual area under mining activity: 91.20 hec.
Mineral Extracted: Silica Sand, Ord. Sand, china clay, quartz & stone mine.
Status: Above groundwater table
Whether ground water is extracted: No.
Status of environmental clearances: Clearance given. No environmental
management plan.
Stone quarry. Very recent lease granted and clearance has only been done in
April 2002. Large seemingly abandoned, pits seen on road. Labourer colony near
on road near mine and a number of trucks seen on this road carrying material.
No plantation seen.
23. (15)
Name of Mine/ Area: Mr. Ashok Gupta
Location: Village Balola, Distt. Gurgaon.
Total Area of Land on lease/Actual area under mining activity : 19.15 hec.
Mineral Extracted : Silica Sand and china clay.
Status: Above groundwater table
Whether ground water is extracted: No.
Status of environmental clearances: Clearance given. No environmental
management plan.
Stone quarry Recent lease and clearance of January, 2002. No plantation seen.
The mine is on the main Delhi bypass - Gurgaon - Faridabad road, which is being
developed as a four-lane bypass.
24. (16)
Name of Mine/ Area: Mr. Ashok Gupta
Location : Plot No.3, Village Behrampur, Distt. Gurgaon.
Total Area of Land on lease/Actual area under mining activity : 94.05 hec.
Mineral Extracted: Silica sand quartzites.
Status: Above groundwater table
Whether ground water is extracted: No. *
Status of environmental clearances: No clearance given. No environmental
management plan.
Stone quarry. Recent lease. No plantation seen. But near village. As this mine
is near the five km radius, other mines with crushers and blasting seen at
close distance.
(11B-22)
Name of Mine/Area: M/s. Maruti Minerals
Location: Village Haidpur, Distt. Gurgaon.
Total Area of Land on lease/Actual area under mining activity: 18.125 hec.
Mineral Extracted: Stone
Status: Above groundwater table
Whether ground water is extracted: No.
Status of environmental clearances: No clearance given. No environmental
management plan.
Stone quarry. No plantation seen. Near habitation of Gurgaon town.
25. (21)
Name of Mine / Area: Mr. Karan Singh
Location: Village Nathpur, Distt. Gurgaon.
Total Area of Land on lease/Actual area under mining activity: 5.996 hec.
Mineral Extracted: Silica Sand.
Status: Above groundwater level (surface mining)
Whether ground water is extracted: No.
Status of environmental clearances: No Clearance given. No environmental
management plan.
Stone quarry. No plantation seen. Mine on main Delhi-Gurgaon road at the border
of Delhi. Mine lease recently awarded at the edge of the DLF residential
colony. Allegations that illegal mining is being done at the Delhi side of this
mine. Next to the protected area of Delhi forest.
In respect of the ground water regime the report states that:
"The key issue to examine is the impact of mining on the ground water
regime in the region. It is evident from the inspection done by EPCA that
ground water reserves are being exploited and destroyed, it must be stressed
that it is not a matter of individual mines reaching ground water levels or
not, the issue to examine is the water regime of the entire area. * "
19. The report further states that 'during its inspection to the mines,
Kartar Singh Badana, Minister of Cooperatives in the State and also a mine
owner told EPCA members that the impact of ground water abstraction is minimal.
He maintained that the miners were harvesting the water and not allowing it to
flow to the Yamuna, where it would be lost to the State. A perusal of the
reports of the ground water regime shows that this contention cannot be
upheld." *
20. It is also stated in the report that "the geology and geomorphology
of the area comprises oldest exposed lithology with upland units. The rock type
is mainly quartzite and these rise 150-200 metres above ground level in the
quartzite's the ground water aquifers occur in the weathered zones and
interspaces within interconnected joints and fractures. According to the CGWB,
the unconfined aquifer is about 50 metres thick. But between the 50-110 metre
below ground level (bgi) a thick clay layer ranging in thickness from 25-60
metres separates the top unconfined aquifer from the confined aquifer. *
21. The mines inspected by EPCA were below 150 feet (45 metres) and on checking
it was found that most mines were further operating at 20-100 feet (6-30
metres) below water levels. This means that the mines are abstracting water
from the confined aquifer. As annual rainfall mostly replenishes the unconfined
or top aquifer levels, the mining activity is destroying a non-renewable
resource. EPCA saw deep and extensive pits of mines with vast waterbodies -
stretching at times to a kilometer and more. EPCA also saw evidence of pumps
and pipes being used to drain out the ground water so that mining could
continue. Therefore, the miners are mining for silica, but also in the process
mining and destroying the ground water reserves of the areas.
22. The NOC given by the Central Pollution Control Board includes an explicit
condition regarding ground water:
"That the mine owner will ensure that there is no discharge of effluent
or ground water outside lease premises. They must take measures for rain water
harvesting and reuse of water so as not to affect the ground water table in the
areas. Most importantly, it stipulates that there should be no mining
operations shall be carried out in the water table area."
*
23. The report of the Central Ground Water Board states very categorically that
the ground water table is already at a critical stage in Faridabad. It states, 'The
stage of ground water development of Faridabad block is 89.02 percent in dark
category and no further abstraction of ground water should be carried out to
avoid any adverse environmental impact on ground water regimes. Thus no
additional tube wells are advisable to be constructed for community water
supply scheme even though they may not affect the storage in Badkhal lake. * The
report further states that 'The domestic water supply to Faridabad town has
to be catered and there are no surface water source which can be tapped."
*
24. EPCA further observes that most of the mining is happening inside the
municipal area of Faridabad. In fact, Department of Mines and Geology states in
the letter dated October 12, 2002, 'it is submitted that the mineral rights
of the mines vests with the State Government.. The surface rights of villages Badkhal,
Pali, Gothra, Mohabtabad, Anangpur, Mewla Maharajpur are with municipal
corporation, Faridabad, and Manager revenue estate are with gram panchayat.' *
25. Sensitivity of this region is further accentuated by its close proximity to
the reserved forests of Asola sanctuary located at the border of Delhi and
Haryana and other ecologically sensitive areas like Surajkund and Badkhal lake.
26. Even in Gurgaon, the CGWB report indicates that the ground water scenario
is grim. According to CGWB, the 'ground water development of Guirgaon block is
124 per cent, indicating that the entire block in which Gurgaon town is
situated is over exploited'. The ground water levels are also falling
dangerously according to the report of CGWB which recommends strict regulatory
measures for ground water use.
27. The EPCA, while reaffirming the recommendations that had been made in its
earlier report dated 9th August, 2002, made the following recommendations:
"The overall assessment of the environmental impact of the mining
activities in the area especially its implication for ground water level in the
region reaffirms EPCA's assessment presented in its earlier report. EPCA
upholds its earlier recommendations made vide the report submitted to the
Hon'ble Supreme Court on August 9, 2002.
EPCA is concerned, that if mining is allowed to continue in this area, it will
have serious implications for the groundwater reserve which is the only source
of drinking water in the area. EPCA has also noticed uncontrolled construction
activities that will expand urban habitation considerably in future. Unless
immediate measures are taken to conserve and augment water resources in the
area acute survival crisis is expected. Interviews with local villagers in the
vicinity of mines confirm that water shortage is already a serious problem in
the region. *
The extent of degradation in and around mines is the evidence of failure to
enforce basic rules for ecological safeguards. Recent attempts at planting
trees are cosmetic. Exposed ground water lakes observed in mining sites only
reconfirms the worst fears. If mining could not be stopped in so many pits even
after reaching groundwater level there is no guarantee that even some of those
mines still at the surface level will abide by the stipulated norms when they
reach the water table." *
Submissions for Confirming or varying Order dated 6th May, 2002
28. Having regard to the ground realities as reflected in the aforesaid
reports, should the order passed on 6th May, 2002 be varied is the question?
The continuance of the order has been strenuously objected to by the mining
lease holders and also by the Government of Haryana. Various applications have
been filed seeking vacation of the order and in support thereof, submissions
have been made mainly by Mr. Shanti Bhushan, Dr. Rajeev Dhawan, Mr. Kapil
Sibbal, Mr. K.B. Rohtagi and Mr. Dhruv Mehta representing the lease holders and
Mr. Mukul Rohtagi learned Additional Solicitor General representing the
Government of Haryana. We have also heard Mr. Raju Ramachandran and Mr. Altaf
Ahmad, learned Additional Solicitor Generals for the Ministry of Environmental
and Forest, Government of India, Mr. C.S. Vaidyanathan and Mr. Kaushik (in
support of IA No. 1825/2002 filed by the villagers). Mr. Ranjit Kumar, learned
Amicus and Mr. M.C. Mehta, Advocate/ petitioners-in-person and Mr. Kailash
Vasudeva for Government of Delhi have made submissions in support of closure of
mining activity and for making the order dated 6th May, 2002 absolute by
prohibiting all mining activities and pumping of ground water in and from an
area upto 5 kms. from Delhi-Haryana Border in the Haryana side of the Ridge and
also in the Aravalli Hills.
Notifications Regarding Mining on Aravalli Hills
29. The notification dated 7th May, 1992 issued by the Ministry of Environment
and Forest, Government of India under Section 3(2)(V) of the EP Act read with
Rule 5 of the Rules made under the said Act has considerable bearing on the
aspect of mining in Aravalli Hills. The notification, inter alia, bans all new
mining operations including renewals of mining leases and sets out the
procedure for taking prior permission before undertaking such an activity. The
notification, in so far as material for the present purposes, reads:
"S.O.319(E) -- Whereas a Notification under Section 3(1) and Section
3(2) (v) of the Environmental (Protection) Act, 1986 (29 of 1986) inviting
objections against restricting certain activities in specified area of Aravali
Range which are causing Environmental Degradation in the Region was published
in the Gazette of India Part II-Section 3 sub-section (ii) vide S.O. 25(E)
dated 9th January, 1992;
And whereas all objections received have been duly considered by the Central
Government;
Now, therefore, in exercise of the powers conferred by sub-section (1) and
clause (v) of sub-section (2), of Section 3 of the Environment
(Protection) Act, 1986 (29 of 1986), read with rule 5 of the
Environmental (Protection) Rules, 1986 the Central Government hereby prohibits
the carrying on the following process and operations, except with its prior
permission, in the areas specified in the Table appended to this Notification:
(i) ....
(ii) (a) All new mining operations including renewals of mining leases.
(b) Existing mining leases in sanctuaries/national Park and areas covered under
Project Tiger and / or
(c) Mining is being done without permission of the competent authority.
(iii) Cutting of trees;
(iv) Construction of any clusters of dwelling units, farmhouses, sheds,
community centers, information centers and any other activity connected with
such construction (including roads a part of any infrastructure relating
thereto);
(v) ....
2. Any person who desires to undertake any of the above mentioned processes or
operations in the said areas, shall submit an application to the Secretary,
Ministry of Environment and Forests, New Delhi, in the attached application
form (annexure) specifying, inter alia, details of the area and purposed
process or operation. He shall also furnish an Environment Impact Statement and
an Environmental Management Plan along with the application and such other
information as may be required by the Central Government for considering the
application.
(3) The Central Government in the Ministry of Environment and Forests shall,
having regard to the guidelines issued by it from time to time for giving
effect to the provisions of the said Act, grant permission within a period of
three months from the date of receipt of the application or where further
information has been asked for from the applicant, within a period of three
months from the date of the receipt of such information, or refuse permission
within the said time on the basis of the impact of the proposed process or
operation on the environment in the said area. *
4. For seeking permission under this Notification, an application in the
prescribed form (See Annexure), duly filled in, may be submitted to the
Secretary, Ministry of Environmental and Forests, Paryavaran Bhavan, CGO
Complex, Lodi Road, New Delhi.
xx xx xx
3.(b)(ii) Erodability classification of the proposed land.
5.(a) Water balance at site surface and ground water availability and demand.
xx xx xx
12.(a) Environmental Impact Assessment Report:
(b) Environmental Management Plan: prepared as per Guidelines of MEF issued
from time to time.
(c) Detailed Feasibility Report.
(d) Proposal for diversion of forest land under Forest
(Conservation) Act, 1980 including benefit cost analysis.
13. Recommendations of the State Pollution Control Board and/ or the State
Department of Environmental and Forests." *
30. The aforesaid notification, restricting mining activities in Aravalli range
is relevant for mining operation in Gurgaon district wherein part of Aravalli
hills range exist.
31. The powers vested in the Central Government in terms of the aforesaid
notification dated 7th May, 1992 were delegated to the State Governments
concerned, namely, Rajasthan and Haryana by issue of notification dated
November 29, 1999 by the Central Government, Ministry of Environment and
Forest. The said notification reads thus:
MINISTRY OF ENVIRONMENT AND FORESTS
NOTIFICATION
New Delhi, the 29th November, 1999
S.O. 1189(E). In exercise of the powers conferred by section 23 of the
Environmental (Protection) Act, 1986 (29 of 1986), (hereinafter referred to as
the said Act), read with sub-rule (4) of rule 5 of the Environment (Protection)
Rules, 1986, the Central Government hereby delegates the powers conferred on it
to take measures for protecting and improving the quality of the environment
and preventing, controlling and abating environmental Pollution, to be
exercised also by the State Governments as notified in the Notification of the
Government of India in the Ministry of Environment and Forests S.O. No. 319(E)
dated 7th May, 1992 subject to certain conditions which are as follows: *
(i) the State Governments concerned, namely, Haryana and Rajasthan shall
constitute an Expert Committee for each state as per the composition given in
the Schedule-I annexed to this Notification;
(ii) each State Government shall also constitute a Monitoring Committee, under
the chairmanship of the District Collector concerned (Gurgaon in Haryana and
Alwar in Rajasthan) as given in the Schedule-II annexed to this Notification
which shall inter alia monitor the compliance of the conditions stipulated
while according environmental clearance by such State Governments and report to
such State Government about the violations, if any, and the action taken
thereon;
(iii) The District Collectors of Gurgaon in Haryana and Alwar in Rajasthan
shall be authorised by the respective State Governments to take necessary
action under section 5 of the said Act in respect of cases where the project
proponents fail to implement the conditions.
2. The State Government concerned shall initiate steps to prepare a Master Plan
for the development of the area covered by the Notification S.O. 319(E) dated
7th May, 1992 integrating environmental concerns and keeping in view the future
land use of the area. This Master Plan shall be prepared by the concerned state
agency, approved by the competent authority and finally published within two
years from the date of issue of this Notification, in accordance with the
procedure laid down in the Town and Country Planning Act or any other similar
Act of the respective State Government. The State Government concerned shall
implement the Master Plan forthwith after its final publication.
3. Any person desirous of undertaking any of the activities mentioned in the
Notification No. 319(E) dated 7th May, 1992 shall submit an application to the
Secretary, Department of Environment of the Government of Haryana/Rajasthan, as
the case may be. The applicant shall also furnish environment impact statement
and an environment management plan and such other information as may be
prescribed by such State Governments. The application after due scrutiny shall
be placed before the Expert Committee for its recommendations. Based on the
recommendations of the Expert Committee, the Department of Environment in the
State Government concerned shall take a final decision and convey the same to
the applicant within three months from the date of receipt of application or
when further information has been asked for from the applicant within three
months from the date of receipt of such information. *
4. The Ministry of Environment and Forests retains appellate power against
rejection of any proposal and the National Environmental Appellate Authority
constituted under the National Environment Appellate Authority
Act, 1997 (22 of 1997) shall continue as an Appellate Authority against
approval."
*
32. Schedule I and II of the notification sets out the composition of the
Expert Committee and of the Monitoring Committee. Some controversy and
confusion in respect of constitution of committees insofar as it relates to
appointment of an expert from non-government organization, was brought to our
notice but the delegation in favour of State Governments having been withdrawn
now, it is not necessary to examine this aspect. The Central Government, in
terms of notification dated 28th February, 2003, has withdrawn the delegation
in favour of State Governments.
Notification of 27th January, 1994 Regarding Environment Impact Assessment
(EIA)
33. Another notification which is of considerable importance on aspect of
mining is dated 27th January, 1994, as amended on 4th May, 1994. The
notification has been issued by Ministry of Environment and Forest, Government
of India, in exercise of powers conferred by sub-section (1) and clause (5) of
sub-section (2) of Section 3 of the EP Act read with clause (d) of sub-rule (3)
of Rule 6 of the EP Rules stipulating that expansion or modernization of any
activity (if the pollution load is to exceed the existing one) or a new project
listed in Schedule I of the notification shall not be undertaken in any part of
India unless it has been accorded environmental clearance by the Central
Government in accordance with the procedure specified in the notification.
34. The issue in these matters is about the interpretation of the notification,
its applicability also to mining leases granted earlier to the issue of the
notification i.e. at the time of the renewal of such mining lease. The
notification dated 27th January, 1994, to the extent material for the present
purpose, reads as under:
"S.O. 60(E) Whereas a notification under clause (a) of sub-rule (3) of
rule 5 of the Environment (Protection) Rules, 1986 inviting objections from the
public within sixty days from the date of publication of the said notification,
against the intention of the Central Government to impose restrictions and
prohibitions on the expansion and modernization of any activity or new projects
being undertaken in any part of India unless environmental clearance has been
accorded by the Central Government or the State Government in accordance with
the procedure specified in that notification was published as S.O. No. 80(E)
dated 28th January, 1993:
And whereas all objections received have been duly considered;
Now, therefore, in exercise of the powers conferred by sub-section (1) and
clause (v) of sub-section (2) of section 3 of the Environment
(Protection) Act, 1986 (29 of 1986) read with clause (d) of sub-rule (3)
of rule 5 of the Environment (Protection Rules, 1986, the Central Government
hereby directs that on and from the date of publication of this notification in
the Official Gazette expansion or modernization of any activity (if pollution
load is to exceed the existing one) or a new project listed in Schedule I of
this notification shall not be undertaken in any part of India unless it has
been accorded environmental clearance by the Central Government in accordance
with the procedure hereinafter specified in this notification.
2. Requirements and procedure for seeking environmental clearance of projects:
1. (a) Any person who desires to undertake any new project or the expansion or
modernization of any existing industry or project listed in Schedule I shall
submit an application to the Secretary, Ministry of Environment and Forests,
New Delhi.
The application shall be made in the proforma specified in Schedule II of this
notification and shall be accompanied by a project report which shall, inter
alia, include an Environmental Impact Assessment Report/Environment Management
Plan prepared in accordance with the guidelines issued by the Central
Government in the Ministry of Environment and Forests from time to time. *
(b) Cases rejected due to submission of insufficient or inadequate data and
plans may be reviewed as and when submitted with complete data and plans.
Submission of incomplete data or plans for the second time would itself be a
sufficient reason for the Impact Assessment Agency to reject the case
summarily.
II. In case of the following site specific projects:
(a) mining;
(b) to (d) ...
(e) prospecting and exploration of major minerals in areas above 500 ha.,
The project authorities will intimate the location of the project site to the
Central Government in the Ministry of Environment and Forests while initiating
any investigation and surveys. The Central Government in the Ministry of
Environment and Forests will convey a decision regarding suitability or
otherwise of the proposed site within a maximum period of thirty days. The said
site clearance shall be granted for a sanctioned capacity and shall be valid
for a period of five years for commencing the construction, operating or
mining.
III. (a) The reports submitted with the application shall be evaluated and
assessed by the Impact Assessment Agency, and if deemed necessary it may
consult a Committee of Experts, having a composition as specified in
Schedule-III of this Notification. The Impact Assessment Agency (IAA) would be
the Union Ministry of Environment and Forests. The Committee of Experts mentioned
above shall be constituted by the IAA or such other body under the Central
Government authorised by the IAA in this regard.
(b) The said Committee of Experts shall have full right of entry and inspection
of the site or, as the case may be, factory premises at any time prior to,
during or after the commencement of the operations relating to the project.
(c) The Impact Assessment Agency shall prepare a set of recommendations based
on technical assessment of documents and data, furnished by the project
authorities, supplemented by data collected during visits to sites or
factories, if undertaken, and interaction with affected population and
environmental groups, if necessary. Summary of the reports, the recommendation
and the conditions, subject to which environmental clearance is given, shall be
made available subject to the public interest to the concerned parties or
environmental groups on request. Comments of the public may be solicited, if so
decided by Impact Assessment Agency, within thirty days of receipt of proposal,
in public hearings arranged for the purpose after giving thirty days notice of
such hearings in at least two newspapers. *
Public shall be provided access, subject to the public interest, to the
summary of the reports/Environmental Management Plans at the Headquarters of
the Impact Assessment Agency.
The assessment shall be completed within a period of ninety days from receipt
of the requisite documents and data from the project authorities and completion
of public hearing where required, and decision conveyed within thirty days
thereafter.
The clearance granted shall be valid for a period of five years for
commencement of the construction or operation.
No construction work preliminary or otherwise, relating to the setting up of
the project may be undertaken till the environmental and/or site clearance is
obtained.
IV. In order to enable the Impact Assessment Agency to monitor effectively the
Implementation of the recommendations and conditions subject to which the
environmental clearance has been given the project authorities concerned shall
submit a half-yearly report to the Impact Assessment Agency. Subject to the
public interest, the Impact Assessment Agency, shall make compliance reports
publicly available.
V. If no comments from the Impact Assessment Agency are received within the
time limit, the project would be deemed to have been approved as proposed by
project authorities.
3. Nothing contained in this Notification shall apply to:
(a) any item falling under entry nos. 3, 18 and 20 of the Schedule I to be
located or proposed to be located in the areas covered by the Notifications
S.O. No. 102(E) dated 1st February, 1989; S.O. 114(E) dated 20th February,
1991, S.O. No. 416(E) dated 20th June, 1991 and S.O. No. 319(E) dated 7th May,
1992.
(b) any item falling under entry Nos. 1, 2, 3, 4, 5, 7, 9, 10, 12, 13, 14, 16,
17, 19, 21, 25 and 27 of the Schedule-I if the investment is less than Rs. 50
crores.
(c) any item reserved for Small Scale Industrial sector with investments less
than Rs. 1 crore.
4. Concealing factual data or submission of false, misleading data/reports,
decisions or recommendations would lead to the project being rejected.
Approval, if granted earlier on the basis of false data would also be to be
revoked. Misleading and wrong information will cover the following: *
-- False information;
-- False data.
-- Engineered report.
-- Concealing of factual data.
-- False recommendations of decisions.
SCHEDULE-I
(See paras 1 and 2)
LIST OF PROJECTS REQUIRING ENVIRONMENTAL CLEARANCE FROM THE CENTRAL GOVERNMENT
1. Nuclear Power and related projects such as Heavy Water Plants, nuclear fuel
complex, rare earths.
2 to 19 ...
20. Mining projects (major minerals) with leases more than 5 hectares.
21 to 29 ...
xxx xxx xxx
SCHEDULE-III
(See sub-para III(a) of Para 2)
COMPOSITION OF THE EXPERT COMMITTEES FOR ENVIRONMENTAL IMPACT ASSESSMENT
1. The Committee will consist of experts in the following disciplines:
(i) Eco-System Management
(ii) Air/Water Pollution Control
(iii) Water Resource Management
(iv) Flora/Fauna Conservation and Management
(v) Land Use Planning
(vi) Social Sciences/Rehabilitation
(vii) Project Appraisal
(viii) Ecology
(ix) Environmental Health
(x) Subject Area Specialists
(xi) Representatives of NGOs/Persons Concerned With Environmental Issues.
2. The Chairman will be an outstanding and experienced ecologist or
environmentalist or technical professional with wide managerial experience.
3. The representative of IAA will act as Member-Secretary.
4. Chairman and members will serve in their individual capacities except those
specifically nominated as representatives.
5. The membership of a Committee shall not exceed 15.
EXPLANATORY NOTE REGARDING THE IMPACT ASSESSMENT NOTIFICATION DATED 27TH
JANUARY, 1994
1 to 3. .....
4. Public Hearing
Public hearings could be called for in case of projects involving large
displacement or having severe environmental ramifications.
5 to 7. ....
8. Exemption for projects already initiated
For projects listed in Schedule-I to the notification in respect of which the
required land has been acquired and all relevant clearances of the State
Government including NOC from the respective State Pollution Control Boards
have been obtained before 27th January, 1994, a project proponent will not be
required to seek environmental clearance from the IAA. However, those units who
have not as yet commenced production will inform the IAA." *
35. Reference may also be made to a notification issued by the Haryana
Government on November 28, 2001 with a view to enforce the recommendations of
NEERI contained in para 6.1 of its report so far as mining operations in the
State of Haryana are concerned. In terms of the notification, the Designated
Authority and the Monitoring Committee were directed to impose the conditions
mentioned in the notification while according environmental clearance. This
notification, it seems, was issued in the purported attempt to comply with the
directions of this Court as contained in the order dated 10th May, 1996 as
reported in M.C. Mehta's case (supra).
36. We may also refer to the circular dated May 14, 2002 issued by the Ministry
of Environment and Forest noticing that in the past several units had come up
in violation of the notification dated 27th January, 1994 and a view had been
taken earlier that such units are permitted to apply for environment clearance
by 31st March, 1999. For period of five years, there was no circular or
notification granting any time to apply for EIA under notification dated 27th
January, 1994. The period to apply for environment clearance was extended upto
30th June, 2001 which deadline was extended upto 31st March, 2003, stating that
it was to give opportunity to defaulting units to avail of the last and final
opportunity to obtain ex post facto environment clearance. The notification
dated 27th January, 1994 is applicable also to construction activity. It seems
that this circular was issued to give opportunity to those who had undertaken
constructions after issue of notification without compliance of stipulations
therein. We are, however, not concerned in these matters with the
construction which may have come up in breach of the notification. It does not
appear that MOEF intended to legalize the commencement or continuance of mining
activity without compliance of stipulations of the notification. In any case, a
statutory notification cannot be notified by issue of circular. Further, if MOEF
intended to apply this circular also to mining activity commenced and continued
in violation of this notification, it would also show total non-sensitivity of
MOEF to the principles of sustainable development and the object behind the
issue of notification. The circular has no applicability to the mining
activity. #
Central Empowered Committee (CEC) - Its Suggestions
37. The notification dated 27th January, 1994 is mandatory. The compliance
of the notification before commencement of any mining operation is essential
and cannot be dispensed with. The MOEF has not so far conducted Environment
Impact Assessment in respect of any of the mining lease under the notification
dated 27th January, 1994. #
38. Before the order dated 6th May, 2002 was passed, the lease holders had not
made any application before the Ministry for grant of EIA. The applications
were filed during the pendency of these matters under the order of this Court.
The EIA applications of the lease holders are lying with CEC. CEC was constituted
in terms of notification dated 17th September, 2002, issued by the Government
of India, Ministry of Environment and Forest in exercise of power conferred by
Section 3(3) of the EP Act for the purposes of monitoring and ensuring
compliance of the order of this Court covering the subject matter of forest and
wildlife and related issues arising out of the said order and one of the
functions of the Committee in terms of the notification is to monitor the
implementation of the orders of this Court and place reports of non-compliance
before the Court including in respect of encroachment and removals, working
plants, compensatory afforestation, plantations and other conservation issues.
39. In the order dated 31st October, 2002, this Court has observed that no mining
activity can be carried out without remedial measures taking place and for this
purpose, it is necessary that environment impact assessment is done and the
applications dealt with before any mining activity can be permitted. It was
also observed that the application of lease holders for environmental clearance
can be disposed of them of within a period to be specified by this Court. In
terms of order dated 25th November, 2002, the Central Empowered Committee was
asked to file its suggestions in regard to the time for considering the
applications for grant of EIA. The CEC had received large number of voluminous
Environment Impact Assessment plans only in the last few days which are being
examined further stating that the process of examination and formulation of
suggestions is likely to take some more time. On 24th January, 2003, the CEC
was granted time to file its report upto 8th February, 2003. CEC has filed
three reports, the last having been filed on 7th February, 2003.
40. In an interim report dated 22nd June, 2003 CEC stated that the complete
information had not been supplied to it by the State of Haryana. The report
states that as per the information provided by the Haryana State, in Faridabad
district there are 21 sanctioned major mineral mines with the varying size from
44.48 hectare to 516.518 hectare. In Gurgaon districts 54 mining leases have
been sanctioned varying in size from 5.96 hectare to 802.322 hectare. All the
mines of major minerals were operating in Faridabad district without obtaining
statutory environmental clearance under the EP Act. It also noticed that in
respect of the Aravalli Hills range being an acknowledged as eco friendly area
under the Aravalli notification, clearances were being granted on the basis of
examination of an expert group without any public hearing or participation of
NGOs or the affected people. As already noticed, the delegation in favour of
the State has been now withdrawn. The report further observes that most of the
mines are operating in violation of approved plans. Instead of doing section
wise mining (bench mining) the mining operations are carried on
unscientifically with the sole aim to make maximum profits which has resulted
in number of fatal accidents involving labourers, hazards to the adjoining population,
indiscriminate scattering of the over burden, wasteful manner of mining with
complete disregard to mineral conservation aspect, rendering reclamation of
mined area impossible. Further it points out that several mining leaves have
been granted in areas where plantations were undertaken with the financial
assistance provided by international donor agencies. Mining activities are
permitted in a manner which is destroying the ground water table and also the
deep aquifers thereby causing irreparable damage to the critical ground water
reserves. There is no effective mechanism to ensure compliance of various
conditions stipulated while granting statutory approvals. No deterrent action
was taken against mines even in those cases where during monitoring serious
violations and non-compliance of conditions were found. The ECE has made the
following suggestions:
" i) For major mineral mines above 5 hectare in Faridabad district,
mining activity may be allowed to be undertaken only after the required environmental
clearances are accorded by the Ministry of Environment and Forest (MOEF);
ii) the powers delegated to the State Government by notification dated
27.1.1997 to grant environmental clearances in respect of areas of Gurgaon
district falling within Aravalli notification dated 7.5.1992 requires to be
reconsidered as the presumptions on the basis of which powers were delegated to
the State Government have been found to be incorrect.
iii) mining activity may be allowed in respect of areas notified under Section
4 and 5 of the PLP Act, which for the purpose of FC Act are 'forest' even as
per the State Government records, only after obtaining prior approval under the
said Act from the MOEF;
iv) all mining leases granted in respect of areas where plantations have been
raised under the financial assistance received from any international donor
agencies may be cancelled forthwith. The concerned authorities may be
prohibited from allowing any mining operations, allowing renewals or grants of
fresh leases in such areas;
v) mining activity may be allowed only as per the approved Mining Plans. Mines
which are found to be operating at variance with the approved Mining Plans may
be made liable for cancellation of lease and payment of exemplary compensation;
vi) in view of rampant and indiscriminate mining, which was being done, a high
level monitoring committee may be constituted comprising representatives of the
State Government, MOEF, Indian Bureau of Mines, Director General of Mine Safety
and reputed NGOs. This Committee may be empowered to monitor the implementation
of the conditions imposed while approving Mining Plans, grants of environmental
clearances and other approvals/clearances. Whenever any violation is detected,
the Committee should have the powers to direct closure of the defaulting mines
and also to impose fines commensurate with the seriousness of the violation; *
vii) in addition to the above (vi), the Officials of the State Government,
Indian Bureau of Mines, MOEF, Director General of Mine Safety may independently
monitor, at least once in three months, to ensure compliance of all statutory
conditions;
viii) the State Government may identify and notify officials, who would ensure
enforcement of the directions given by the Monitoring Committee and or the
above mentioned officials.
ix) no mining activities may be allowed without obtaining 'No Objection
Certificate' from the Central Groundwater Board to ensure that the water table
and the underground aquifers are not adversely affected;
x) before allowing resumption of mining activity in any approved mining lease,
the status of compliance of the conditions of the approved Mining Plans,
approved Environmental Management Plans, environmental clearances and other
statutory conditions/clearances may be ascertained. Suitable and adequate
compensation/penalty for non-compliance of stipulations may be recovered,
otherwise such stipulations would remain only on paper;
xi) in respect of forest area, including areas notified under Section 4 and 5,
net present value of the land leased out for mining may be recovered as per the
Hon'ble Supreme Court order dated 30.10.2002 in I.A. No. 566 in Writ Petition
(Civil) No. 202/95 (forest matter);
xii) a suitable system of securing adequate bank guarantee, bank deposit or
other personal guarantee from the mine owner may be worked out to ensure
compliance of all statutory and other conditions;
xiii) after considering the annual approved rate of mining and mineral deposits
in the area, optimum size of the mines may be determined in respect of approved
mines to ensure optimum utilization of the mineral resources;
xiv) presently, the over burden is not stacked as per approved Mining Plan,
which makes it practically impossible to carry out any reclamation work. The
over burden dumping may be allowed only at identified sites within the mining
lease area as per approved Mining Plans; *
xv) for the purpose of afforestation, the funds may be recovered from the
mine owners and deposited with the forest department for undertaking afforestation
in a planned manner;
xvi) the identification of the consultants for preparation of the EIA's should
be done by the regulating agency instead of by the mine owners to ensure good
and credible reports. It is important that payment to the consultants should
also be routed through the regulating agency and not directly by the mine
owners." *
41. The report of CEC dated 7th February, 2003 mentions that the State
Government, despite letters, had not made available to the Committee the
following information:
i) mine wise details of stipulated conditions, which have been fulfilled and
those which have not been fulfilled.
ii) details of five major mineral mines in Faridabad and Gurgaon Districts
which have fulfilled all the conditions stated in the approved mining plans,
environmental and other clearances;
iii) details of the mines where mining activity has been undertaken without
obtaining requisite environmental clearance.
42. In the absence of the information as aforesaid the CEC gave its suggestions
on the basis of information available to it which are as under:
i) the ban on mining activity may continue up to 2 km from Surajkund and Badkal
Lakes, as per the Hon'ble Court's order dated 10.5.1996;
ii) each of the existing mines may be physically inspected by Inspection
Team(s) comprising officials of the State Government, Indian Bureau of Mines,
Director General of Mines Safety and the Ministry of Environment and Forest to
report the specific conditions which have not been fulfilled/violated especially
in respect of:
a. sectionwise (benchwise) mining to be doe as per approved mining plan;
b. storage of top soil as per approved mining plan;
c. dumping of over-burden in identified area as per the approval mining plan;
d. plantations as per Environmental Management Plan;
e. observance of mines safety Rules and Regulations;
f. damage to the plantations raised under externally aided projects (foreign
funding);
g. damage if any to the water table/underground aquifers; and
h. compliance of environmental clearance stipulations;
The inspection Team(s) may submit the reports to the State Government and the
Ministry of Environment & Forest (MOEF) with copies to the Central
Empowered Committee (CEC) for their comments and for carrying out verification,
if found necessary.
iii) suitable penalties for non-compliance/violation of various conditions, as
found by the above Inspection Team(s) or by the CEC may be imposed. Norms for
quantifying the penalties for violation of various conditions may be formulated
by the State Government with the concurrence of the CEC. No mine may be allowed
to resume mining activity without first paying the penalty imposed on it.
iv) mining activity may completely be prohibited in area where plantations have
been undertaken with the foreign assistance/funding (externally aided
projects). Mining leases already granted/approved in all such areas may be
cancelled.
v) yearwise requirement of funds for implementation of various conditions under
which mining has been approved may be computed for each mine. To ensure
compliance of these conditions, adequate safeguards by way of bank guarantee,
mortgage of immovable assets, pledge of movable assets, personnel guarantee of
the lessee or others (supported by adequate assets) may be put in place;
vi) MOEF may examine the Environment impact Assessment Report/Environment
Management Plan of individual major mineral mines and proposals for approval
under the FC Act, if the mining lease is in 'forest' as per the Hon'ble Supreme
Courts order dated 12.12.1996 in Writ Petition (C) No. 206/95, and take
decision (s) thereon, including regarding measures for protecting the water
table and underground aquifers, in a time bound manner; and
vii) regular inspection of the mines may be undertaken by the identified
officials of the State Government, Indian Bureau of Mines and Director General
of Mines Safety. Mines which are found to have violated the conditions may be
made liable to pay stiff penalties including closure of the mines."
43. Some mining leases were granted prior to notification dated 27th January,
1994 and some after the issue of that notification. Even in respect of the
leases granted prior to 27th January, 1994, the renewal of most of the leases
has come up after issue of notification. Some of the leases are for extraction
of major mineral, some for extraction of minor mineral and some for extraction
of both major and minor mineral. In respect of none of the leases, before
commencement of mining activity, EIA was obtained from the MOEF. In respect of
mining in Aravalli Hills in Gurgaon, the relevant notifications dated 7th May,
1992, 29th November, 1999 and 28th January, 2003 have been noticed earlier.
Under the notification dated 7th May, 1992, no permission was granted by the
MOEF though some applications were pending before it when power was delegated
to the State Government. Permissions were granted by the State Government after
the powers were delegated to it. The delegation in favour of the State has
since been withdrawn.
Legal Parameters
44. The natural sources of air, water and soil cannot be utilized if the
utilisation results in irreversible damage to environments. There has been
accelerated degradation of environment primarily on account of lack of
effective enforcement of environmental laws and non-compliance of the statutory
norms. This Court has repeatedly said that the right to live is a fundamental
right under Article 21 of the Constitution and it includes the right to of
enjoyment of pollution-free water and air for full enjoyment of life. (See
Subhash Kumar vs. State of Bihar ].
45. Further, by 42nd Constitutional Amendment, Article 48-A was inserted in the
Constitution in Part IV stipulating that the State shall endeavour to protect
and improve the environment and to safeguard the forest and wildlife of the
country. Article 51A, inter alia, provides that it shall be the duty of every
citizen of India to protect and improve the natural environment including
forest, lakes, rivers and wildlife and to have compassion for living creatures.
Article 47 which provides that it shall be the duty of the State to raise the
level of nutrition and the standard of living and to improve public health is
also relevant in this connection. The most vital necessities, namely, air,
water and soil, having regard to right of life under Article 21 cannot be
permitted to be misused and polluted so as to reduce the quality of life of
others. Having regard to the right of the community at large it is permissible
to encourage the participation of Amicus Curiae, the appointment of experts and
the appointments of monitory committees. The approach of the Court has to be
liberal towards ensuring social justice and protection of human rights. In M.C.
Mehta vs. Union of India [ ], this Court held that life, public health and
ecology has priority over unemployment and loss of revenue. The definition of
'sustainable development' which Brundtland gave more than 3 decades back still
holds good. The phrase covers the development that meets the needs of the
present without compromising the ability of the future generation to meet their
own needs. In Narmada Bachao Andolan vs. Union of India & Ors. [ 4], this Court observed that sustainable development
means the type or extent of development that can take place and which can be
sustained by nature/ecology with or without mitigation. In these matters, the
required standard now is that the risk of harm to the environment or to human
health is to be decided in public interest, according to a "reasonable
person's test. [See Chairman Barton: The Status of the Precautionary Principle
in Australia: (Vol. 22) (1998) (Harv. Envtt. Law Review, P. 509 at p. 549-A) as
in AP Pollution Control Board vs. Prof. M.V. Nayuder (Retd.) & Ors.
[ ].
46. The mining operation is hazardous in nature. It impairs ecology and
people's right of natural resources. The entire process of setting up and
functioning of mining operation require utmost good faith and honesty on the
part of the intending entrepreneur. For carrying on any mining activity close
to township which has tendency to degrade environment and are likely to effect
air, water and soil and impair the quality of life of inhabitants of the area,
there would be greater responsibility on the part of the entrepreneur. The
fullest disclosures including the potential for increased burdens on the
environment consequent upon possible increase in the quantum and degree of
pollution, has to be made at the outset so that public and all these concerned
including authorities may decide whether the permission can at all the granted
for carrying on mining activity. The regulatory authorities have to act with
utmost care in ensuring compliance of safeguards, norms and standards to be
observed by such entrepreneurs. When questioned, the regulatory authorities
have to show that the said authorities acted in the manner enjoined upon them.
Where the regulatory authorities, either connive or act negligently by not
taking prompt action to prevent, avoid or control the damage to environment,
natural resources and peoples' life, health and property, the principles of
accountability for restoration and compensation have to be applied.
#
47. The development and the protection of environments are not enemies. If
without degrading the environment or minimizing adverse effects thereupon by
applying stringent safeguards, it is possible to carry on development activity
applying the principles of sustainable development, in that eventuality, the
development has to go on because on cannot lose sight of the need for development
of industries, irrigation resources and power projects etc. including the need
to improve employment opportunities and the generation of revenue. A balance
has to be struck. We may note that to stall fast the depletion of forest,
series of orders have been passed by this Court in T.N. Godavarman's case
regulating the felling of trees in all the forests in the country. Principle 15
of Rio Conference of 1992 relating to the applicability of precautionary
principle which stipulates that where there are threats of serious or
irreversible damage, lack of full scientific certainly shall not be used as a
reason for proposing effective measures to prevent environmental degradation is
also required to be kept in view. In such matters, many a times, the option
to be adopted is not very easy or in a straight jacket. If an activity is
allowed to go ahead, there may be irreparable damage to the environment and if
it is stopped, there may be irreparable damage to economic interest. In case of
doubt, however, protection of environment would have precedence over the
economic interest. Precautionary principle requires anticipatory action to be
taken to prevent harm. The harm can be prevented even on a reasonable
suspicion. It is not always necessary that there should be direct evidence of
harm to the environment. #
48. Bearing in mind the aforesaid principles, we have to consider the main
question: should the mining activity in areas in question be banned altogether
or permitted and, if so, conditions to be provided therefor? The reports and
suggestions of NEERI, EPCA and CEC have already been extensively noted. The
effect of mining activity in area upto 5 km. from Delhi-Haryana border on
Haryana side of the ridge and also in the Aravalli Hills is to be seen in light
of these reports and another report dealt later. One of the aspect stated in
these reports is about carrying on of mining activity in close proximity to the
residential area and/or main roads carrying traffic.
Mines and Minerals (Regulation and Development) Act and Rules thereunder
49. The grant of mining lease is governed by the Mines and
Minerals (Regulation and Development) Act, 1957 (for short, 'the MMRD
Act) which was enacted to provide for the development and regulation of mines
and minerals under the control of the Union. Section 13 is the rule making
power of the Central Government. The Central Government is empowered to make
rules to provide for the manner in which rehabilitation of flora and other
vegetation. Such as trees, shrubs and the like destroyed by reason of any
mining operation shall be made in the same area or in any other area selected
by the Central Government (whether by way of reimbursement of the cost of
rehabilitation or otherwise) by the person holding the mining lease. Section
18, inter alia, costs a duty upon the Central Government to take all such steps
as may be necessary for the conservation and systematic development of minerals
in India and for the protection of environment by preventing or controlling any
pollution which may be caused by mining operations and for such purposes, the
Central Government may, by notification in the official gazette, make such
rules as it thinks fit.
50. The Mineral Concession Rules, 1960 have been framed by the Central
Government in exercise of the powers conferred by Section 13 of the MMRD Act.
Chapter IV of these Rules relate to grant of mining leases in respect of land
in which the minerals vest in the Government. Rule 22(4), inter alia, provides
that on receipt of the communication from the State Government of the precise
areas to be granted for mining purpose, the applicant shall submit a mining
plan, within the period stipulated in the Rules, to the Central Government for
its approval. The applicant, on approval of the mining plan by the Central
Government, shall submit the same to the State Government to grant mining lease
over that area. Rule 4A, inter alia, provides that notwithstanding anything
contained in Sub-rule(4), the State Government shall be competent to approve
mining plan of open cost mines (mines other than underground mines) in respect
of now metallic or industrial minerals, named therein, one of it being Silica
sand. The mining plan, as provided in sub-rule (5) of Rule 22, shall, inter
alia, incorporate the mineral reserves of the area and the plan of area
showing, inter alia, water courses, limit of reserves and other forest areas
and density of trees, if any, assessment of impact of mining activity on,
forest, land surface and environment including air and water pollution; details
of the scheme of restoration of the area by afforestation, land reclamation,
use of pollution control devices and such other measures as may be directed by
the Central Government or the State Government from time to time. A tentative
scheme of mining and annual programme and plain for excavation from year to
year for five years is also required to be incorporated in the mining plan.
Rule 22(5) was inserted in the Rules by notification dated 27th September, 1994
to which certain amendments were made in terms of notification dated 17th
January, 2000 also inserting by same notification Rule 22(4A). Sub-rule(4) to
Rule 22 had been earlier inserted by notification dated 27th September, 1994.
51. The grant of permission for mining and approving mining plan and the scheme
by the Ministry of Mines, Government of India by itself does not mean that
mining operation can commence. It cannot be accepted that by approving
Mining Plan and Schedule by Ministry of Mines, Central Government is deemed to
have approved mining and it can commence forthwith on such approval. Section 13
of the MMRD Act and the Rules made in exercise of powers under the said
section, deal, Inter alia, with the aspect of grant of mining of lease and not
commencement of mining operations. Rules made under Section 18, however, deal
with commencement of mining operations and steps required to be taken for
protection of environment by preventing or controlling any pollution which may
be caused by mining operation. A mining lease holder is also required to comply
with other statutory provisions such as Environment (protection) Act, 1966, AIR (Prevention and control of Pollution) Act, 1981, The
Water (Prevention and and Control of Pollution) Act, 1974, Forest
(Conservation) Act, 1980. Mere approval of the mining plan by Government
of India, Ministry of Mines would not absolve the lease holder from complying
with the other provisions. #
52. Rules 31 to 41 contained in Chapter V of the Mineral Conservation and
Development Rules, 1988 framed under Section 18 of the MMRD Act deal with the
measures required to be taken by the lessee for the protection of environment
from any adverse effect of mining or irreversible consequences thereof. These
Rules, inter alia, provide that every holder of a mining lease shall take all
possible precautions for the protection of environment and control of pollution
while conducting mining operations in the area, shall, wherever top soil exists
and is to be excavated for mining operations, remove it separately and utilize
for restoration or rehabilitation of the land which is no longer required for
mining operations. The holder is also required to take steps so that the
overburden, waste rock, rejects and fires generated during prospecting and
mining operations or tailings, slims and fines produced during sizing salting
and benefication or metallurgical operations shall be stored in separate dumps
which shall be properly secured to prevent escape of material therefrom in
harmful quantities which may cause degradation of environment. Wherever
possible, the waste rock, overburden etc. shall be back-filled into the mines
excavation with a view to restoring the land for its original use as far as
possible and wherever it is not feasible during mining operation, the waste
dumps shall be suitably tarraced and stabilized through vegetation or
otherwise. It is also required that the phased restoration, reclamation and
rehabilitation of lands affected by mining operation shall be undertaken which
work shall be completed before the conclusion of mining operations and the
abandonment of mine. Air pollution due to fines, dust and smoke or gaseous
emissions during mining operations and related activities shall be controlled
and kept within 'permissible limits' specified under various environmental laws
of the country including the AIR (Prevention and Control of
Pollution) Act, 1981 and the Environment
(Protection) Act, 1986 by the holder of mining lease. Further, noise
arising out of such operations shall be abated or controlled by the lessee at the
source so as to keep it within the permissible limit. The mining operations
shall be carried out in such a manner so as to cause least damage to the flora
of the area and nearby areas. Every holder of mining lease shall take immediate
measures for planting in the same area or any other area as selected by the
authorized officer and not less than twice the number of trees destroyed by
reason of any mining operation and look after them during the subsistence of
the licence/lease and restore, to the extent possible, other flora destroyed by
mining operations. #
53. The aforesaid measures are not required to remain only on paper but
strictly complied for the protection of environment and control of pollution as
a result and consequence of mining operations. #
National Forest Policy
54. In respect of mining in the forest area, we may also refer to the National
Forest Policy, 1988 issued by Ministry of Environment and Forest, Government of
India which, inter alia, notices that over the years, forests in the country
have suffered serious depletion. One of the reason of it is inadequacy of
protection measure and diversion of forest and to non-forest uses. Without
ensuring compensatory afforestation and essential environmental safeguards; and
the tendency to look upon forests as revenue earning resource. The basic
objectives of the policy, inter alia, are maintenance of environment stability
through preservation and, where necessary, restoration of the ecological
balance that has been adversely disturbed by serious depletion of the forests
of the country and checking the soil erosion and water conservation and
increasing substantially the forest/tree cover through massive afforestation
and social forestry/programmes. # It provides that the National goal should
be to have a minimum of 1/3rd of the total land area of the Country under
forest or tree cover. In the hills and in mountains regions, the aim should be
to maintain 2/3rd of the area under such cover in order to prevent erosion and
land degradation and to ensure the stability of the fragile eco-system. It also
provides that a massive need based and time bound programme of afforestation
and tree planting, with particular emphasis on fuel would and fodder
development, on all degraded and denuded lands in the country, whether forest
or non-forest land, is a national imperative.
Mining in Forest Area
55. The question of permitting mining in the area where large scale of
afforestation with foreign funding has taken place is required to be examined
keeping in view the National Forest Policy which also provides that forest land
or land with tree cover should not be treated merely as a resource readily
available to be utilized for various projects and programmes but as a national
asset which required to be properly safeguarded for providing sustained
benefits to the entire community. Division of forest land for any non-forest
purpose should be subject to the most careful examinations by specialists from
the standpoint of social and environmental costs and benefits. The mining and
industrial development should be consistent with the needs for conservation of
trees in forest. # It provides that no mining should be granted to any
party, private or public, without a prior mine management plan appraised from
the environmental angle and enforced by adequate machinery.
56. Our attention was drawn by learned counsel appearing for lease-holders to
the part of national policy which provides that beneficiaries who are allowed
mining and quarrying in forest land and in land covered by trees should be
required to repair and re-vegetate the area in accordance with established
forestry practices to submit that the policy itself contemplates mining
operations in the forest area. For present, we are not suggesting a complete
ban of mining operations on forest land so long as it is possible to undertake
the said operation on the sustainable development principles and other
obtaining due approvals under various statutory provisions including Section 2
of the Forest (Conservation) Act, 1980. At the same
time, we are unable to appreciate the commencement and continuation of mining
over areas on which crores of the foreign funds have been spent for
afforestation and plantation. Further, it is also not possible to accept the
contention urged on behalf of the lease holders that only that part of such
leased land where allegedly damage has been caused to plantation as a result of
mining operations, be excluded from mining and not the entire area of the
lease. For example, if the mining area is 5 hectare and damages as a result of
mining is to plantation in an area of 1 hectare, it is not practicable or
reasonable to exclude only that 1 hectare and permit the mining operation on
the rest of the mining area. # Reference can also be usefully made to the
part of the State of Forest Report, 1999 issued by Forest Survey of India in
relation to Haryana. it, inter alia, provides that large scale plantations were
carried out under Aravalli project since 1992. The document claims increase of
the forest cover in the State as a result of plantation under the Aravalli
project. It, inter alia, mentions that forest cover increase in Gurgaon and
Faridabad is mainly due to plantation raised under the Aravalli project which
was started in early 1990s. In these matters, neither the State nor the
leaseholders can be permitted to turn round and now take a stand that the areas
covered under the Aravalli project is not forest. The National Forestry Action
Programme of December 2000 issued by the Ministry of Environment and Forest,
Government giving project profile also makes detailed reference to the
institution building and integrated national resource development in the
Aravalli region, Haryana under the project implementing agency of Forest
Department, Government of Haryana. The project profile, inter alia, states that
the Central to such a policy is rehabilitation of common lands to meet the
needs of the rural poor and to reduce soil and water erosion and the proposed
programme was envisaged to bring the benefit of integrated development of the
Aravalli eco-system to the whole community, particularly, to the poorer
sections. The project, it is stated, has been implemented in Aravalli hills
situated in the five districts of Haryana including Gurgaon. One of the
expected outcome of the project is the reduced soil erosion and improved water
regime in the rehabilitated area will be drastically reduce and run-off leading
to recharge of constantly depleting ground water resources. It records that
Haryana Forest Department has implemented a project on the eco-restoration of
common lands in the Aravalli hills, from June 1990 to October 1999. The project
is being funded by Delegation of European Communities. The total cost was 28.8
million ECU in which external assistance was to the extend of 23.2 million EUC.
Aravallis Hill Range
57. The Aravallis, most distinctive and ancient mountain chain of peninsular
India, mark the site of the one of the oldest geological formations in the
world. Heavily eroded and with exposed outcrops of the slate rock and granite,
it has summits reaching 4950 feet above sea level. Due to its geological
location, the Aravalli range harbours a mix of Saharan, Ethiopian, Peninsular,
oriental and even Malayan elements of flora and fauna. In the early part of this
century, the Aravallis were well wooded. There were dense forests with
waterfalls and one could encounter a large number of wild animals. Today,
the changers in the environment at Aravalli are severe. Though one finds a
number of tree species in the hills, timber quality trees have almost
disappeared. Despite the increase of population resulting in increase of demand
from the forest, it cannot be questioned nor has been questioned that to save
the ecology of the Aravalli mountain, the laws have to be strictly implemented.
The notification dated 7th May, 1992 was passed with a view to strictly
implement the measures to protect the ecology of the Aravalli range. The
notification was followed more in its breach. #
58. In the aforesaid background, any mining activity on the area under
paintation under Aravalli project cannot be permitted. The grant of leases for
mining operation over such an area would be wholly arbitrary, unreasonable and
illogical. #
Report of CMPDI on Aravalli
59. The Central Mine Planning & Design Institute Limited (CMPDI) on being
asked by the Central Pollution Control Board to conduct a study of
environmental problems of Aravalli hills and preparation of action plan for
restoration of environmental quality in Gurgaon district, after extensive
examination, has submitted to CPCB its final report in July 2003. CMPDI is a
subsidiary of Coal India Limited (Government of India Enterprise). The report
in respect of Aravalli range in Gurgaon district has been prepared by CMPDI
with the following objectives.
1. To prepare status report of the pollution problems in the Aravalli Hills.
2. To prepare environmental management plan to abate various environmental
problems.
3. To prepare action plan for restoration of environmental quality.
60. The environmental problems in the Aravalli Range in Gurgaon district have
been identified and remedial measures including the pollution control
guidelines and action plan for various stakeholders have been suggested by
CMPDI. It has been noticed that in large scale mining projects what is still
required is a proposal on district level as to what will be mined, how it will
be mined and with what method and many such areas of environmental concern
which had not been adequately addressed keeping in view the environmental
degradation of the Aravalli Hills. It has also been noticed that the Aravalli
notification restricts process and operations under certain categories of the
land in district. Though the records of such lands are available at every
village level map, there is no record available in the district level in
respect of these areas to undertake realistic appraisal and effective
monitoring of mining and other projects at the macro level on such lands. While
noticing that, notification dated 29th November 1999, inter alia, made
provision for preparing a master plan integrating the environmental concerns
and the future land use of the area, but the master plan prepared on 28th
August, 2002 does not, inter alia, address the issue of natural resource
assessment and water Resource status; the areas near crushing zone and active
mining zone remain a matter of concern and concerted efforts have not been
given to the quality of roads and the dust suppression measures to maintain the
air quality within safe limits. The guidelines of operation in an
eco-friendly manner have been issued by the State Government but the compliance
is only partial, inasmuch as wind breaking walls are not proper, pollution
control devices are not operating and the green belt around the crushing zones
are not maintained. Identification of mines in the district is difficult. There
does not seem to be mechanism to upgrade the mining technologies and
methodologies to minimize the impact due to mining in the eco-sensitive zones
in the district. There is no identified land where overburden could be
temporarily dumped prior to being utilized for void filling and for other
purposes. There does not seem to adequate awareness among the people in respect
of the environmental problems. In some parts of the district, the ground water
potential is already in the dark category. Lack of water conservation measures
and rainwater harvesting may ultimately lead to water scarcity in the near
future. #
61. Having identified the environmental problems, various actions have been
recommended by CMPDI for the eco-restoration in the Aravalli Range in Gurgaon
district. It has been, inter alia, recommended that it is imperative on the
part of the State Government to improve inter departmental co-ordination among
various Government departments to achieve the common objective, i.e.,
ecological restoration of Aravalli Hills in the district. The master plan
should indicate the proposed eco-restoration plan to compensate the
environmental degradation by the proposed activities in the master plan.
Rehabilitation programmes for the abandoned mines areas either to convert these
to water reservoirs and eco-parks or reclamation by filling by rural waste,
urban waste or fly ash. The master plan should be detailed to show the areas
where overburden could be dumped, areas where waste material could be stocked,
areas where plantation could be carried out, etc.etc. The planning should,
inter alia, include environmental impact and concerns of activities of one
sector on the other sectors in the district, e.g., afforestation should be
planned not only with a view to increase vegetation on the hills but also to be
supplement for fuel, fodder etc. in the district. All efforts should be made to
preserve the ground water resources. Water shed management and rainwater
harvesting to be implemented in the Aravalli hills regions on war footing. In
the areas where mining deeper than the ground water lable of the area is to be
carried out, adequate provision of pollution control and conservation of water
resources should be made. There should be frequent inspections of the mining
operations to ensure that these are in line with the requirement for
sustainable development. The inspections may be carried out at an interval of
three months. There should be continual source of revenue from the mining
operations to the fund, recommended to be created, for the eco-restoration of
the Aravalli hills. the minimum period of lease should be for 15-20 years.
These will induce the mine operators to take environmental protection measures
more seriously. The State Pollution Control Board shall undertake regular
monitoring to check compliance and to assess the ambient air quality, water
quality and other environmental protection measures. The Ministry of
Environment and Forest should take initiative to appoint a Central Agency to
monitor the eco-restoration efforts and to provide technical support to the
implementing organizations. #
The renewal of mining lease and granting new leases should be effected after
examining the environmental protection measures taken by the lessee. Requisite
data should be displayed on the internet to arouse awareness in public and for
further usage. Stringent action should be taken for water conservation. #
62. The Forest Department may even carry out the afforestation on behalf of
mine operators. Expenses should, however, be borne by the mine operators. The
afforestation shall be carried out keeping in view, inter alia, the
consideration of checking the soil erosion. # The mine lessee should
implement the environmental management plan and mining plan approved by the
concerned authority. In future, efforts in respect of search for sustainable
development should broadly take into consideration resource potential in the
region, the demand of the products and the supply options.
63. Though the demand for the niche products existing in the Aravalli range
which is one of the oldest mountain ranges in India will continue to grow, the
supply options need to be given a closer look due to eco-sensitivity of the
region. The environmental cost needs to be internalized in the cost of the
product and there is need to limit the supply options. Noticing that the
Aravalli range prevents the desert from spreading into Indo-Gangetic plains, it
has been suggested that all future planning should not only concentrate to meet
the ever growing demand of the products but due consideration should also be
given to protect the chain. All the developmental activities should,
therefore, be planned in a coherent manner and there should be integrated
approach for sustainable development. #
64. CMPDI has noticed that in the Aravalli Hills, a large number of activities,
operations of stone crushers and deforestation besides other activities are
causing environmental degradation. These mines are usually located in the
clusters in remote mineral rich districts/areas where living standards is lower
and understanding of people towards environmental impact is also poor. In the
past, the mine operators took no note of environmental damage. In fact, they
were not even conscious about it.
65. The attitude of mining community is to ignore the environmental
concerns. In majority of the cases, the environmental concerns are ignored for
making quick profits. The small mines (less than 5 hectares) and the mining of
minor minerals which are no doubt small individually but have damaging
characteristics when in clusters, e.g. the mines of granite, marble, slates,
quartzite etc. (falling under minor minerals) are no less damaging than the others,
especially when the processing is taken into consideration. The mining
activities results in disturbance of land surface, altering drainage pattern
and land use, besides the pollution problems, which may lead to the
environmental problems of air, water and noise pollution and solid waste
pollution.It has been suggested that the short term and long term action plan
for the restoration of environmental quality of the area shall be prepared
separately. The action plan shall be prepared in such a way that it should be a
guiding tool also in the hands of the state pollution control boards and
Government agencies for enforcement of the environmental laws for the
restoration of environmental quality of the area. Monitoring programme shall
include frequency of monitoring for air quality, water quality, ground water,
solid wastes, noise level etc. #
66. In respect of water resources, it has been, inter alia, suggested that in
order to draw water resource management plan, it is essential to assess the
water quality of the various components of the hydrologic cycle, i.e., stream,
ground water, surface water etc. It has been pointed out that since the surface
water potential is not promising in the district, there is increased dependence
on the ground water for meeting the agricultural, domestic and industrial
requirement resulting in depletion of ground water resources in the district.
It has been suggested that utmost care is required for further development of
ground water in the areas where the recharge of the ground water is low.
67. Dealing with the flora and fauna, it has been pointed out that the earliest
account shows that at one time the Aravalli hills were well covered with dhauk
(Anogeissus pendula). Now, except in few places, viz., the Jhir Forest in Firozpur
Jhirka (dedicated to Mahadeo Temple) and near Bhondsi recently regenerated with
dhauk, the Aravallis are by and large, bereft of vegetation in the district.
68. It has been noticed that in order to take stock of the environmental
problems, CPCB and CMPDI team made several visits to Aravalli hills and held
discussion with the mine operators, State officials and local people. There are
number of mining projects etc. which are already existing and there is also
tremendous potential to further increase the industrial and the other
development activities. The environmental impact due to mining projects on air
quality, water quality, noise level, overburden etc. have been noticed and it
has been pointed out that the opening of new projects will further affect some
of the environmental attributes.
69. The report notices that the environmental degradation has taken place due
to mining activities. The existing crusher units are also not functioning on
the environmental sound systems. The situation warrants closer look on various
components of the systems affecting the environmental attributes in the area,
devising pragmatic approaches to facilitate eco-restoration of the Aravalli
hills and offering broad framework to the industrial units to function under environmentally
sustainable framework. The suggestions also include the enactment of rules for
grant of mine leases to levy a separate charge for dump removal, ecological
restoration in the area, the technology to be used for mining operations and
post mining land use and mine decommissioning. As far as environmental
protection in the Aravalli hills is concerned, planning and provisions must
start from the stage of grant of mine lease and what all it should include have
been set out. It has been, inter alia, suggested that the environmental
framework shall include the framework for environmental clearance such as depth
of cutting, area of plantation and the type of plantation, which are attributes
related to closure planning as also framework for monitoring and for forestry
besides air quality, land use pattern etc. In nutshell, it has been suggested
that it is imperative on the part of the mine operators to carry out the mine
operations in such a fashion that it has least impact on the ecology of the
area. # The pollution prevention guidelines have been suggested in para
7.1.1.2 Having regard to the detailed study, the recommendations and action
plan has been dealt with in Chapter VIII of the report, inter alia, suggesting
that concerted efforts from various departments are needed.
70. The report states that though the environmental upgradation measures need
to be taken more seriously by the mine and other industrial operators, there is
need on the part of the State Government to immediately start these measures in
the areas where degradation has already taken place. The other recommendations
have already been broadly noticed.
71. No one has raised any objection to the recommendations contained in the
report of CMPDI. We accept the recommendations in principle. Modification of
Order dated 6th May, 2002 Regarding Mining in Aravalli
72. Now, the question is should mining activities in the Aravalli range in
Gurgaon district be permitted to restart and, to that extent, the order dated
6th May, 2002 be modified, meanwhile directing implementation of
recommendations in the report of CMPDI and earlier referred reports. The other
option is to first constitute a monitoring committee directing it to
individually examine and inspect mines from environmental angle in the light of
the said recommendations and file a report in this Court in respect of
individual mines with its recommendations for restart or otherwise as also
recommendation, if any, for the payment by the mine operators and/or by State
Government towards environmental fund having regard to the precautionary
principles and polluter pays principle and on consideration of that report, to
decide the aspect of modification of the order dated 6th May, 2002, partially
or entirely. We are of the view that the second option is more appropriate. We
are conscious of observations in CMPDI that measures for protecting the
environment can be undertaken without stopping mine operations and also the
suggestions of MOEF to permit mining subject to the mine lease holders undertaking
to comply with such conditions which remain to be complied, but, having regard
to the enormous degradation of the environment, in our view, the safer and the
proper course is to first constitute a Monitoring Committee, get a report from
it and only thereafter consider, on individual mine to mine basis, lifting of
ban imposed in terms of order dated 6th May, 2002. # Before concluding this
aspect, we may note that assuming there was any ambiguity about the
applicability of order dated 6th May, 2002 to mining in Aravalli Range, it is
clarified that the said order would be applicable to all the mines in Aravalli
hill range in Gurgaon district.
73. Applicability of notification dated 27th January, 1994.
The notification has been reproduced in the earlier part of the judgment. It,
inter alia, applies to mining projects (major minerals) with leases of more
than 5 hectares. It can neither be disputed nor has been disputed that the
notification is mandatory. It, inter alia, provides that on and from the date of
its publication in official Gazette expansion or modernization of any activity
(if pollution load is to exceed the existing one) or a new project listed in
Schedule A of this notification shall not be undertaken in any part of India
unless it has been accorded environmental clearance by the Central Government
in accordance with the procedure specified therein. The contention urged on
behalf of the lease-holders is that the leases in question do not relate to
expansion or modernization of any activity as postulated by the notification.
Further, it is contended, that the notification applies to 'a new project'
which means that it will apply to mining lease granted after issue of
notification. It has been strenuously contended that the renewal of existing mining
lease is neither 'an expansion' nor 'modernization' nor is it a 'new project'
and, therefore, the notification will have no applicability at the time of
consideration of the renewal of the lease. Reliance has been placed on a
decision of this Court in Narmada's case (supra) holding that the notification
is clearly prospective and, inter alia, prohibits the undertaking of a new
project listed in Schedule I without prior environmental clearance from the
Central Government. The contention urged was that since in Narmada's case,
where construction had commenced nearly 8 years prior to the notification, same
very notification was not held applicable. On the same analogy, it cannot have
any applicability to the leases granted prior to the issue of notification. No
doubt, the notification is prospective but the question here is whether it
would be applicable when the aspect of renewal comes up for consideration after
the issue of the notification. In Narmada's case, it was not held that this
notification will not apply at the stage of renewal. The observations made in
para 129 of the said decision and relied upon by learned counsel for the lease
holders have no relevance to determine the applicability of the notification at
the stage of renewal. In Narmada's case, the environmental clearance had been
granted in the year 1987 and this Court noticing that when it was granted by
the Prime Minister, whatever studies were available were taken into
consideration, it was known that the construction of the dam would result in
submergence and the consequent effect which the reservoir will have on the
ecology of the surrounding areas and various studies relating to environmental
impact had been taken into consideration and that there was no obligation to
obtain the statutory clearance under 1994 notification.
74. In the present case, regarding the manner of grant of no objection
certificate from environmental angle for proposed mining activity, by way of
illustration, we may refer to the order dated 18th January, 1999 issued by
Haryana State Pollution Control Board whereby no objection certificate for
renewal of lease was granted stipulating that the applicant Som Prakash Sethi
in respect of mining activity at village Anangpur, district Faridabad shall
also seeking environmental clearance of its mining project in compliance with
this notification without even mentioning any time limit for it and admittedly
till date that had not been done. None bothered to find out whether conditions
in the order has been complied or not. Further the letter dated 25th January,
2003, sent to Principal Secretary of Central Empowered Committee by Director
Mines and Ecology, Haryana shows how the State Government has been
circumventing the legal requirements and permitting mining. In that letter, it
has been stated that pending approval of the environmental plan, the mining
lessees undertook the mining operation of the minor mineral on issue of short
term permit, in cases where the fresh mining leases were granted and in case of
renewal of mining leases, the mining activities were going on. This is despite
conditions in the judgment dated 10th May, 1996 by this Court that the Director
Mining and Ecology Haryana would be responsible for mining in the State of
Haryana.
75. Be that as it may and reverting to legal position, in Ambica Quarry Works
v. State of Gujarat & Ors. [ ], though a case under Forest (Conservation) Act, 1980 rejecting the contention
that approval at the stage of renewal was not necessary and also the plea that
since the leaseholders had invested sum of money in mining operation, it was
the duty of the authorities to renew the lease, it was held that having regard
to the awareness that deforestation and ecological imbalances as a result of
deforestation have become social menaces and the same should be prevented and
that the concept that power coupled with the duty enjoined upon the respondents
to renew the lease stood eroded by the mandate of the FC Act. It was held that
The primary duty was to the community and that duty took precedence. In such
cases, the obligation to the society must predominate over the obligation to
the individuals. It would be apposite to reproduce what was said by Justice
Mukherjee (as he then was) in paras 14 and 15 which read thus :
"14. Here the case of the appellants is that they have invested large
sums of money in mining operations. Therefore, it was the duty of the
authorities that the power of granting permission should have been so exercised
that the appellants had the full benefits of their investments. It was
emphasized that none of the appellants had committed any breach of the terms of
grant nor were there any other factors disentitling them to such renewal. While
there was power to grant renewal and in these cases there were clauses
permitting renewals, it might have cast a duty to grant such renewal in the
facts and circumstances of the cases specially in view of the investments made
by the appellants in the areas covered by the quarrying leases, but renewals
cannot be claimed as a matter of right for the following reasons.
15. The rules dealt with a situation prior to the coming into operation of 1980
Act. '1980 Act' was an Act in recognition of the awareness that deforestation
and ecological imbalances as a result of deforestation have become social
menaces and further deforestation and ecological imbalances should be
prevented. That was the primary purpose writ large in the Act of 1980.
Therefore the concept that power coupled with the duty enjoined upon the
respondents to renew the lease stands eroded by the mandate of the legislation
as manifest in 1980 Act in the facts and circumstances of these cases. The
primary duty was to the community and that duty took precedence, in our
opinion, in these cases. The obligation to the society must predominate over
the obligation to the individuals." *
76. In Rural Litigation and Entitlement Kendra v. State of U.P. ],
agreeing with views expressed in Ambica Quarry Workers, it was held that the FC
Act applies to renewals as well and even if there was a provision for renewal
in the lease agreement on exercise of lessee's option, the requirement of the
Act had to be satisfied before such renewal could be granted. In State of M.P.
& Ors. v. Krishnadas Tikaram 9], these
two decisions were relied upon and it was held that even the renewal of lease
cannot be granted without the prior concurrence of the Central Government. It
is settled law that the grant of renewal is a fresh grant and must be
consistent with law.
77. We are unable to accept the contention that the notification dated 27th
January, 1994 would not apply to leases which come up for consideration for
renewal after issue of the notification. The notification mandates that the
mining operation shall not be undertaken in any part of India unless environmental
clearance by the Central Government has been accorded. The clearance under the
notification is valid for a period of five years. In none of the leases the
requirement of notification was complied with either at the stage of initial
grant of the mining lease or at the stage of renewal. Some of the leases were
fresh leases granted after issue of the notification. Some were cases of
renewal. No mining operation can commence without obtaining environmental
impact assessment in terms of the notification. #
The Applicability of Forest (Conservation) Act, 1980
to areas treated as forest by State Forest Department.
The provisions of the Act provide for the conservations of forest and for
matters connected therewith or ancillary or incidental thereto. Any forest land
or portion thereof cannot be used for any non-forest purposes or assigned by
way of leases or otherwise to any private person or to any authority,
corporation, agency or any other organization not owned, managed or controlled
by the Government, except with the prior approval of the Central Government.
Mining activity within forest area cannot be permitted in contravention of the
provisions of the Act. The Act makes the contravention of any of the provisions
of Section 2 as an offence punishable in the manner provided in the Act.
78. The controversy is in respect of certain leases where area under the lease
is covered under notification issued under Section 4 and/or 5 of the Punjab
Land Preservation Act, 1900. The question is whether such area is 'forest' of
any kind. Under Section 3 of the aforesaid Act, whenever it appears to the
State Government that it is desirable to provide for the conservation of
sub-soil water or the prevention of erosion in any area subject to erosion or
likely to become liable to erosion, such Government may by notification make a
direction accordingly. Under Section 4(b), the State Government has power to
regulate, restrict or prohibit the quarrying of stone or the burning of lime at
placed where such stone or lime had not ordinarily been so quarried or burnt
prior to the publication of the notification under section 3. Section 5(b) in
respect of any specified village or villages, or part or parts thereof,
comprised within the limits of any area notified under section 3, the State
Government may, by special order, temporarily regulate, restrict or prohibit
the quarrying of any stone or the burning of any lime at places where such
stone or lime had ordinarily been so quarried or burnt prior to the publication
of the notification under section 3. In respect of some mining areas
notifications have been issued under Section 4 and in respect of some
notifications have been issued both under Sections 4 and 5. The submission is
that invoking of Sections 3, 4 and 5 is only to conserve sub-soil water and
prevention of the area from erosion of land and is not to create any forest. It
has been pointed out that in cases where the notifications have been issued,
only felling of trees had been prohibited and not quarrying of stone.
79. It cannot be disputed that the State Forest Department has been treating
and showing the aforesaid areas as 'forest'. The contention urged on behalf of
the State Government is that it was on account of erroneous view point of
Forest Department. In fact and law, such area is not 'forest' and mining is not
prohibited and, therefore the question of seeking permission under Section 2 of
the FC Act does not arise. In the instant case, it is not necessary to decide
the legal effect of issue of the notification under Section 4 and/or 5 of the
Act. Not only in their record the area has been shown as forest but the
affidavits have been filed in this Court stating the area to be 'forest'. In
T.N. Godavarman Thirumulkpad v. Union of India & Ors. [ 4] , this Court held that the term 'forest' is to be
understood in the dictionary sense and also that any area regarded as a forest
in Government record irrespective of ownership would be a forest. The State of
Haryana, besides having filed affidavits in the forest matters treating such
areas as forest for the purposes of the FC Act has been seeking prior approval
from the Central Government for diversion of such land for non-forestry
purpose.
80. Reference in this connection may also be made to the affidavit dated 8th December,
1996 filed by Banarsi Das, Principal Chief Conservator of Forest, Chandigarh,
Haryana in Civil Writ No.171 of 1996 Environmental Awareness Forum v. State of
Jammu & Kashmir and Ors. Our attention has also been drawn to letter dated
26th November, 2002 addressed by Divisional Forest Officer, Faridabad to Mining
Officer, Faridabad forwarding to him a list of blocked forest areas of
Faridabad district and requesting him to ensure that the said forest areas are
not affected by any mining operations as also to a letter dated 17th September,
2001 sent by Principal Chief Conservator of Forest, Haryana (Panchkula) to
Director of Environment, Haryana stating therein that no mining activity can be
permitted in the area. On the facts and circumstances of the case, we cannot
permit the State Government to take a compete summersault in these proceedings
and contend that the earlier stand that the area is 'forest was under some
erroneous impressions. In the present case, for the purposes of the FC Act,
these areas shall be treated as forest and for use of it for non-forestry
purpose, it would be necessary to comply with the provisions of the FC Act. #
81. We may also note that assuming that there was any confusion or erroneous
impression, it ought to have been first sorted out at appropriate level and
where affidavits had been filed in this Court, clarifications/orders sought
before issue of the mining lease in respect of such area.
82. Impact of Mining on Ground Water
Where during mining water level is touched, the Monitoring Committee shall
carve out that area and it was agreed on behalf of the leaseholders that they
would co-operate and not undertake any mining in such an area. #
83. Non-payment of royalty to the villagers.
A controversy has been raised about non-payment of royalty by the leaseholders
to villagers on whose behalf it was contended that the order dated 6th May,
2002 prohibiting mining should not be varied till the leaseholders discharge
their liability to pay royalty to the villagers. On the other hand, mine
leaseholders dispute the claim put-forth on behalf of the villagers and it has
been submitted that no amount is payable by them and the villagers can make
their claim, if any, from the State Government. The dispute of this nature
cannot be properly adjudicated in these proceedings. We leave it open to be
adjudicated before appropriate forum in accordance with law. Leases in respect
of minor mineral.
84. Though notification dated 27th January, 1994 is not applicable to minor
minerals, but having regard to what we have discussed above in regard to
degradation of environment and the required standard about the risk of harm to
the environment or to human health to be decided in public interest according
to 'reasonable person's test', and the report of CMPDI, we direct the
Monitoring Committee to examine the leases granted for extraction of minor
mineral in light thereof and file its report. The Committee would, however,
bear in mind that the notification dated 27th January, 1994 as such is not applicable
to these leases. #
85. Mining in Faridabad District.
Having examined the matter, we are of the view that though the study conducted
by CMPDI relates to mining activity in Aravalli Hills in Gurgaon district, in
public interest the general safeguards and suggestions in that report deserve
to be implemented in respect of mining in Faridabad district as well.
We have already extracted the recommendations of NEERI, as also violations
noticed in the reports submitted by EPCA and the suggestions of EPCA, CEC and
CMPDI. The Monitoring Committee shall inspect the leases in question in
Faridabad District as well in the light of these recommendations and file its
report containing suggestions on recommencement or otherwise of the mining
activity therein.
It may be reiterated that if, despite stringent conditions, the degradation
of environment continues and reaches a stage of no return, this Court may have
to consider, at a later date, the closure of mining activity in areas where
there is such a risk. #
As earlier noticed as well, it would not be expedient to lift the ban on mining
imposed in terms of the order of this Court dated 6th May, 2002 before ensuring
implementation of suggestions of CMPDI and other recommendations of experts
(NEERI, EPCA and CEC). The safer course is to consider this question, on
individual basis after receipt of report of the Monitoring Committee.
86. Environment Impact assessment applications .
During the course of hearing environment assessment applications in terms of
notification dated 27th January, 1994 have been filed by some of the
leaseholders. In case, those applications are presently with Central Empowered
Committee, the same shall be forthwith forwarded by CEC to MOEF. The adverse
effect, if any, and extent thereof on human health and ecology shall be
examined while deciding impact of these activities.
There is also the desirability of transparency in such matter. The MOEF is
directed to consider the said applications within a period of 10 weeks. #
87. Monitoring Committee.
With a view to monitor the overall eco-restoration efforts in the Aravalli
Hills and to provide technical support to the implementing organizations and
also to monitor implementation of recommendations contained in reports referred
herein, it is necessary to constitute a Monitoring Committee. The heads of the
following departments would be members of the Monitoring Committee :
1. Regional Officer of State Pollution Control Board.
2. Forest Department
3. District Administration
4. Department of Mining & Geology
5. Irrigation Department
6. Regional Officer of CGWB
7. Agriculture Department
8. District Industry Department.
9. Chairman - CPCB.
Besides above, MOEF is directed to appoint an officer from Central Ground Water
Board to be a member of the Monitoring Committee. The following persons as
representatives of public shall also be members of the said Committee :
1. Prof. Dilip Biswas, Ex Chairman, CPCB.
2. Mr. Valmiki Thapar,
3. Mr. Bhure Lal.
The MOEF would act as a nodal agency of the Monitoring Committee. The Secretary
of MOEF is directed to appoint an officer not below the rank of a Joint
Secretary in the Ministry for the said purpose.
The Monitoring Committee is directed to inspect the mines in question and file
a report within a period of three months, inter alia, containing suggestions
for recommencement of mining in individual cases. All concerned individuals and
departments are directed to render full co- operation to the Monitoring
Committee. #
88. Conclusions
1. The order dated 6th May, 2002 as clarified hereinbefore cannot be vacated
or varied before consideration of the report of the Monitoring Committee
constituted by this judgment.
2. The notification of environment assessment clearance dated 27th January,
1994 is applicable also when renewal of mining lease is considered after issue
of the notification.
3. On the facts of the case, the mining activity on areas covered under Section
4 and/or 5 of Punjab Land Preservation Act, 1900 cannot be undertaken without
approval under the Forest (Conservation) Act, 1980.
#
4. No mining activity can be carried out on area over which plantation has
been undertaken under Aravalli project by utilization of foreign funds.
5. The mining activity can be permitted only on the basis of sustainable
development and on compliance of stringent conditions.
6. The Aravalli hill range has to be protected at any cost. In case despite
stringent condition, there is an adverse irreversible effect on the ecology in
the Aravalli hill range area, at a later date, the total stoppage of mining
activity in the area may have to be considered. For similar reasons such step
may have to be considered in respect of mining in Faridabad District as well.
7. MOEF is directed to prepare a short term and long term action plan for the
restoration of environmental quality of Aravalli hills in Gurgaon district
having regard to what is stated in final report of CMPDI within four months.
8. Violation of any of the conditions would entail the risk of cancellation of
mining lease. The mining activity shall continue only on strict compliance of
the stipulated conditions.
The matters are directed to be listed after reopening of courts after summer
vacation on receipt of the report from the Monitoring Committee. #