SUPREME COURT OF INDIA
Messrs Ongc Limited
Vs.
Association of Natural Gas Consuming Industries
C.A.Nos.8530-40 of 1983
(S. R. Babu and A. S. Lakshmanan JJ.)
12.04.2004
JUDGMENT
S. Rajendra Babu, J.
1. A batch of writ petitions was filed in the High Court of Gujarat
challenging the increase in the price of gas and by an interim order, the High
Court directed ONGC to supply gas at the old rate of Rs.504/- per 1000 M3.
Subsequently, by another order made on 29.10.1982, the price was raised to
Rs.1000/- per 1000M3. By an order made on 30.7.1983, the High Court allowed the
writ petitions and set aside the price which had been determined by ONGC.
Pursuant to a certificate of fitness, appeals were filed in this Court and this
Court continued the interim order granted by the High Court and thereby the
respondents in the appeals received gas for which they paid a price of
Rs.1000/- per 1000M3.
2. This Court, on 4.5.1990, by judgment upheld the prices fixed by ONGC and
allowed the appeals. After the appeals were allowed, ONGC became entitled to
receive the difference in the price of gas supplied. ONGC, in addition to the
said principal amount, also demanded interest thereon in terms of Clause 5.02
of the contract. When payment was not made in accordance with their demands,
I.A. Nos.1-11 and 23-33 were filed in this Court and this Court, by an order
made on 6.4.1993, passed the orders for categorising the respondents into three
categories. The first category being where the principal amount was allowed to
be paid in instalments. Where such offer was not made, this Court made it clear
that ONGC was entitled to recover the entire dues. The third category is of
such cases where the companies concerned have become sick and proceedings were
pending before BIFR under the SICA. Subsequently, it was directed that these
IAs will remain pending and would be listed for hearing for directions
regarding payment of interest after the principal amount is paid. But in some
of the cases, there is no dispute that the payment of principal amount has been
made in terms of this Court's order.
3. Thereafter, applications in I.A.Nos. 190-200 were filed by ONGC claiming
interest on the balance principal amount in terms of this Court's order dated
4.5.1990. This Court, after examining the matter, held as under:
“ONGC was under an obligation by virtue of the interim orders to comply with
the terms of the earlier contracts and to supply gas in the manner provided
thereunder. This part of the contract was performed by the ONGC who thus became
entitled to recover from the industries the price which had originally been
charged by them. For the late payment of the amount, the contract in clause 5
had contemplated payment of interest at the rate and the manner specified
therein..."
4. However, it was made clear therein that the cases of Sarabhai Common
Services and Alembic Chemicals Ltd. [now known as 'Alembic Ltd.'] will be dealt
with separately and now these applications have come up for consideration.
5. There is a serious dispute between ONGC and the applicants as regards the
demands raised by ONGC. It is contended that the ONGC while calculating the
arrears of principal amount has applied for a higher price contrary to the
decision of this Court and hence the arrears of principal amount had to be
recalculated by applying the correct rate/price in accordance with the order of
this Court; that the arrears claimed on account of short-liftment have been
calculated by ONGC using the rates for actual supply which include the element
of sales tax and royalty on the short-lifted quantities; that the money payable
for short-liftment of gas less than the minimum quantity of gas agreed to be
purchased is neither delivered nor supplied and hence cannot be treated as sale
and in such a case neither royalty nor tax is leviable and, therefore, they
contend that the statement of arrears which contained the element of royalty
and sales tax will have to be recalculated by excluding the same; that they had
made a request by a letter dated 24.6.1985 for reduction in the contracted
quantity from 60000 cubic meters per day to 50, 000 cubic meters per day; that
since the matter was sub-judice before this Court, the change in the contracted
quantity could not be done.
6. Therefore, they claim that this aspect has to be considered now that the
matters have been disposed of by ONGC and thereafter to re-compute the demands.
In addition, it is also contended that the contract provides for force majeure
and strike by workmen and furnace collapse are covered by this clause and ONGC
is required to bill on actual usage quantity during the period of strike and
furnace collapse. Again on the plea that the matter was pending before this
Court, this aspect was not examined by ONGC. In these circumstances, it is
submitted that the applicant is entitled to relief.
7. A similar application has also been made by M/s Sarabhai Common Services
contending that the interest payable by them on the amounts due will have to be
taken note of and there have been representations made by both M/s Sarabhai
Common Services and also by Alembic Ltd. However, in neither of the cases has
ONGC considered the demands made by them effectively and thereafter determined
the amount of arrears due from them without making appropriate adjustments for
the money paid by them pursuant to the orders of this Court or further claims
arising therefrom. The representations made by both these companies have been
dealt with in usual bureaucratic style without due consideration to the points
raised.
8. We find that the points raised by them both in regard to the payment of
interest and in regard to other aspects are of substantial nature and cannot be
brushed aside as has been done now but needs to be considered by ONGC
appropriately.
9. So far as interest is concerned, though this Court stated in the order made
on 26.7.2001, that interest is payable in terms of clause 5 of the contract as
contract continued to be in force till the matters were finally disposed of by
this Court, but that was in the normal circumstances arising in this case. We
may notice that these two cases where Sarabhai Common Services and Alembic
Chemicals Ltd. [now known as 'Alembic Ltd.'] are drug manufacturing companies
and prices at which they sell their goods are fixed by the Drug Price Control
Orders, which had taken into consideration the price at which the gas was
supplied, which now gets enhanced by reason of the orders of this Court.
10. Therefore, in the totality of the circumstances, we think, interest shall
be payable by these two companies at the rate as stipulated in clause 5 of the
contract but not compoundable but simple rate of interest. To that extent, we
allow the applications filed by Sarabhai Common Services and direct ONGC to
reduce their claim to that extent in the demands made by them. In case of M/s
Alembic Ltd. ONGC shall examine other points raised by them as regards: (i) the
exclusion of the royalty and sales tax on the damages for short- liftment; (ii)
the effect of their letter seeking for reduction of supply from 60000 cubic
meters per day to 50, 000 cubic meters per day; and (iii) Claim made on the
basis of force majeure clause and thereafter re- determine the arrears payable
by them along with interest.
11. The applications accordingly stand disposed of in terms of the aforesaid
directions.