SUPREME COURT OF INDIA
Haryana Urban Development Authority
Vs.
Saurabh Aggarwal
C.A.No.5877 of 2002
(S. N. Variava and A.K.Mathur JJ.)
24.09.2004
JUDGMENT
S. N. Variava, J.
1.
Before this Court a large number of Appeals have been filed by the Haryana
Urban Development Authority and/or the Ghaziabad Development Authority
challenging Orders of the National Consumer Disputes Redressal Commission,
granting to Complainants, interest at the rate of 18% per annum irrespective of
the fact of each case. This Court has, in the case of Ghaziabad Development
Authority vs. Balbir Singh reported in, deprecated this practice. This Court
has held that interest at the rate of 18% cannot be granted in all cases
irrespective of the facts of the case. This Court has held that the Consumer
Forums could grant damages/compensation for mental agony/harassment where it
finds misfeasance in public office. This Court has held that such compensation
is a recompense for the loss or injury and it necessarily has to be based on a
finding of loss or injury and must co-relate with the amount of loss or injury.
This Court has held that the Forum or the Commission thus had to determine that
there was deficiency in service and/or misfeasance in public office and that it
has resulted in loss or injury. This Court has also laid down certain other
guidelines which the Forum or the Commission has to follow in future cases.
2. This Court is now taking up the cases before it for disposal as per
principles set out in earlier judgment. On taking the cases we find that the
copies of the Claim/Petitions made by the Respondent/Complainant and the
evidence, if any, led before the District Forum are not in the paper book. This
Court has before it the Order of the District Forum. The facts are thus taken
from that Order.
3. In this case, the Respondent was allotted a plot bearing No. 4/13(P) Sector,
Hisar on 4th April 1986. The Respondent paid substantial amounts but the
possession was not delivered. Thus the Respondent filed a complaint. On these
facts, the District Forum awarded interest @ 18% p.a. on the deposited amount.
4. The State Forum confirmed the Order of the District Forum but reduced
interest from 18% to 15%. The Appellants went in Revision before the National
Commission. The National Commission dismissed the Revision filed by the
Appellants relying upon its own decision in the case of Haryana Urban
Development Authority v. Darsh Kumar and observing that interest @ 18% p.a. has
been allowed by them under similar circumstances. As has been stated in so many
matters, the Order of the National Commission cannot be sustained. It cannot
dispose of the matters by confirming award of interest in all matters
irrespective of the facts of that case. It must, on facts of a case, award
compensation/damage under appropriate heads if it comes to the conclusion that
such award is justified/necessary. Accordingly the Order of the National
Commission is set aside.
5. We are informed that the Appellants have offered possession on 22nd July
1997. Counsel had no instructions whether Respondent had taken possession or
not. Undoubtedly the Respondent will be entitled to take possession, if he has
not already taken possession. Appellants will deliver possession without
demanding any further or other amounts.
6. We are informed that the Respondent has paid a sum of Rs. 1, 68, 338.25. We
however find from the copy of the allotment letter, filed in this Court along
with the affidavit of the Estate Officer dated 29th July 2004, that a sum of
Rs. 1, 68, 186.50 was payable. In the affidavit the following statement is
made:
"The interest on the amounts deposited by the respondent has been adjusted
on 25.5.1998 for an amount of Rs.2, 49, 829.65 at the interest rate of 15%
p.a."
7. Counsel had no instructions and could not explain what were the amounts due
from the Respondent which are supposed to have been adjusted. As stated above
Respondent has paid more than what he was bound to pay. Also neither before the
District Forum or the State Forum or the National Commission and even in the
Appeal Memo before this Court is there a claim that Appellants have to recover
amounts from the Respondent. When the dispute has been subjudice the Appellants
are bound to put before the Court/Forum not just their defence but also their
claim/counterclaim, if any. Without permission of Court the Appellants cannot
set at naught awards of the Forum by raising, outside Court, demands against
the Respondents. It must be remembered that the Appellants were to deliver
possession within a reasonable time. They do not offer possession till 22nd
July 1997. As can be seen from the Order of the District Forum possession was
not being offered because development work had not taken place. As they were
not in a position to deliver possession they cannot expect parties like the
Respondent i.e. allottees to keep on paying installments to them. In such cases
i.e. where Appellants are not in position to deliver possession they cannot
charge interest on delayed payments till after they offer possession. Clause 6
of the letter of allotment also so provides. It reads as follows:
"6.The balance amount i.e. Rs.1, 26, 139/50 of the above tentative price
of the plot/building can be paid in lump sum without interest within 60 days
from the date of issue of the allotment letter or in six equal installments.
The first installment will fall due after the expiry of one year of the date of
issue of this letter. Each installment would be recoverable together with interest
on the balance price at 10% interest on the remaining amount. The interest
shall, however accrue from the date of offer of possession."
8. Thus, interest could only have been charged from date of offer of
possession.
9. As we are unable to understand and Counsel has no instructions to be able to
explain why extra payment has been collected and/or what adjustments are
purported to have been made, we direct that Appellants shall now recalculate in
the manner set out hereunder. In this case, Appellants must pay interest at 15%
from date of each deposit till date of payment. They will not charge interest
on delayed payments prior to 22nd July 1997. If by that date the original price
of Rs. 1, 68, 186.50 had been paid they will not be entitled to and will not
charge any interest. If anything extra is recovered they will repay that back
to the Respondent with interest thereon at 15% from the date of such wrongful
recovery till payment. We, however, clarify that if Appellants have a claim and
feel that they have to recover such amounts from Respondent, they are at
liberty to approach this Court for clarification/modification of the Order and
if on that application they are permitted to so recover they may. But in the
absence of any such permission, they shall not recover anything extra/over and
above the allotment price of Rs. 1, 68, 186.50.
10. Further, if TDS amount is deducted they will now pay that over to the
Respondent with interest thereon at the rate of 15% from date it was so
deposited till payment. Such recalculation to be made within 15 days from today
and the amounts found due and payable to the Respondent to be paid to him
within 15 days thereafter. A compliance report to be filed in this Court within
one month from date. A copy of the recalculation to be annexed to the
compliance report.
11. We clarify that this Order shall not be taken as a precedent in any other
matter as the order is being passed taking into account special features of the
case. The Forum/Commission will follow the principles laid down by this Court
in the case of Ghaziabad Development Authority vs. Balbir Singh (supra) in
future cases.
12. With these observations, the Appeal stands disposed of with no order as to
costs.