SUPREME COURT OF INDIA
Special Land Acquisition Officer
Vs.
Indian Standard Metal Company Limited
C.A.No.6368 of 2004
(Arijit Pasayat and C.K.Thakker JJ.)
30.09.2004
JUDGMENT
C.K.Thakker, J.
1. Leave granted.
2. This appeal by special leave is directed against the judgment and order
dated July 3, 2001 in First Appeal No.758 of 1988 by the High Court of
Judicature at Bombay partly allowing the appeal of the claimants for grant of
enhanced compensation.
3. The brief facts of the case are that the respondent-claimant, the Indian
Standard Metal Company Limited ("Company" for short) owned various
pieces of land admeasuring about 21 hectres and 31.5 acres (2,13,150 Sq.Mtrs.)
located at village Wadghar in Taluka Panvel of District Raigard in Maharashtra.
Those lands were acquired by the State Government for New Bombay Project by
issuing notification dated February 3, 1970 under Section 4 of the Land
Acquisition Act, 1894 (hereinafter referred to as 'the Act') which was
published in Government Gazette on February 4, 1970. Corrigendum dated
September 5, 1970 was published in Government Gazette on September 7, 1970.
Thereafter, notification under Section 6 of the Act was issued on October 25,
1972 which was published in Government Gazette on December 7, 1972. Notices
under Section 9(1) and 9(2) of the Act were issued on May 10, 1973 and were
published in Government Gazette on May 21, 1973 and May 10, 1973 respectively.
Individual notices under Section 9(3) and 9(4) were also issued on October 10,
1975 which came to be served on respondent-Company on October 16, 1975.
Respondent-Company claimed compensation @ Rs. 20/- per square yard for
non-agricultural land and @ Rs. 15/- per square yard for agricultural land. The
Special Land Acquisition Officer, Metro Centre No.1, Panvel passed an award
under Section 11 of the Act on February 22, 1985 and fixed the market value of
the land including trees, construction, solatium and additional compensation
etc. as Rs. 7,40,832.67 ps thereby fixing the market value of the land at Rs.
1.10 ps per sq.mtr. An amount of Rs. 7,40,832.75 was paid to the claimants on
February 25, 1985 and possession of the entire land was taken over.
4. After receipt of notice under Section 12(2) of the Act, being dissatisfied
with the award, the claimant-respondent-Company filed a Land Reference being
LAR No. 189 of 1986 under Section 18 of the Act before the Special Land
Acquisition Officer requesting him to forward the same to the Civil Court for
adjudication and claimed compensation for entire land at the uniform rate of
Rs. 15/- per sq. meter. Thus, additional amount of Rs. 29, 58,790/- was
claimed. The appellant-State filed its written statement before the Civil
Judge, Senior Division Bench, Raigad at Alibag in the Reference. In the Land
Reference, respondent-Company examined its Power of Attorney holder Balchandra
Shantaram Sule as C.W.1 as also Jeewan Naraya Kulkarni as C.W.2, valuer who
visited the land in August-September, 1986. The Civil Judge, Raigad by an order
dated April 18, 1987 awarded compensation@ Rs. 1.80 per sq.meter. Thus,
additional amount of Rs. 5, 09,103.60 together with interest @ 9% for first
year and @ 15% for subsequent years was granted.
5. Dissatisfied with the quantum of compensation, the respondent-Company
preferred First Appeal No. 758 of 1988 before the High Court of Bombay and
claimed compensation at the uniform rate of Rs. 15/- per sq. meter.
Claimant-respondent also filed Civil Application No. 930 of 1992 in pending
First Appeal No. 758 of 1988 seeking permission to produce additional evidence
and also sought amendment by claiming enhanced compensation @ Rs. 45/- per sq.
meter. The High Court by the impugned order dated July 3, 2001 awarded enhanced
compensation of the acquired land @ Rs. 12.50 per sq. meter for entire land by
deducting development charges @ 20%. It was observed by the High Court that
location of the land was near several important places and assessing the market
value of those lands compensation had to be awarded in consonance with the
industrial growth in the vicinity. The Court stated that N.A. potentiality of
the land was also required to be considered. The Court further observed that
valuation report of Expert Valuer was ignored by the trial Judge without
assigning reasons. The Court noted that a consistent view has been taken in
such cases that development aspect has to be considered. It observed:
"We may further note that this court has taken consistent view in the case
involving the lands in the same area in respect of the compensation to be
awarded and while dealing with the land situated in the adjacent villages, it
was held the development factor for consideration of the market value was on
the basis of their proximity to various factors such as National Highway, State
High Highways and other infrastructural facilities. Therefore, if we are to
follow the same rule consistent with other decisions of this court, and taking
into account all the relevant aspects in respect of the location of the
impugned land along with its potentiality, we are of the view that the proper
rate of compensation for this land would be Rs. 12.50 ps. per sq.mtr."
6. Being dissatisfied with the order of the High Court, the Special Land
Acquisition Officer has preferred this appeal by special leave.
7. Notice was issued pursuant to which the respondent appeared. A counter
affidavit and affidavit in rejoinder have been filed. We have heard learned
counsel for the parties.
8. Learned counsel for the appellant contended that the High Court has committed
an error of law as well as of jurisdiction in allowing the appeal. It was
submitted that the relevant date for deciding the quantum of compensation was
Notification under Section 4 of the Act. The said Notification was issued in
February, 1970. It was, therefore, on the basis of that date that the amount of
compensation was required to be determined. Development of the area was
subsequent to and post of 1970 and the amount of compensation could not be
fixed considering the development of area after 1970. The High Court by
considering such development committed an error in enhancing the amount of
compensation. It was also submitted that the Reference Court considered the
evidence of two witnesses of the claimant in its proper perspective. From the
said evidence, it was clear that most of the development was post 1970. So far
as the evidence of Jeewan Naraya Kulkarni, the valuer is concerned, it was
urged that he had admitted that he was entrusted with the work of valuation of
acquired land by the claimants only in August, 1986, i.e. after more than 15
years of issuance of notification under Section 4 of the Act. He visited the
land thereafter, i.e. in the end of 1986 and prepared his report on that basis.
Obviously, therefore, he had no knowledge as to what happened between 1970 and
1986 except what he had heard from other persons or so-called information
received by him. The counsel further submitted that the land in question is a
large track of land admeasuring more than 2 kilometers. Sale instances sought to
be relied upon by the claimants in respect of small pieces of lands, therefore,
were not much relevant and not comparable. Deduction of development charges
would have been more comparing the development of recent past. In calculating
development charges @ 20%, an error on the face of the record has been
committed by the High Court. Serious grievance voiced by the learned counsel
for the appellant was that the High Court has not considered extremely
important material, namely, that a part of the land was acquired by the
Government for the Company as also the fact that the Company had purchased some
land by private negotiations in or about 1964-65. In spite of insistence by the
appellant, no documentary evidence was furnished nor sale-deeds were produced by
the Company. All those facts ought to have been appreciated by the High Court
before allowing the appeal and granting enhancement of compensation. By not
doing so, the High Court acted illegally and the order allowing the appeal by
the High Court deserves to be set aside by restoring the order passed by the
Reference Court.
9. Mr. Gopal Subramaniam, senior advocate appearing for the respondent-Company
on the other hand, supported the order passed by the High Court. The counsel
submitted that in undoubted exercise of appellate jurisdiction, the High Court
considered all points argued by the parties and recorded a finding that the
land was developed land and such development was there even in 1970 when the
Notification under Section 4 of the Act was issued. It also took into account
potential non-agricultural use of land which was indeed a relevant and vital
fact. The valuer's report was considered in the light of substantive evidence
of the valuer wherein he had stated about the development of land in or about
1970. The counsel also submitted that though the deduction of development
charges @ 20 per cent was on higher side, the High Court has reduced the amount
of compensation by depriving the appellant-Company of substantial amount. The
order of the High Court has not caused prejudice to the Government and the
appeal deserves to be dismissed.
10. Having given our thoughtful consideration to the rival contentions of the
parties, in our opinion, the appeal deserves to be partly allowed. The High
Court allowed the appeal of the Company and granted enhancement in the amount
of compensation by deducting development charges @ 20 per cent. To us, however,
it appears that the learned counsel for the appellant is right in submitting
that the High Court had not appreciated the evidence of witnesses for the
claimants properly. From the evidence of Balchandra S/o Shantaram Sule,
Claimant-Witness No.1 it appears that the entire developments was not prior to
or in or about 1970 and such development was after the said period. Moreover,
the evidence of architect-cum-valuer Claimant-Witness No.2 also relates to the
period of August, 1986 and thereafter. In his examination-in-chief itself, he
had stated that in August, 1986, he was entrusted with the work of valuation of
acquired land by the Company. He thereafter visited the acquired land. He also
admitted that he visited the place four times. Afterwards, he studied the
development in neighbouring area and its effect on the acquired land. He
visited the office of Talathi and collected necessary information regarding
sale transactions and valuation of land by studying the sale transactions from
1967 to 1972.
11. In cross-examination, the witness admitted that he did not know that the
acquired land was purchased by the claimant in 1967. He also admitted that he
did not feel to see sale transactions in respect of the land in question. He
denied that he ignored those transactions because otherwise valuation could not
be enhanced. He had to admit that there was no industry in Wadghar village and
no commercial zone was formed in Wadghar village before 1970. There was no
residential colony except college campus quarters. So far as acquired land is
concerned, he admitted that in 1970, it was partly agricultural land and partly
uncultivable. All the sale instances except the award of NIDC were on the
eastern side of the Bombay Highway and the acquired land was about 2 kilometers
away from Bombay-Pune Highway and by road it was 2.5 kilometers. All the sale
instances were between 500 meters and 1 kilometer from Bombay-Pune Highway. The
sale deeds were in respect of minimum area of 500 sq. mtrs. and maximum of 1500
sq.mtrs.
12. It is clear from the record and also from the cross-examination of
Claimant-Witness No.1 that the Government had acquired some land (12 acres) for
the respondent-Company. The Government gave possession of the land to the
Company in April, 1967. The witness then stated that he was not aware what was
the price paid to the Government for acquisition of the land. He also stated
that he could not trace the record in the office. He could not say as to
whether the Company had papers when the representation was made to the
Government. He could not give the name of the officer who dealt with the
purchase of the land. He stated that he had no personal knowledge in the
matter. He admitted that though some land was purchased by the Company
thereafter, he was unable to produce sale deeds in respect of the said land. He
also stated that he had not procured sale transactions of the land nearby. He
had not made any enquiry about those transactions. He had flatly stated that he
was not going to produce any sale deed. In further cross-examination he
admitted that all the industries mentioned by him were towards the north of
Panvel. There was no industry near about the acquired land. He admitted that he
did not know whether prior to 1970 there was any commercial or industrial area
and residential activities within the vicinity of the acquired land. He also
did not know the situation of the acquired land in or before 1970.
13. From the evidences of the two witnesses of the claimant as also from other
evidence, the Reference Court observed that admittedly some land was purchased
in the year 1964 by the Company itself and yet witness No.1 stated that he was
not knowing anything about the purchase price. The Court noted that the
transactions were of 1964-1965 and thus "not so much immemorial so as to
treat the record evidence lost". In the circumstances, those documents
ought to have been produced by the company.
14. In our opinion, by making the above observations, the Reference Court has
not committed any illegality. The High Court, unfortunately, has not considered
this aspect in its proper perspective. Again, the Reference Court was right in
stating that when the claimant itself has purchased some land, purchase price
of the land was an important factor in determining the value of the acquired
land. The Reference Court also observed that according to the Government, some
land was subject matter of purchase by the Company in 1964-65 and price paid by
the Company was much lower ranging from 0.45 paise to 0.75 paise per sq.mtr.
The State also relied upon Index Extracts (Ex.37) showing the price paid by the
Company in 1964-65. In view of non-production of documentary evidence of the
land purchased by the Company, the Reference Court observed:--
"It cannot be ignored that the price that was actually paid for a
particular piece of land by the claimants in the year 1964-65 is within their
knowledge and obviously it is a company viz. Indian Standard Metal Company Ltd.
that has kept accounts and has furnished extensive list of machinery that was
required to be purchased at the time of starting factory on the acquired land
and must be presumed to be in possession of the record and the 11 sale deeds
that were executed. The year 1964-65 is not so much immemorial so as to treat
the record as lost and therefore, obviously it looks that the claimants are not
willing to put forth the relevant record and for one reason or the other they
want to suppress the fact viz. the price that was paid for the acquired pieces
in the year 1964-65."
15. It is thus clear that a relevant and germane consideration has not been
taken into account by the High Court in deciding the appeal and enhancing the
amount of compensation. To us, the submission on behalf of the appellant is
also well-founded that in the instant case, the acquisition of land is on a
large scale of more than 2 kilometers, and as such, the instances of small pieces
of land would not be of much assistance to the claimant. In our opinion,
therefore, the High Court ought not to have given undue importance to sale
instances. Since the High Court failed to consider documentary evidence as also
the fact of non-production of sale deeds by the Company and also the evidence
of two witnesses for the claimants in its proper perspective, it would be
appropriate if we set aside the decision of the High Court and remit the matter
to the High Court so that the Court may consider the matter afresh in the light
of the evidences before it and in the light of observations made by us
hereinabove.
16. For the foregoing reasons, the appeal deserves to be partly allowed and is
allowed and is allowed by setting aside the order passed by the High Court. We
remit the matter to the High Court for taking an appropriate decision afresh in
accordance with law. In the facts and circumstances of the case, however, there
shall be no order as to costs.