SUPREME COURT OF INDIA
Punjab State Electricity Board Limited
Vs
Zora Singh
Appeal (Civil) 4910-4981 of 2005, [@ S.L.P. (C) No. 22352-22423 of 2003], Civil Appeal Nos. 4983-4984 of 2005 [@ Slp (C) Nos. 14960 and 16202 of 2004]
(Ashok Bhan and S.B.Sinha)
11/08/2005
S. B. SINHA, J.
Leave granted in S.L.Ps.
Punjab State Electricity Board (for short 'the Board') is a statutory authority
created in terms of Section 5 of the Electricity (Supply)
Act, 1948 inter alia for the purpose of rationalization of the
production and supply of electricity to the consumers. Supply and distribution
of electricity indisputably are public utility services. The Respondents herein
are agriculturists.
Section 22 of the Indian Electricity Act, 1910
imposes a statutory obligation on the licensee to supply the electrical energy
in the following
term:
"Where energy is supplied by a licensee, every person within the area
of supply shall, except in so far as is otherwise provided by the terms and
conditions of the licence be entitled, on application, to a supply on the same
terms as those on which any other person in the same area is entitled in
similar circumstances to a corresponding supply." *
Electrical undertakings acquire the character of public utilities by reason of
their virtually monopolistic position and their profession to serve the public.
The State in exercise of its legislative power had a right to compel the
licensees to render service efficiently, promptly and impartially to the
members of the public, as has been done by enacting Section 22 of the said Act.
Even in common law such public utilities having obtained a licence under a
statute are under an automatic obligation by reason of the fact that the
property of a public utility is dedicated to public service and impressed with
public interest to serve the public and any such statutory obligation is in
effect and substance a declaration of the common law.
Upon the dedication of public utility to public use and in return for the grant
to it of a public franchise, the public utility is under a legal obligation to
render adequate and reasonably efficient service, without unjust discrimination
and at reasonably rates to all the members of the public to whom its use and
scope of operation extend and who apply for such service and comply with
reasonable rules and regulations of the public utility. Although Section 22 of
the Indian Electricity Act, 1910 per se does not
apply to Board in view of the provisions of the Electricity
(Supply) Act, 1948, the provisions contained therein indicate that the
Board has also a duty to render such services.
The right of a prospective consumer is meticulously and minutely regulated
under the Electricity (Supply) Act, 1948 and/ or the
Indian Electricity Act, 1910 and Indian Electricity
Rules. The grounds upon which a licensee can refuse to supply electrical energy
is also governed by the statute.
The licensee, thus, has a statutory liability to supply electrical energy to
any prospective consumer on the same terms as those on which any other person
in the same area is entitled in similar circumstances to a corresponding
supply. Such a statutory obligation on the part of the licensee is also
reinforced in terms of Clause VI of the Schedule appended to the Act.
The Respondents herein with a view to obtain supply of electricity energy filed
applications and the Board asked them to deposit the security amount. As
despite deposit of such security amount and compliance of other formalities
electrical energy was not supplied to the Respondents, complaints were filed
before various District Forums alleging deficiency in service on the part of
the Board.
The Respondents had also spent a huge amount on construction of Kotha and
making other arrangements for obtaining supply of electrical energy. The
District Forums found the Board guilty of deficiency in service and directed
the Board to give the connections to the complainants within the period(s)
specified therein and also awarded compensation. The Board preferred appeals
there against inter alia on the ground that it was obligated to supply
electrical energy to the applicants maintaining the order of seniority, in view
of Regulation 24 of the Sales Manual. The said appeals were dismissed.
Aggrieved by and dissatisfied therewith Revision Petitions were filed by the
Board and by reason of the impugned judgment dated 4.8.2003, the National
Commission while upholding the claim of the Board that the order of seniority
should be maintained in the matter of supply of electrical energy, directed it
to release connections to all applicants by 31.3.2004.
It also directed payment of interest at the rate of 12% per annum on the
amounts deposited by the complainants and awarded compensation of Rs. 10, 000/-
each to them. Cost of Rs. 2000/- was also directed to be paid. Aggrieved the
Board is before us.
In these appeals, an additional affidavit has been filed annexing therewith the
regulations purported to have been framed under Section 79(j) of the Electricity (Supply) Act, 1948. Mr. Ashwani Kumar, learned
senior counsel appearing on behalf of the Board would contend that the National
Commission acted illegally and without jurisdiction in passing the impugned
judgments and orders without taking into consideration that the Board at the
relevant time did not act only in terms of the circulars issued by the State
but also acted under the regulations framed under Section 79(j) of the said Act
in terms whereof no interest was payable.
The learned counsel submitted that this Court should take judicial notice of
the fact that the Government of Punjab at one point of time directed supply of
free electrical energy to the agriculturists resulting in drainage of huge fund
and on that account the Board was not in a position to purchase materials
required for supply of electrical energy.
The learned counsel would contend that if the order of the Commission is to be
given effect to, the Board would have to bear a huge financial liability as during
the relevant period 15000 applications for supply of electrical energy were
received.
It is not in dispute that prior to framing of the regulations, the Board by way
of executive instructions issued circulars known as Sales Manual and Abridged
Conditions of Supply. The said executive instructions were restricted for
internal circulation only. However, allegedly with a view to provide
transparency in the functioning of the Board, Sales Regulations were issued in
1999 incorporating and amending certain provisions contained in Commercial
Circular No. 2/97 dated 3.1.1997, including Instruction No. 26. The said
Regulations were also placed before the State Legislature on 28.3.2000 as is
required in terms of Section 79-A of the Electricity (Supply) Act.
The relevant provisions of Commercial Circular No. 2/97 which allegedly formed
a part of Regulation framed under Section 49 and Sub- section (j) of Section 79
of the Electricity (Supply) Act read, thus:
"Subject: Time limit for grant of connections SMI26. The matter
regarding time limit for release of connections to various categories of
consumers has been reconsidered and it has been decided as under:
After the compliance of demand notice, the connection to various categories of
prospective consumers should be given within the time schedule specified
below:-
i) Large Industrial Power Supply and Bulk Supply above 100 KW :3 months
ii) Medium Industrial Power Supply and Bulk Supply upto 100 KW: 2 months
iii) Small Industrial Power Supply category:
a) Where no augmentation is involved : 2 weeks
b) Where augmentation is involved: 6 weeks
iv) Domestic and Non-residential Supply category: 2 weeks
v) Agricultural Pumping Supply category: 2 months
Note: The above specified period shall be subject to availability of requisite
material like poles, conductors, transformers, insulators and other allied
material. It will further be subject to any court case/ dispute or other
bottlenecks such as damage of power transformer etc.
However, where connections cannot be released within the above time schedule,
reasons for delay shall be displayed on the Notice Board but individual
intimation would also be given, in case of small power, medium supply and large
supply applicants, indicating the probable date. Where the connection cannot be
released within 2 months of compliance of requisite formalities/ compliance of
demand notice then the same with the detailed reasons would be brought to the
notice of C.E./ Operation concerned.
2......................
3. In view of the time limits specified above, it should be ensured that the
demand notices are issued carefully taking all the circumstances viz.
availability of the funds, materials and also power position into
consideration. The release of connections will also be subject to restrictions
imposed due to power shortage and loading conditions of the system etc.
The provisions of SMI-26 may be considered as amended above." *
Clause 24 of the Sales Regulations also specifies the period during which
electrical connections are to be granted. Clauses 24.6 and 24.8 read as under:
"24.6 Above time frame shall be subject to availability of requisite
material particularly poles, conductors, transformers and insulators. It will
further be subject to any court case/ dispute or other bottlenecks such as
damage to power transformer, etc.
24.8 In view of the time limits specified above, it should be ensured that the
demand notices are issued carefully taking all the circumstances viz.
availability of funds, materials and also power position into consideration.
Release of connections will also be subject to restrictions imposed due to
power shortage and loading conditions of the System etc." *
On or about 11.7.2001, a Commercial Circular No. 57/2001 was also issued
wherein it was stated:
"8.1 Before commencing supply to a prospective consumer or resuming
supply / allowing additional load to an existing consumer or any time during
the existence of an agreement executed by the consmer with Board, the Board may
require the consumer to lodge with it an Advance Consumption Deposit (ACD) and
/ or Additional Advance Consumption Deposit (AACD), against advance energy
charges on which no interest shall be payable.
This advance consumption deposit shall not be transferable. Normally, the
Advance Consumption deposit will be equivalent to three months electricity bill
on the prevalent tariff. 8.4 The ACD/ AACD/ security shall be deposited in
cash. No interest is payable on ACD/ AACD deposit against energy consumption.
However, interest @ 6% per annum shall be payable on security deposit of Rs.
100/- and above against meters/ metering equipment. However, no interest will
be payable, if a connection is disconnected within a year of giving
supply." *
Before adverting to the rival contentions raised before us, we may notice that
keeping in view the fact that the Board had failed and/ or neglected to supply
electrical energy to a large number of agriculturists, the National Commission
secured the presence of the Chief Engineer (Commercial) of the Board who gave
an assurance and undertaking that while maintaining the seniority list
electrical connections would be given to all the complainants/ Respondents by
31.3.2004.
Although a contention was raised that the Board is bound to supply electrical
energy in terms of the seniority of the applications, no factual dispute was
raised that electrical connections were required to be granted within two
months of issue of demand notice, the same had not been done for years. Section
79(j) of the Electricity (Supply) Act, 1948 confers
power upon the Board to make regulations laying down principles governing the
supply of electricity by the Board. Although it is doubtful as to whether the
Board in exercise of its regulation making power under Section 79(j) can direct
that no interest shall be payable at all or limit the rate of interest, it may
not be necessary for us to go into the said question in this case as the said
regulations are not applicable in the instant case having been brought into
force only in 1999 in view of the fact that all the applications had been filed
prior to 1999 and demands were raised in 1999.
The administrative circulars as thence existed as also the regulations
indisputably require supply of electrical energy to the agriculturists within a
period of two months from the date of receipt of the amount asked for in terms
of the demand notice. It may be true that the note appended thereto provides
that the period specified therein shall be subject to availability of requisite
material but the same does not absolve the Appellant from performing its
statutory duties.
In Andhra Pradesh State Road Transport Corporation v. The State Transport
Appellate Tribunal & Ors., 2001 ILR (AP) 1], a Full Bench of the Andhra
Pradesh High Court has noticed thus:
"24. The meaning of "note" as per P. Ramanatha Aiyar's Law
Lexicon, 1997 Edition is 'a brief statement of particulars of some fact', a
passage or explanation" *
The note, therefore, was merely an explanatory in nature and thereby the rigor
of the main provision was not diluted. The Board in terms of the Regulations
was obligated to display the reasons for delay on the Notice Board. They were
also required to indicate the probable date of supply therefor. Furthermore,
such cases were also required to be brought to the notice of Chief Engineer
(Operation). Compliance of the said statutory requirements had not been brought
on record. Clause 2 of the said Circular reads as under:
"2. It may, however, be pointed out that the period specified above is
the maximum to give connections in much shorter period." *
Clause 3 of the said Circular mandates the authorities to ensure that prior to
issuance of demand notice, care is taken to take into consideration all circumstances,
viz., availability of funds, materials and also power position. Commercial
Circular No. 57/2001 provides for advance consumption deposit or meter security
deposit. Clause 8.4 thereof which puts a restriction in the matter of payment
of interest relates to only ACD/AACD. 6%, however, is payable on security
deposit of Rs. 100/- and above against meters/ metering equipment. Consumer
Protection Act was enacted to provide for better protection of the interests of
consumers and for that purpose to make provision for the establishment of
consumer councils and other authorities for the settlement of consumers'
dispute and for matters connected therewith. No dispute has been raised before
us that the provisions of the said Act are not applicable.
"Deficiency" has been defined in Section 2(g) to mean "any
fault, imperfection or shortcoming in the quality, quantity, potency, purity or
standard which is required to be maintained by or under any law for the time
being in force or under any contract, express or implied or as is claimed by
the trader in any manner whatsoever in relation to any goods".
"Service" is defined in Section 2(o) to mean "service of any
description which is made available to potential users and includes provision
of facilities in connection with banking, financing, insurance, transport,
processing, supply of electrical or other energy, board or lodging or both,
housing construction, entertainment, amusement or the pureveying of news or
other information, but does not include the rendering of any service free of
charge or under a contract of personal service".
The Board is a statutory authority. It is a 'State' within the meaning of
Article 12 of the Constitution of India. As a State, the Board is expected to
discharge its statutory functions within a reasonable time having regard to the
fact that it undertakes an important public utility service. Its actions
besides being governed by the Electricity (Supply) Act and the regulations
framed thereunder, it must also fulfill the test of reasonableness as
envisioned under Article 14 of the Constitution of India.
What would be a reasonable period for supply of electrical energy to different
categories of consumers has been specified in the administrative circulars
issued as well as the regulations made by the Board itself. We find from the
records that the persons had applied for grant of electrical connection as far
back in 1986 and the Board had asked then to deposit the security amount only
sometimes in the year 1999. The complaints were filed as despite expiry of the
prescribed period, no electrical connection was given. If the Board was serious
to implement its own circular, it was obligatory on its part to draw a
blue-print so as to enable it to make supply of electrical energy to the consumers
in order of seniority of application upon procuring the requisite materials
therefor. It failed and/ or neglected to do so. It was also under an obligation
to notify the persons concerned stating the reasons why such supply could not
be made during the period specified in the administrative circular and/ or
regulations. The Board does not say that the said requirements were complied
with.
It is also idle to contend that the Board was cash-starved owing to any faulty
decision on the part of the State. If it suffered losses owing to any direction
issued by the State pursuant to any policy decision adopted by it, the same
being an internal matter between the State and the Board, the prospective
consumers cannot suffer therefor.
Furthermore, it is evident from the orders passed by the District Forums, State
Commission and the National Commission that no reason was assigned by the Board
as to why it could not comply with its administrative circulars/ regulations.
Section 24 of the Indian Electricity Act, 1910
mandates a licensee to grant electrical connection to an applicant. Although
the said provision is not applicable so far as the Board is concerned, as has
been noticed hereinbefore, it is bound to supply electrical energy. The
provisions contained therein also envisage supply of electrical energy within a
reasonable time. The Board being a deemed licensee under the Indian Electricity
Act having been constituted in terms of Section 5 of the Act ordinarily cannot
be heard to say that it was not in a position to supply electricity to a class
of consumers, having invited applications there for from them.
In this case, apparently, the Board was not in a position to supply electrical
energy to the consumers within a reasonable time from the date of issuance of
the demand notice. It not only failed to supply electrical energy to the 71
complainants who were before the National Commission but even failed to supply
electrical energy to those who had applied much prior thereto. Before the State
Commission and the National Commission, the primal contention of the Board was
that the claimants-Respondents could not have been given a march over others
who had filed applications prior to them. The National Commission rightly did
not find fault with such contention but secured the presence of the Chief
Engineer of the Board only for the purpose of ascertaining as to how soon
supply of electrical energy could be ensured to all concerned including the
claimants-Respondents.
Faced with the orders passed by the District Forums and State Commission and
having regard to its own stand taken before the National Commission, the Chief
Engineer gave an undertaking that all such connections would be given by 31st
March, 2004. From the aforementioned conduct of the authorities of the Board,
we have no doubt in our mind had the claimants-Respondents not knocked the
doors of the forum under the Consumer Protection Act, they might not have even
obtained electrical connection for years to come.
In the premises aforementioned, the Commission, in our opinion, has rightly
found that the Board having not made itself ready to supply electrical energy
to the agriculturists unjustly enriched itself with the money deposited by the
complainants without rendering any service in return. It is evident that the
Board wanted to fill its coffer with the amount of the security deposits and
other deposits made by the prospective buyers of electricity. It has also not
been denied that relying on or on the basis of the representations made by the
Board in terms of its circular letters and / or regulations, the prospective
consumers also spent a huge amount on construction of kotha and making
themselves ready for getting the electrical connection.
We are not oblivious of the fact that when public functionary is asked to
perform a statutory duty within a specified time, the provisions of the
statutes are normally held to be directory in nature. # [See P.T. Rajan Vs.
T.P.M. Sahir and Others, ] But the said principle would not apply in
cases when injustice or inconvenience to others would be caused who have no
control over those exercising the duty if such requirements are not essential
or imperative. [See Karnal Improvement Trust, Karnal Vs. Parkash Wanti (Smt.)
(Dead) and Another [ 9]
In Chandrika Prasad Yadav Vs. State of Bihar and Others [ ], this Court
held:
"31. The question as to whether a statute is directory or mandatory
would not depend upon the phraseology used therein. The principle as regards
the nature of the statute must be determined having regard to the purpose and
object the statute seeks to achieve." * [See also U.P. State
Electricity Board Vs. Shiv Mohan Singh and Another, 4]
Furthermore, there cannot be any doubt whatsoever that even if an order is
found to be not vitiated by reason of malice on fact but still can be held to
be invalid if the same has been passed for unauthorized purposes, as it would
amount to malice in law.
In Smt. S.R. Venkataraman Vs. Union of India, : ] this Court
observed:
"It is not therefore the case of the appellant that there was actual
malicious intention on the part of the Government in making the alleged
wrongful order of her premature retirement so as to amount to malice in fact.
Malice in law is however, quite different. Viscount Haldane described it as follows
in Shearer v. Shields: "A person who inflicts an injury upon another
person in contravention of the law is not allowed to say that he did so with an
innocent mind; he is taken to know the law, and he must act within the law. He
may, therefore, be guilty of malice in law, although, so far the state of his
mind is concerned, he acts ignorantly, and in that sense innocently."
Thus malice in its legal sense means malice such as may be assumed from the
doing of a wrongful act intentionally but without just cause or excuse, or for
want of reasonable or probable cause." *
In State of A.P. and Others Vs. Goverdhanlal Pitti [ ], this Court
observed:
"12. The legal meaning of malice is "ill-will or spite towards a
party and any indirect or improper motive in taking an action". This is
sometimes described as "malice in fact". "Legal malice" or
"malice in law" means "something done without lawful
excuse". In other words, "it is an act done wrongfully and wilfully
without reasonable or probable cause, and not necessarily an act done from ill
feeling and spite. It is a deliberate act in disregard of the rights of
others". (See Words and Phrases Legally Defined, 3rd Edn., London
Butterworths, 1989.)
13. Where malice is attributed to the State, it can never be a case of personal
ill-will or spite on the part of the State. If at all it is malice in legal
sense, it can be described as an act which is taken with an oblique or indirect
object. Prof. Wade in his authoritative work on Administrative Law (8th Edn.,
at p.414) based on English decisions and in the context of alleged illegal
acquisition proceedings, explains that an action by the State can be described
mala fide if it seeks to "acquire land" "for a purpose not
authorised by the Act" * [See also Chairman & MD, BPL Ltd. Vs.
S.P. Gururaja and Others, and P. Anjaneyulu vs. Chief Manager, A.P.
Circle, Bharat Sanchar Nigam Ltd., Govt. of India, Hyderabad and Another
- 2001 (3) ALD 313].
A 'State' within Article 12 of the Constitution of India must act fairly and
bona fide. It cannot act for a purpose which is wholly unauthorized and not
germane for achieving the object it professes whether under a statute or
otherwise. #
We do not, therefore, find any fault in the judgments of the National
Commission. However, before us a statement has been made that all connections
have been given to the claimants-Respondents within the period of
aforementioned 31.3.2004.
Keeping in view the said fact as also the peculiar facts and circumstances of
this case, we are of the opinion that the interest of justice shall be
sub-served if the directions issued by the National Commission is modified to
the extent that in stead and place of interest at the rate of 12% per annum,
the Appellants are directed to pay interest at the rate of 9% per annum and in
stead of compensation at the rate of Rs. 10, 000/- in each, compensation of Rs.
5000/- in each is directed to be awarded. These appeals are dismissed subject
to the aforementioned modifications. No costs.