SUPREME COURT OF INDIA
U.P.S.E.B.
Vs
Sant Kabir Sahakari Katai Mills Limited
Appeal (Civil) 7965 of 2001, Civil Appeal Nos. 7966 to 7973 of 2001, 7990 to 7991 of 2001
(Arijit Pasayat and H.K.Sema)
19/09/2005
ARIJIT PASAYAT, J.
These appeals are directed against the judgments rendered by a Division Bench
of the Allahabad High Court. The main judgment was rendered in Civil Misc. Writ
Petition no. 5859 of 1999 which is the subject-matter of challenge in Civil
Appeal No. 7965 of 2001. Following the judgment rendered in the said case other
writ petitions were disposed of. In each of the writ petitions filed before the
High Court correctness of the electricity bills raised by the appellant
no.1-Uttar Pradesh State Electricity Board (hereinafter referred to as the
'Board') was questioned.
The High Court by the impugned judgment held that the Board was as authority
under Article 12 of the Constitution of India, 1950 (in short 'the
Constitution') and similar was the position so far as the writ petitioners are
concerned who according to the High Court were Public Sector Undertakings. The
High Court held that in cases where the dispute involves the State Government
and a Public Sector Undertaking, Committee in the line indicated by this Court
in Oil and Natural Gas Commission and Another v. Collector of Central Excise
(for convenience referred to as ONGC-I) should be set up. Accordingly it
was observed that the writ petitioners would move the State through the Chief
Secretary to constitute a Committee to resolve the dispute. Further direction
was given to the effect that the power supply to the writ petitioners was not
to be discontinued.
According to the appellant-Board factual position is as follows:-
"State Government issued a notification under Section 22-B of the Indian Electricity Act, 1910 (in short 'Electricity Act')
titled as Uttar Pradesh Electricity (Regulation of Distribution, Consumption)
Order 1972 (in short the '1972 Order') which imposed certain restrictions on
various categories of consumers for using electricity during certain periods.
The 1972 Order was repealed and in the year 1977 another Notification under
Section 22-B, known as Uttar Pradesh Electricity (Regulation of Supply,
Distribution, Consumption and Use) Order 1977 (in short '1977 Order') was
issued. In this order consumers were divided into several categories and so far
as the Industrial Consumers are concerned two categories were indicated.
They are "Continuous Process Industries Power Consumers" and
"Non-continuous Process Industries Power Consumers". List of
consumers belonging to the aforesaid category was annexed as Annexure 2 of the
said Order. It was provided in the 1977 Order that Non-continuous Process
Industries Power Consumers would not use electricity from 18.00 to 22.00 hours
every day. It meant that the distinction between the Continuous Process
Industries Power Consumers and the Non- Continuous Process Industries Power
Consumers was that peak hours restrictions, not to use electricity were not applicable
in case of Continuous Process Industries Power Consumers. The spinning mills
and textiles Mills were exempted from observing power cutting during peak hours
as per clause 8 of the Order and thus these industries also were covered by
category "Continuous Process Industries". *
The Writ Petitioners were co-operative societies registered under Uttar Pradesh
Co-operative Societies Act, 1965. Undisputedly they had entered into agreements
with the Board and one of the clauses in the agreement provided that supply
shall be available to the consumers continuously during 24 hours of each day
and throughout whole period of agreement. This Clause was however, subject to
the following restrictions:
"Supplier shall not be responsible for the damages or otherwise on
account of accidental interruption of supply or stoppage or deficiency of
energy caused by any order or direction issued by the Government of U.P. or
resulting from fire, flood, temptest or any accident or from any strike or lock
out of workers or from any other cause beyond the control of the supplier but
the supplier shall make every effort to restore the supply as soon as
possible."*
Clause 20 of the Agreement provided that in case of any dispute between the consumer and the Board the matter was to be decided by a person nominated by the Chairman of the Board and the dispute can only be referred when the consumer pays outstanding dues. The said clause reads as follows:
"If any question or dispute or difference arises between the parties to
this agreement as to the interpretation or effect of any provisions or clause
herein contained or the construction thereof or as to any other matter thereof
or the rights, duties or liabilities of either party in connection therewith,
such question, dispute or difference shall be referred to the arbitration of
the Chairman, U.P. State Electricity Board or the person nominated by him and
the award/decision of the said arbitrator shall be final and binding upon the
parties.
Provided that if the question, dispute or difference relates to or concerns any
dues chargeable to the Consumer in terms of this agreement, no reference to
arbitration shall at the instance of such consumer be made till the consumer
has either deposited with the supplier the amount of dues in dispute or
difference or given a Bank Guarantee of such amount in favour of the Supplier
valid upto the period of one year from the date in which the award becomes
final or the amount or dues is cleared, whichever is earlier." *
In the year 1984 in exercise of powers conferred under Section 49 read with
Section 79 of the Electricity Supply Act, 1948 (in
short the 'Supply Act') the Uttar Pradesh Electricity Supply (Consumers
Regulation) 1984 (in short the 'Regulations') was framed. The regulations have
statutory force and Regulation 14 has considerable significance so far as the
present cases are concerned. It reads as follows:
"Regulation 14: Failure of supply
The supplier shall not be liable for any claim for any loss, damage or compensation,
whatsoever arising out of any accidental failure of supply or stoppage or
curtailment of diminution or variation in supply or for failure restoring as a
result of any direct or indirect strike or order of the Government or other
competent Authority in regard to distribution of power or due to war, mutiny,
commotion, Riot, strike, lockout, fire flood, lighting earthquake or other
causes beyond the control of the supplier." *
In 1986 a Notification dated 28.1.1986 was issued categorizing the industrial
consumers into two categories i.e. Continuous Process Industries and
Non-Continuous Process Industries. Challenging the different rates fixed by the
Board, writ petitions were filed which were dismissed by the High Court
upholding the validity. It was held that it was a valid classification. Board
felt that the language of the Notification dated 28.1.1986 was not very clear
and therefore a corrigendum was issued clarifying the position that Continuous
Process Industries which are not observing peak hours restrictions have to pay
higher charges. Writ Petitions were filed challenging the levy of higher
charges.
The High Court allowed the levy from the date the corrigendum was issued. The
Board has filed appeals questioning the High Court's view. During pendency of
the appeals, writ petitions were filed alleging that uninterrupted power supply
was not given though higher rates were being charged. Therefore, it was claimed
that amounts paid, which were in excess of the amounts payable, should be adjusted
against the future bills along with interest. The High Court by its impugned
order held that the writ petitioners and the Board were 'State' within Article
12 of the Constitution, and directed a resolution of the dispute by a person to
be nominated by the Chief Secretary of State of U.P. It held that writ
petitioners were "Public Sector Undertakings".
According to the learned counsel for the appellant Board and its functionaries,
the approach of the High Court is clearly erroneous. Huge amounts have not been
paid by the respondents-writ petitioners. What was challenged before the High
Court was the levy of higher charges on the allegation that uninterrupted power
supply was not given. The decision in ONGC-I case (supra) has no application to
the facts of the present case. In any event, the High Court should not have
passed a blanket order of stay.
Learned counsel for the respondents on the other hand submitted that the
respondents are entitled to receive some amount from the appellants. According
to him, the payment raised is absolutely unreasonable and without any basis. It
was also submitted that disputes between public sector undertakings and the
State should be resolved in the line suggested by this Court in ONGC-I case
(supra). There is nothing wrong in the High Court's order granting interim
protection.
In ONGC-I case (supra) it was felt desirable that to avoid unnecessary
litigation, disputes between the Governments and the Public Sector Undertakings
should be sorted out by a Committee to be constituted. It was pointed out that
most of the disputes between the Public Sector undertakings and the Government
get resolved by meeting of minds.
It is certainly desirable that inter-departmental disputes and disputes between
Governments and Public Sector Undertakings should be sorted out in the manner
suggested by this Court in ONGC-I case (supra).
The stand of the learned counsel for the Board is that the operation of the
High Court's order was stayed and, therefore, the Committee as directed by this
Court has not been set up. The quantum of arrears in different cases has been
set out in the affidavit filed by the appellant-Board. They are as follows:
1. CIVIL APPEAL NO. 7965 Rs. 1, 65, 49, 000/-
2. CIVIL APPEAL NO. 7968 Rs. 6, 26, 73, 485/-
3. CIVIL APPEAL NO. 7970 Rs. 16, 62, 497/-
4. CIVIL APPEAL NO. 7971 Rs. 1, 04, 11, 681.02/-
5. CIVIL APPEAL NO. 7972 Rs. 1, 88, 85, 823/-
6. CIVIL APPEAL NO. 7990 Rs. 4, 98, 42, 000/- High Court equated the Board with
the State Government and held that the writ petitioners who were co-operative
societies were public sector undertakings.
The High Court's view is clearly untenable. Board cannot be equated with
State Government. Section 80 of the Code of Civil
Procedure, 1908 (in short 'CPC') is a pointer in that regard.
Co-operative Societies and Pubic Sector Undertakings are conceptually
different. The Board is a Public Sector Undertaking and not a State Government
department. It may be "State" for the purpose of Article 12 of the
Constitution. There the similarity ends. Co- operative Societies (writ
petitioners) cannot be, without examination of relevant factual aspects,
equated with Public Sector Undertaking. The High Court has come to abrupt
conclusion that they are Public Sector Undertakings without indicating any
reason for such conclusion. The High Court, therefore, was wrong in applying
ratio of ONGC-I case (supra) to the facts of the present cases. #
The view in ONGC-I case (supra) was further elaborated in Oil and Natural Gas
Commission v. C.C.E. 1995 (4) Supp(SCC) 541) (For sake of convenience
described as ONGC-II). It was noted in Oil and Natural Gas Commission v. C.C.E.
(for convenience described as ONGC-III) that some doubts and problems
arose in the working out of the arrangements in terms of the order of this
Court dated 11.10.1991 (ONGC-II case (supra). It was noted in ONGC-III case
(supra) as follows:
"There are some doubts and problems that have arisen in the working out
of these arrangements which require to be clarified and some creases ironed out.
Some doubts persist as to the precise import and implications of the words
"and recourse to litigation should be avoided". It is clear that the
order of this Court is not to the effect that nor can that be done so far as
the Union of India and its statutory corporations are concerned, their
statutory remedies are effaced. Indeed, the purpose of the constitution of the
High-powered Committee was not to take away those remedies. The relevant
portion of the order reads: (SCC pp. 541-42 para 3) "3. We direct that the
Government of India shall set up a committee consisting of representatives from
the Ministry of Industry, the Bureau of Public Enterprises and the Ministry of
Law, to monitor disputes between Ministry and Ministry of the Government of
India, Ministry and public sector undertakings of the Government of India and
public sector undertakings in between themselves to ensure that no litigation
comes to court or to a tribunal without the matter having been first examined
by the Committee and its clearance for litigation. The Government may include a
representative of the Ministry concerned in a specific case and one from the
Ministry of Finance in the Committee. Senior officers only should be nominated
so that the Committee would function with status, control and discipline."
It is abundantly clear that the machinery contemplated is only to ensure that
no litigation comes to court without the parties having had an opportunity of
conciliation before an in-house committee." *
The matter was again examined in the case of Chief Conservator of Forest v.
Collector). In Paras 14 and 15 it was noted as follows:
"Under the scheme of the Constitution, Article 131 confers original
jurisdiction on the Supreme Court in regard to a dispute between two States of
the Union of India or between one or more States and the Union of India. It was
not contemplated by the framers of the Constitution or the C.P.C. that two
departments of a State or the Union of India will fight a litigation in a court
of law. It is neither appropriate nor permissible for two departments of a
State or the Union of India to fight litigation in a court of law. Indeed, such
a course cannot but be detrimental to the public interest as it also entails
avoidable wastage of public money and time. Various departments of the
Government are its limbs and, therefore, they must act in co-ordination and not
in confrontation.
Filing of a writ petition by one department against the other by invoking the
extraordinary jurisdiction of the High Court is not only against the propriety
and polity as it smacks of indiscipline but is also contrary to the basic
concept of law which requires that for suing or being sued, there must be
either a natural or a juristic person. The States/Union of India must evolve a
mechanism to set at rest all inter- departmental controversies at the level of
the Government and such matters should not be carried to a court of law for
resolution of the controversy. In the case of disputes between public sector
undertakings and Union of India, this Court in Oil and Natural Gas Commission
v. Collector of Central Excise * (referred) called upon the
Cabinet Secretary to handle such matters. In Oil and Natural Gas Commission
& Anr. v. Collector of Central Excise * 1995 (4) Suppl(SCC) 541) (referred),
this Court directed the Central Government to set up a Committee consisting of
representatives from the Ministry of Industry, the Bureau of Public Enterprises
and the Ministry of Law, to monitor dispute between Ministry and Ministry of
the Government of India, Ministry and public sector undertakings of the
Government of India and public sector undertakings in between themselves, to
ensure that no litigation comes to court or to a Tribunal without the matter
having been first examined by the Committee and its clearance for litigation.
The Government may include a representative of the Ministry concerned in a
specific case and one from the Ministry of Finance in the Committee. Senior
officers only should be nominated so that the Committee would function with
status, control and discipline.
The facts of this appeal, noticed above, make out a strong case that there is a
felt need of setting up of similar committees by the State Government also to
resolve the controversy arising between various departments of the State or the
State and any of its undertakings. It would be appropriate for the State
Governments to set up a Committee consisting of the Chief Secretary of the
State, the Secretaries of the concerned departments, the Secretary of Law and
where financial commitments are involved, the Secretary of Finance. The
decision taken by such a committee shall be binding on all the departments
concerned and shall be the stand of the Government. " *
The directions as noted above were quoted in Mahanagar Telephone Nigam Ltd. v.
Chairman, Central Board, Direct Taxes and another ) and were adopted in
paragraph 8. It was noted as follows:
"Undoubtedly, the right to enforce a right in a court of law cannot be
effaced. However, it must be remembered that courts are overburdened with a
large number of cases. The majority of such cases pertain to Government
Departments and/or public sector undertakings. As is stated in Chief
Conservator of Forests' case * (referred) it was not contemplated
by the framers of the Constitution or the Civil Procedure Code that two
departments of a State or Union of India and/or a department of the Government
and a public sector undertaking fight a litigation in a court of law. Such a
course is detrimental to public interest as it entails avoidable wastage of
public money and time.
These are all limbs of the Government and must act in co-ordination and not
confrontation. The mechanism set up by this court is not, as suggested by Mr.
Andhyarujina, only to conciliate between Government Departments. It is also set
up for purposes of ensuring that frivolous disputes do not come before courts
without clearance from the High Powered Committee. If it can, the High Powered
Committee will resolve the dispute. If the dispute is not resolved the Committee
would undoubtedly give clearance. However, there could also be frivolous
litigation proposed by a department of the Government or a public sector
undertaking. This could be prevented by the High Powered Committee. In such
cases there is no question of resolving the dispute. The Committee only has to
refuse permission to litigate. No right of the Department/public sector
undertaking is affected in such a case.
The litigation being of a frivolous nature must not be brought to court. To be
remembered that in almost all cases one or the other party will not be happy
with the decision of the High Powered Committee. The dissatisfied party will
always claim that its rights are affected, when in fact, no right is affected.
The Committee is constituted of highly placed officers of the Government, who
do not have an interest in the dispute, it is thus expected that their decision
will be fair and honest. Even if the Department/public sector undertaking finds
the decision unpalatable, discipline requires that they abide by it. Otherwise
the whole purpose of this exercise will be lost and every party against whom
the decision is given will claim that they have been wronged and that their
rights are affected. This should not be allowed to be done." *
The ONGC I to III cases (supra), Chief Conservator's case (supra) and Mahanagar
Telephone's case (supra) deal with disputes relating to Central Government,
State Government and Public Sector Undertakings. They have no application to
the facts of these cases as the High Court has not indicated any reason for its
abrupt conclusion that the writ petitioners are Public Sector Undertakings. In
the absence of a factual determination in that regard, the decisions can have
no application.
Accordingly, we set aside the impugned judgments of the High Court and remit
the matter for fresh consideration of the cases. As the matter is pending
consideration for a long time, it would be appropriate if the writ petitions
are disposed of early. It is made clear that if parties place material to show
that writ petitioners are Public Sector Undertakings then the High Court can
direct action in line with Chief Conservator of Forest's case (supra) and not
otherwise.
The appeals are accordingly disposed of. No costs.