SUPREME COURT OF INDIA
Shin Satellite Public Company Limited
Vs
Messrs Jain Studios Limited
Arbitration Petition 1 of 2005
(C. K. Thakker, JJ)
31.01.2006
JUDGMENT
C. K. THAKKER, J.
This Arbitration Petition is filed by the petitioner, Shin Satellite Public Co. Ltd. against the respondent, M/s Jain Studios Ltd. under sub-section (6) of Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as 'the Act'). It is prayed in the application that Hon'ble Mr. Justice M. L. Pendse (Retired) be appointed as Sole Arbitrator, or in the alternative, any other retired Judge of a High Court may be appointed as an Arbitrator. The Hon'ble the Chief Justice of India has nominated me to exercise power under sub-section (6) of Section 11 of the Act and that is how the matter has been placed before me for passing an appropriate order.
It is the case of the petitioner that it is a Company registered under the laws of Thailand, having its principal office in Thailand. The petitioner carries on the satellite business and has got three satellites in the orbit, viz., Thaicom-1, Thaicom-2 and Thaicom-3. The petitioner, through above satellites, provides broadcasting and internet services to various Companies/ firms in the world. The respondent is a Company duly registered under the Companies Act, 1956 having its registered office at New Delhi.
According to the petitioner, an agreement was entered into between the parties on August 10, 1999 for availing broadcasting services of the petitioner by the respondent. The agreement, inter alia, provided for supply of satellite services, payment of fees, etc. Clause 23 provided for arbitration in case of dispute arising from the interpretation or from any matter relating to the performance of the agreement or rights or obligations of the parties. Since the dispute arose between the parties, the petitioner, through advocate addressed a letter/notice to the respondent on September 9, 2004 demanding for arbitration under clause 23. The petitioner, in the said letter, stated that it had appointed Hon'ble Mr. Justice M.L. Pendse (Retired) as its arbitrator and called upon the respondent to appoint an arbitrator. The petitioner, however, received a letter dated 7th October, 2004 from the respondent's advocate contending that the arbitration clause was not legal and valid and clause 23 of the Arbitration Agreement could not be termed as 'Arbitration Clause'. According to the petitioner, thus, the respondent failed to appoint an arbitrator which compelled the petitioner-company to file present application under Section 11(6) of the Act. A prayer was, therefore, made to make an appointment of an arbitrator.
On March 17, 2005, notice was issued on the application. The learned counsel appeared on behalf of the respondent and waived service of notice. Time was sought to file counter-affidavit, which was granted.
A reply-affidavit was then filed by the respondent urging therein that the
Arbitration Agreement was not legal and valid. It was contended that Clause 23
contained a condition that the arbitrator's determination would be treated as
'final and binding between the parties' and the parties had waived 'all rights
of appeal or objection in any jurisdiction'. It was also submitted that the
disputes were to be resolved by arbitration under the rules of United Nations
Commission on International Trade Law (UNCITRAL). Whereas Agreement in question
dated August 10, 1999 provided that the arbitration would be held in Delhi in
accordance with Indian Law, under other two Agreements, the place of
arbitration was fixed at Singapore and London respectively, and the governing
law was English Law. It was, therefore, stated that in the present case also,
arbitration may be held in London or in Singapore, where arbitration
proceedings were going on between the parties.
The matter could not be heard finally as the question as to the nature of
function to be performed by the Chief Justice or his nominee under sub-section
(6) of Section 11 of the Act was referred to a seven-Judge Bench. In SBP &
Company v. Patel Engineering Ltd., 2005 (8) SCC 618 the point was finally
decided. It was held by majority that the function performed by the Chief
Justice or his nominee under Section 11(6) of the Act is a judicial function.
After the above decision, the matter was placed for hearing and both the sides
were heard.
The learned counsel for the petitioner contended that an agreement had been entered into between the parties which contained an arbitration clause and in accordance with the terms of the agreement, a letter/notice was issued by the petitioner to the respondent for referring the matter to an arbitrator. It was also stated that the petitioner has appointed Hon'ble Mr. Justice M.L. Pendse (Retd.) as its arbitrator and asked the respondent to appoint an arbitrator. The respondent, however, contended that the Arbitration Agreement was not legal and valid and arbitration clause was not in consonance with law. In the circumstances the petitioner has filed the present application which deserves to be allowed by appointing an arbitrator.
Learned counsel for the respondent, on the other hand, submitted that the petition is not maintainable as the so called arbitration clause can neither be said to be legal, nor in accordance with law and as such cannot be enforced. According to the counsel, the arbitration clause takes away completely the right of the parties to challenge the award passed by the arbitrator. Clause 23 of the agreement is not only in restrain of legal proceedings to be initiated in a competent court of law but is also against public policy. Such provisions are held to be unenforceable in several cases. The petitioner is, therefore, not entitled to seek enforcement of arbitration clause and the petition is liable to be dismissed.
On merits, it was submitted that three agreements had been entered into between the parties. Whereas, in other two cases, arbitration proceedings were held in foreign country, in this case the venue is Delhi. This would create enormous difficulties for both the parties. If an arbitration is held in London or in Singapore, the dispute can be decided along with other matters. It was stated that the respondent has no objection if the petitioner is agreeable to the suggestion of the respondent to hold arbitration out of India.
The question for consideration before me is whether the arbitration agreement is legal, valid and enforceable. Before considering respective contentions of learned counsel on the point, it would be appropriate if the relevant clauses of the agreement are considered. As already stated, the agreement had been entered into on 10th August, 1999. It was duly signed by the parties. It provides for resolution of disputes, if any, arising between the parties to the agreement. Clause 19 relates to "Governing Law" and declares that the rights and responsibilities of the parties would be governed by Indian Law. Clause 23 deals with arbitration and is, therefore, material and may be quoted in extenso:
"23. ARBITRATION
Any dispute arising from the interpretation or from any matter relating to the performance of this Agreement or relating to any right or obligation herein contained which cannot be resolved by the parties shall be referred to and finally resolved by arbitration under the rules of the United Nations Commission on International Trade Law (UNCITRAL). The arbitration shall be held in New Delhi and shall be in the English language. The arbitrator's determination shall be final and binding between the parties and the parties waive all rights of appeal or objection in any jurisdiction. The costs of the arbitration shall be shared by the parties equally." (emphasis supplied) Clause 20 is another relevant clause providing severability and reads thus:
"20. SEVERABILITY
If any provision of this agreement is held invalid, illegal or unenforceable
for any reason, including by judgment of, or interpretation of relevant law, by
any Court of competent jurisdiction, the continuation in full force and effect
of the remainder of them shall not be prejudiced."
The main contention of the learned counsel for the respondent is that clause 23
made the arbitrator's determination "final and binding between the
parties" and the parties have waived all rights of appeal or objection
"in any jurisdiction". According to the counsel, the said provision
is inconsistent with Section 28 of the Contract Act, 1872 as also against
public policy.
In reply, the learned counsel for the petitioner submitted that clause 23 is in
several parts and all parts are severable. It was expressly conceded before me
by the learned counsel for the petitioner that the italicized portion on which
reliance was placed by the learned counsel for the respondent is not in
consonance with law and is not enforceable. He, however, submitted that the
said part is independent of other parts and ignoring the offending part, the
remaining parts which are legal, valid and binding, can be enforced.
Moreover, the agreement itself provides for severability. Clause 20 of the
agreement declares that if any provision is held invalid, illegal or
unenforceable for any reason, it would not affect other clauses. It was,
therefore, submitted that ignoring the objectionable part relating to
acceptance of arbitrator's determination as 'final and binding' and waiving
right of objecting the award as unenforceable, the remaining parts can be
enforced. The petition, therefore, deserves to be allowed.
In the light of submissions of the learned counsel, let me consider the legal
position.
In Halsbury's Laws of England (Fourth Edition); Volume 9; Para 430; p. 297, it
has been stated: "430. Severance of illegal and void provisions. A
contract will rarely be totally illegal or void and certain parts of it may be
entirely lawful in themselves. The question therefore arises whether the
illegal or void parts may be separated or "severed" from the contract
and the rest of the contract enforced without them. Nearly all the cases arise
in the context of restraint of trade, but the following principles are
applicable to contracts in general.
First, as a general rule, severance is probably not possible where the
objectionable parts of the contract involve illegality and not mere void
promises. In one type of case, however, the courts have adopted what amounts
almost to a principle of severance by holding that if a statute allows works to
be done up to a financial limit without a licence but requires a licence above
that limit, then, where works are done under a contract which does not specify
an amount but which in the event exceeds the financial limit permitted without
licence, the cost of the works up to that limit is recoverable.
Secondly, where severance is allowed, it must be possible simply to strike out
the offending parts but the court will not rewrite or rearrange the contract.
Thirdly, even if the promises can be struck out as afore-mentioned, the court
will not do this if to do so would alter entirely the scope and intention of
the agreement.
Fourthly, the contract, shorn of the offending parts, must retain the
characteristics of a valid contract, so that if severance will remove the whole
or main consideration given by one party the contract becomes unenforceable.
Otherwise, the offending promise simply drops out and the other parts of the
contract are enforceable.
Reference may be made to Chitty on Contracts (29th Edition); Volume I; pp. 1048-49;
"16-188 Introductory. Where all the terms of a contract are illegal or
against public policy or where the whole contract is prohibited by statute,
clearly no action can be brought by the guilty party on the contract; but
sometimes, although parts of a contract are unenforceable for such reasons,
other parts, were they to stand alone, would be unobjectionable. The question
then arises whether the unobjectionable may be enforced and the objectionable
disregarded or "severed". The same question arises in relation to
bonds where the condition is partly against the law. 16-189
Partial statutory invalidity. It was laid down in some of the older cases that
there is a distinction between a deed or condition which is void in part by
statute and one which is void in part at common law. This distinction must now
be understood to apply only to cases where the statute enacts that an agreement
or deed made in violation of its provisions shall be wholly void. Unless that
is so, then provided the good part is separable from and not dependent on the
bad, that part only will be void which contravenes the provisions of the
statute. The general rule is that "where you cannot sever the illegal from
the legal part of a covenant, the contract is altogether void; but, where you
can sever them, whether the illegality be created by statute or by the common
law, you may reject the bad part and retain the good." Thus, a covenant in
a lease that the tenant should pay "all parliamentary taxes, " only
included such as he might lawfully pay, and a separate covenant to pay the
landlord's property tax, which it was illegal for a tenant to contract to pay,
although void, did not affect the validity of the instrument. In some
situations where there is a statutory requirement to obtain a licence for work
above a stipulated financial limit but up to that limit no licence is required,
the courts will enforce a contract up to that limit. There is some doubt
whether this applies to a lump sum contract "for a single and indivisible
work." Even in this situation if the cost element can be divided into its
legal and illegal components, the courts will enforce the former but not the
latter." (emphasis supplied)
It is no doubt true that a court of law will read the agreement as it is and
cannot rewrite nor create a new one. It is also true that the contract must be
read as a whole and it is not open to dissect it by taking out a part treating
it to be contrary to law and by ordering enforcement of the rest if otherwise
it is not permissible. But it is well-settled that if the contract is in
several parts, some of which are legal and enforceable and some are
unenforceable, lawful parts can be enforced provided they are severable.
The learned counsel for the petitioner, in my opinion, rightly submitted that
the court must consider the question keeping in view settled legal position and
record a finding whether or not the agreement is severable. If the court holds
the agreement severable, it should implement and enforce that part which is
legal, valid and in consonance of law.
In several cases, courts have held that partial invalidity in contract will not
ipso facto make the whole contract void or unenforceable. Wherever a contract
contains legal as well as illegal parts and objectionable parts can be severed,
effect has been given to legal and valid parts striking out the offending parts.
In Goldsoll v. Goldman, 1914 (2) Ch 603, the defendant was a dealer in
imitation jewellery in London. He sold his business to the plaintiff and
covenanted not to compete with the plaintiff as a "dealer in real or
imitation jewellery in any part of the United Kingdom, the United States of
America, Russia or Spain". When the covenant was sought to be enforced, it
was contended that the same was in restrain of a trade and could not be
enforced. It was, however, held that the covenant was unreasonable and unenforceable
insofar as it extended to 'real' jewellery and also to competition outside the
United Kingdom. But it was valid, reasonable and enforceable with regard to
rest, namely, dealing in imitation jewellery and in United Kingdom. According
to the Court, the words "real or" and the listed places outside the
United Kingdom could be severed leaving only reasonable covenant which was
enforceable.
In Attwood v. Lamont, 1920 (2) KB 146, the plaintiff was carrying on business as a draper, tailor and general outfitter at Kidderminster. By a contract for employment, the defendant agreed with the plaintiff that he would not, at any time thereafter "either on his own account or on that of any wife of his or in partnership with or as assistant, servant or agent to any other person, persons or company carry on or be in any way directly or indirectly concerned in any of the following grades or businesses, that is to say, the trade or business of a tailor, dressmaker, general draper, milliner, hatter, haberdasher, gentlemen's, ladies' or children's outfitter at any place within a radius of ten miles of" Kidderminster. The defendant, however, subsequently set up business as a tailor at Worcester, outside the ten miles limit, but obtained and executed tailoring orders in Kidderminster. When the plaintiff brought an action, it was contended by the defendant that the agreement was illegal and could not be enforced. The Court, however, held that various parts of the contract were severable and valid part thereof could be enforced. Upholding the argument of the plaintiff and granting relief in his favour, the Court observed that the Courts would sever in a proper case, where the severance can be made by using a 'blue pencil'. But it could be done only in those cases where the part so enforceable is clearly severable and not where it could not be severed. By such process, main purport and substance of the clause cannot be ignored or overlooked. Thus, a covenant "not to carry on business in Birmingham or within 100 miles" may be severed so as to reduce the area to Birmingham, but a covenant "not to carry on business within 100 miles of Birmingham" will not be severed so as to read "will not carry on business in Birmingham". The distinction may appear to be artificial, but is well-settled.
In Re Davstone Estates Ltd.'s Leases, Manprop, Ltd. v. O'Dell & Ors., 1969 Indlaw CHD 83, on which reliance was placed by the learned counsel for the respondent, is clearly distinguishable. In that case, the Court held that the agreement entered into between the parties was opposed to public policy and hence was not enforceable.
Similarly, Kall-Kwik Printing (U.K.) Limited v. Frank Clearence Rush, 1996 FSR
114, instead of supporting the respondent, helps the petitioner. There it was
observed that if the covenant is severable, it could be implemented by applying
the 'blue pencil' test.
The legal position in India is not different.
In Coringa Oil Co. v. Koegler, 1876 (1) ILR(Cal) 466, a clause in the
agreement stated that all disputes be referred to arbitrator of two competent
London Brokers and their decision would be 'final'. Dealing with the question
of legality of such clause, the Court held that the contract could be enforced
by excluding the part as regards challenge to such award. It would not affect
the jurisdiction of the court, and to that extent, the clause is not
enforceable. The other stipulation, however, would not become void or
inoperative
.
In Babasaheb Rahimsaheb v. Rajaram Raghunath, 1931 AIR(Bom) 264, there
were several clauses in the contract. When the question as to enforceability
came up before the court, it was held that if different clauses in an agreement
are separable, the fact that one clause is void does not necessarily cause the
other clauses to fail.
In Union Construction Co. (P) Ltd. v. Chief Engineer, Eastern Command, Lucknow & Anr., 1960 AIR(All) 72, a similar contention was raised that the Arbitration Agreement giving finality and conclusiveness was illegal and unenforceable as it was hit by Section 28 of the Contract Act. Clause 68 of the Arbitration Agreement, which was similar to the case on hand, read thus:
"68. Arbitration All
disputes, between the parties to the Contract arising out of or relating to the
Contract, other than those for which the decision of the C.W.E. or of any other
person is by the Contract expressed to be final and conclusive, shall after
written notice by either party to the Contract to the other of them be referred
to the sole arbitration of an Engineer. Officer to be appointed by the
authority mentioned in the tender documents.
Unless the parties otherwise agree, such reference shall not take place until
after the completion, alleged completion or abandonment of the Works or the
determination of the Contract.
The venue of Arbitration shall be such place or places as may be fixed by the
Arbitrator in his sole discretion.
The award of the Arbitrator shall be final, conclusive and binding on both
parties to the Contract." (emphasis supplied)
The Court held that the sub-clause making the award 'final and conclusive' was
clearly separable from the main clause which made reference to an arbitrator
imperative. "The existence of the sub-clause or the fact that the sub-
clause appears to be void does not in any way affect the right of the parties
to have recourse to arbitration and does not make a reference to an arbitrator
any the less an alternative remedy."
In the present case, clause 23 relates to arbitration. It is in various parts.
The first part mandates that, if there is a dispute between the parties, it
shall be referred to and finally resolved by arbitration. It clarifies that the
rules of UNCITRAL would apply to such arbitration. It then directs that the
arbitration shall be held in Delhi and will be in English language. It stipulates
that the costs of arbitration shall be shared by the parties equally. The
offending and objectionable part, no doubt, expressly makes the arbitrator's
determination "final and binding between the parties" and declares
that the parties have waived the rights of appeal or objection "in any
jurisdiction". The said objectionable part, in my opinion, however, is
clearly severable as it is independent of the dispute being referred to and
resolved by an arbitrator. Hence, even in the absence of any other clause, the
part as to referring the dispute to arbitrator can be given effect to and
enforced. By implementing that part, it cannot be said that the Court is doing
something which is not contemplated by the parties or by 'interpretative
process', the Court is re-writing the contract which is in the nature of
'novatio'. The intention of the parties is explicitly clear and they have
agreed that the dispute, if any, would be referred to an arbitrator. To that
extent, therefore, the agreement is legal, lawful and the offending part as to
the finality and restraint in approaching a Court of law can be separated and
severed by using a 'blue pencil'.
The proper test for deciding validity or otherwise of an agreement or order is 'substantial severability' and not 'textual divisibility'. It is the duty of the court to severe and separate trivial or technical part by retaining the main or substantial part and by giving effect to the latter if it is legal, lawful and otherwise enforceable. In such cases, the Court must consider the question whether the parties could have agreed on the valid terms of the agreement had they known that the other terms were invalid or unlawful. If the answer to the said question is in the affirmative, the doctrine of severability would apply and the valid terms of the agreement could be enforced, ignoring invalid terms. To hold otherwise would be "to expose the covenanter to the almost inevitable risk of litigation which in nine cases out of ten he is very ill able to afford, should he venture to act upon his own opinion as to how far the restraint upon him would be held by the court to be reasonable, while it may give the covenantee the full benefit of unreasonable provisions if the covenanter is unable to face litigation."
The agreement in the instant case can be enforced on an additional ground as
well. As already noted, clause 20 (Severability) expressly states that if any
provision of the agreement is held invalid, illegal or unenforceable, it would
not prejudice the remainder. In my view, clause 20 makes the matter free from
doubt. The intention of the parties is abundantly clear and even if a part of
the agreement is held unlawful, the lawful parts must be enforced. Reference of
a dispute to an arbitrator, by no means can be declared illegal or unlawful. To
that extent, therefore, no objection can be raised by the respondent against
the agreement.
It may be stated here that on behalf of the respondent, it was submitted that
if the matter is referred to arbitration in London or in Singapore, it had no
objection. But as the Arbitration Agreement provides 'Delhi' as the venue and
since that part of the agreement is enforceable, the prayer of the respondent
cannot be granted.
Finally, it was submitted by the respondent that if this Court is not upholding
the objection of the respondent and is inclined to grant the prayer of the
petitioner, some time may be granted to the respondent to make an appointment
of an arbitrator. It was not done earlier because according to the respondent,
clause 23 was not enforceable. The learned counsel for the petitioner objects
to such a prayer. According to him, a letter/notice was issued and in spite of
request by the petitioner, the respondent had failed to exercise his right to
appoint an arbitrator. At this belated stage, now, the respondent cannot be
permitted to take advantage of its own default. In my opinion, since there is
failure on the part of the respondent in making an appointment of an arbitrator
in accordance with the agreement, the prayer cannot be granted.
For the foregoing reasons, the arbitration petition stands allowed and Hon'ble
Mr. Justice M.L. Pendse (Retired) is accordingly appointed as Sole Arbitrator.
In the facts and circumstances of the case, there shall be no order as to
costs.
(C.K. Thakker) New Delhi, January 31 , 2006.
In Babasaheb Rahimsaheb v. Rajaram Raghunath Alpe, 1931 AIR(Bom) 264,
there were several clauses in the contract. The parties were wrestlers and
agreed to wrestle in Poona on a particular day. It was void that if either of
them failed to turn up, then he was to forfeit Rs.500/- to the opposite party
and the winner was to receive Rs.1125/- as gate money. The defendant failed to
turn up in the ring and the plaintiff sued him for Rs.500/-. It was contended
on behalf of the defendant that the contract was a wagering contract and the
plaintiff could not enforce it. The plea, however, was negatived. The Court
observed:
"In an agreement, if different clauses are separable, the fact that one
clause is void does not necessarily cause the other clauses to fail. In the
present case, we are not satisfied that Cl.2, which is now in question, cannot
be separated from the last clause, and even on the view put forward by the
petitioner the claim based on Cl.2 would appear to be legal. But even the last
point raised by the petitioner is not in our opinion proved. The words in the
English statute are somewhat different. It is to be noted that in the present
case the stakes did not come out of the pockets of the parties, but had to be paid
from the gate money provided by the public".
In Union Construction Co. (Private Ltd.) v. Chief Engineer, Eastern Command,
Lucknow and Anr., 1960 AIR(All) 72, a similar contention was raised that the
Arbitration Agreement giving finality and conclusiveness was illegal and not
enforceable, has been hit by Section 28 of the Contract Act but the contention
was negatived. Clause 68 of the Arbitration Agreement which is akin to the case
in hand read thus:
"68. Arbitration. All disputes, between the parties to the Contract arising out of or relating to the Contract, other than those for which the decision of the C.W.E. or of any other person is by the Contract expressed to be final and conclusive, shall after written notice by either party to the Contract to the other of them be referred to the sole arbitration of an Engineer. Officer to be appointed by the authority mentioned in the tender documents.
Unless the parties otherwise agree, such reference shall not take place until
after the completion, alleged completion or abandonment of the Works or the
determination of the Contract.
The venue of Arbitration shall be such place or places as may be fixed by the
Arbitrator in his sole discretion.
The award of the Arbitrator shall be final, conclusive and binding on both
parties to the Contract."
According to the Court, the sub-clause making the award final and conclusive
was clearly seperable from the main clause which makes a reference to an
arbitrator imperative. "The existence of the sub-clause or the fact that
the sub-clause appears to be void does not in any way affect the right of the
parties to have recourse to arbitration and does not make a reference to an
arbitrator any the less an alternative remedy." Similar questions also
came up for consideration while dealing with Article 13 of the Constitution.
The said Article indicates that laws inconsistent with or in derogation of the
Fundamental Rights contained in Part III of the Constitution would "to the
extent of such inconsistency, be void". In R.M.D.Chamarbaugwalla &
Anr. v. Union of India & Anr. 1957 SCR 930 : the Constitution
Bench of this Court held that when an Act is held to be inconsistent with the
Constitution, it ca partly be saved, if it satisfies the test of severability.
When a statute is in part- wise, it will enforce the rest if it is severable
from what is invalid. The Court summarized the principles as follows:
1. In determining whether the valid parts of a statute are separable from the
invalid parts thereof, it is the intention of the legislature that is the
determining factor. The test to be applied is whether the legislature would
have enacted the valid part if it had known that the rest of the statute was
invalid. Vide Corpus Juris Secundum, Vol. 82, p. 156; Sutherland on Statutory
Construction, Vol. 2, pp. 176-177.
2. If the valid and invalid provisions are so inextricably mixed up that they
cannot be separated from one another, then the invalidity of a portion must
result in the invalidity of the Act in its entirety. On the other hand, if they
are so distinct and separate that after striking out what is invalid, what
remains is in itself a complete code independent of the rest, then it will be
upheld notwithstanding that the rest has become unenforceable. Vide Cooley's
Constitutional Limitations, Vol. 1 at pp. 360- 361; Crawford on Statutory
Construction, pp. 217-218.
3. Even when the provisions which are valid are distinct and separate from
those which are invalid, if they all form part of a single scheme which is
intended to be operative as a whole, then also the invalidity of a part will
result in the failure of the whole. Vide Crawford on Statutory Construction,
pp. 218-219.
4. Likewise, when the valid and invalid parts of a statute are independent and
do not form part of a scheme but what is left after omitting the invalid
portion is so thin and truncated as to be in substance different from what it
was when it emerged out of the legislature, then also it will be rejected in
its entirety.
5. The separability of the valid and invalid provisions of a statute does not
depend on whether the law is enacted in the same section or different sections;
(Vide Cooley's Constitutional Limitations, Vol. 1, pp. 361-362); it is not the
form, but the substance of the matter that is material, and that has to be
ascertained on an examination of the Act as a whole and of the setting of the
relevant provisions therein.
6. If after the invalid portion is expunged from the statute what remains
cannot be enforced without making alterations and modifications therein, then
the whole of it must be struck down as void, as otherwise it will amount to
judicial legislation. Vide Sutherland on Statutory Construction, Vol. 2, p.
194.
7. In determining the legislative intent on the question of separability, it
will be legitimate to take into account the history of the legislation, its
object, the title and the preamble to it. Vide Sutherland on Statutory
Construction, Vol. 2, pp. 177-178.
It is an accepted principle of law that while interpreting statutory
provisions, the Court would attempt to find out the intention of the
Legislature and try to save statute to the extent it is possible.
Read Dickerson has suggested:
"... The Courts are at least free from control by original
legislatures. Curtis, for one, has contended that consistently with the
ascertained meaning of the statute, a court should be able to shake off the
dust of the past plant its feet firmly in the present.
..... The Legislature which passed the stature has adjourned and its members
gone home to their constituents or to a long rest from all law making. So why
bother about what they intended or what they would have done ? Better be
prophetic than archaeological, better deal with the future than with the past,
better pay a decent respect for a future legislature than stand in awe of one
that has folded up its papers and jointed its friends at the country club or in
the cemetery....
..... Let the Courts deliberate on what the present or a future legislature
would do after it had read the court's opinion, after the situation has been
explained, after the Court has exhibited the whole fabric of the law into which
this particular bit of legislation had to be adjusted."
In Attwood v. Lamont 1920 (2) KB 146, the plaintiff was carrying on
business as a draper, tailor and general outfitter. By a contract for
employment, the defendant agreed with the plaintiff that he would not, at any
time thereafter "either on his own account or on that of any wife of his
or in partnership with or as assistant, servant or agent to any other person,
persons or company carry on or be in any way directly or indirectly concerned
in any of the following grades or businesses, that is to say, the trade or business
of a tailor, dressmaker, general draper, milliner, hatter, haberdasher,
gentlemen's, ladies' or children's outfitter at any place within a radius of
ten miles of" Kidderminister. The defendant subsequently set up business
as a tailor at Worcester, outside the ten miles limit, but obtained and
executed tailoring orders in Kidderminister. When the plaintiff approached a
Court of law, it was contended by the defendant that the agreement was illegal
and could not be enforced. The Court however held that various parts were
severable and that valid part could be enforced. Upholding the argument of the
plaintiff, the Court observed that the Courts would sever in a proper case,
where the severance can be performed by a blue pencil but not otherwise. It was
however observed that this can be done only in those cases where the part so
enforceable is clearly severable and not where it would not be severed. By the
said process, main purport and substance of the clause can be ignored.
In Re Davstone Estates Ltd.'s Leases, Manprop, Ltd. v. O'Dell & Ors. 1969 Indlaw CHD 83, on which reliance was placed by the learned counsel for the respondent, is clearly distinguishable. In that case, the Court held that the agreement entered into was not legal and valid and hence was not enforceable. Similarly, Kall-Kwik Printing (U.K.) Limited v. Frank Clearence Rush [1996] F.S.R. 114 also does not help the respondent. On the contrary, in the said case it was held that if the covenant is severable, the same can be implemented. In the present case, clause 23 relates to arbitration, mainly it is in four parts. The first part states that, if there is dispute between the parties, it shall be referred to and finally resolved by arbitration. It also says that the rules of UNCITRAL would apply to such arbitration. It then states that the arbitration shall be held in Delhi and will be in English language. It also states that the costs of arbitration shall be shared by the parties equally. The disputed part declares the arbitrator's determination as "final and binding between the parties" and also that parties have waived the rights of appeal or objection in any jurisdiction. The said objectionable part, in my opinion, is clearly severable as it is independent of matter being raised to and decided by an arbitrator. Therefore, even in the absence of any other clause, the said part can be given effect to and enforced. By implementing the said part, it cannot be said that the Court is doing something which is not contemplated by the parties or by interpretative process, the Court is re-writing a contract which is in the form of novatio. The intention of the parties is abundantly clear that in case of dispute, the matter must be referred to arbitrator. To that extent, therefore, the agreement is legal, valid, in accordance with law and enforceable.
In the instant case, such an agreement can be enforced even on an additional
ground and that is clause 20 (severability). The said clause expressly states
that if any provision of the agreement is held invalid, illegal or
unenforceable, it would not prejudice the remainder. In my judgment, therefore,
the intense of the parties is abundantly clear that in case of dispute the
matter was to be referred to arbitrator and to that extent, no objection can be
raised by the respondent.
In fact, on behalf of the respondent also, it was submitted that if the matter
is referred to arbitration in foreign country, it had no objection but as the
Arbitration Agreement in question provides 'Delhi' as the venue and as such a
provision is enforceable, the prayer of the respondent cannot be accepted.
Finally, it was submitted that if this Court is not upholding the objection of
the respondent and inclined to grant the prayer of the petitioner, some time
may be granted to make an appointment of an arbitrator which was not done
earlier because according to the respondent, there was no provision in the
agreement for arbitration and clause 23 was not enforceable. The learned
counsel for the petitioner has objected to such a prayer, according to him, a
letter/notice was issued and in spite of a request has been made, the
respondent had failed to exercise his right to appoint an arbitrator and at
this belated stage, no such prayer deserves to be granted. In my opinion, since
there is failure on the part of the respondent in making of appointment in
accordance with the agreement, the prayer cannot be granted.
For the foregoing reasons, the arbitration petition stands allowed and Hon'ble
Mr. Justice M.L. Pendse (Retired) is accordingly appointed as Sole Arbitrator.
In the facts and circumstances of the case, there shall be no order as to
costs.