SUPREME COURT OF INDIA
State of Karnataka and Another
Vs
All India Manufacturers Organisation and Others
Civil Appeal Nos .3492 to 3494 of 2005 Connected With Civil Appeal Nos.3497, 3842, 3844, 3848 to 3884, 3889 to 4127 and Etc.Of 2005 :61, 73, 74 to 76 of 2006 and Civil Appeal No 2141 of 2006 and Slp(c ) Nos 1562 and 1563 of 2006
((Mrs.) Ruma Pal, B. N. Srikrishna, JJ)
20.04.2006
B. N. SRIKRISHNA, J.
Leave granted in Special leave Petition (C) Nos 1562 and 1563 of 2006
2 since this matter consists of two sets of distinct but related appeals, for
the sake of convenience, they may be considered under the two heads of: (i) the
Main Matters; and (ii) the Land Acquisition Matters.
The Main Matters (Civil Appeal Nos. 3492 to 3494, 3497 and 3842 to 3844 of
2005)
The Background
3.These appeals are directed against a common judgment of the High Court of
Kamataka by which three Public Interest Litigations being in All India
Manufacturers Organisation, Bangalore v State of Kamataka and Other 2005
(3) KarLJ 438 (DB)]); J.C. Madhuswamy and Others v State of Karnotaka and
Others[W.P. No. 45386 of 2004, dated 3-5-2005] and Dakshinamurthy and Another v
State of Kamataka and Others[W.P. No. 48981 of 2004, dated 3-5-2005], were
disposed of resulting in dismissal of Mr. J.C. Madhuswamy's writ petition and a
direction to the State of Kamataka to continue to implement a certain project
known as the "Bangalore-Mysore Infrastructure Corridor Project"
(hereinafter "the Project").
4.A brief statement regarding the Project: Bangalore is the capital of the
State of Kamataka and a rapidly developing city, which is projected to be the
IT boom town in the country. As a result of the pressures of urbanisation and
industrialisation, the infrastructure in and around Bangalore was found to be
inadequate. The traffic situation in Bangalore and on the roads leading into
and out of the city was found to be chaotic and hardly conducive to the
important role that the city is expected to play in the near future. The
Government of Kamataka, realising the importance of rapidly developing the city
of Bangalore, and also for developing its transport and communication systems,
conceived of the Project. The Project had twin objectives: firstly, to provide
for an express highway linking Bangalore with Mysore, the former capital of the
erstwhile State of Mysore, which is now coming up as an industrial town, and
for developing infrastructure along the corridor and in and around Bangalore
city. The Project is a massive undertaking, which requires design,
construction, maintenance and operation of an Express Highway between Bangalore
and Mysore. Equally, the Project is to also develop infrastructure around the
periphery of Bangalore and all along the Bangalore-Mysore Express Highway,
which is about hundred years old and has become incapable of handling the heavy
volume of vehicular traffic.
5.On 28-9-1988, the State of Karnataka invited tenders for implementation of
such an Express Highway. There was no satisfactory response to the tenders
called for. There was only one tenderer and the tenderer insisted on certain
conditions which were not acceptable to the Government of Kamataka. Thus, the
bid of the tenderer was not accepted. A survey was conducted by the Asian
Development Bank and its report pointed out that the projected population of
Bangalore city would be about 8.2 million by the year 2011 and, therefore,
there was an urgent need for improvement of the Bangalore-Mysore Corridor. It was
also suggested that the State Government bear 20% of the project cost, along
with the cost of land acquisition, if such a project was to be implemented. The
State Government did not have sufficient means and had to look for other
alternative ways for implementing this project. The State Government then
decided to take up the project on a Build-Own-Operate-Transfer (hereinafter
"BOOT") basis with any consortium. The consortium was to carry out
the development of the project from its own resources and recoup its investment
by collection of tolls along the Express Highway.
6.On 20-2-1995, a Memorandum of Understanding (hereinafter "MOU") was
entered into between the State Government and the Consortium of Vanasse Hangen
Brustlin Inc. USA (hereinafter "VHB"), Kalyani Group of Companies
(hereinafter "Kalyani") and SAB Engineering and Construction Inc. USA
(hereinafter "SAB"). The Governor of the State of Massachusetts,
U.S.A., Mr. William Weld and Mr. H.D. Deve Gowda, the then Chief Minister of
the State of Karnataka were present and appended their signatures thereto. It
was agreed that the State Government would extend support for the development
of the Bangalore-Mysore Expressway, provided commercial viability,
competitiveness and feasibility of the project was established to the
satisfaction of the State Government. The Consortium submitted a Project Report
for review by the State Government.
7.On 5-6-1995, a "High Level Committee" (hereinafter "the HKf)
was formed under the Chairmanship of the Minister for Public Works. The HLC
consisted of the Principal Secretary, Commerce and Industries Department;
Principal Secretary, Housing and Urban Development; Secretary, Public Works
Department; Chief Engineer C and B (South Zone, Bangalore). The Chairman and
Managing Director, Karnataka State Industrial Investment Development
Corporation were official members and the Chairman, Technical Advisory
Committee (Irrigation) one KC. Reddy was a non-official member. The HLC met
from time to time and reviewed the progress made in the implementation of the
Project. On 26-8-1995, the Consortium presented the details of the Project to
the HLC. After detailed consideration of the Project, on 12-10-1995 the HLC
submitted its report to the Government. The Project was considered in detail by
the State Cabinet Sub-Committee, which recommended that the matter be placed
before the Cabinet for consideration. The report of the HLC and the Project
report made by the consortium was accepted by the Cabinet, subject to the
modification that instead of seven townships as proposed in the Project Report,
only five townships were to be developed.
8A Government Order (No. PWD 32 CSR 95, Bangalore, dated 20-11-1995) ensued,
which in terms pointed out that the implementation of the Project was to be done
by a private Consortium. The preamble to the Government Order recited that the
Project work was to be completed by the Consortium with their own resources and
that the Consortium would keep the Project going for thirty years, so as to get
a return of the expenditure, profit, etc., through collection of tolls. It is
important to note that the land acquisition expenditure was also to be borne by
the Consortium. To make the Project economically viable, the Consortium had
proposed development of seven townships, which as already stated, was reduced
to five by the Cabinet. It is also important to note that the Government Order
specifically permitted the development of five townships along with the
construction of the Express Highway. As already stated, the Consortium was to
recoup its expenditure and obtain profits through tolls - the first system of
its kind in Karnataka. Consequently, it was felt that the modification of the
existing laws might become necessary. The necessary legal changes were to be
examined by the concerned administrative departments, who would take "...
necessary action and also extend co-operation for implementation of the
Project".
9.The three members of the Consortium - VHB, Kalyani and SAB entered into a
"Consent and Acknowledgement Agreement" (hereinafter "the
CAA"), dated 9-9-1996, specially assigning their respective rights under
the Government Order (dated 20-11-1995) and the MOU with regard to the Project,
in favour of Nandi Infrastructure Corridor Enterprises Limited (hereinafter
"Nandi"). Nandi had been registered on 16-1-1996 as a company under
the Companies Act, 1956, to serve as a corporate
vehicle for the development and implementation of the Project. On 21-12-1996,
the CAA was forwarded to the State Government for necessary action. The State
Government was advised by its Law Department (through Opinion No. 182 OPN
11/97, dated 3/4-3-1997) that since the Government was finalising a separate
agreement with Nandi, there was no need to specifically consent to the CAA.
Consequently, the State Government took no further action except noting it.
10.In February 1997, Nandi submitted a draft of the Framework Agreement
(hereinafter "the FWA") to be executed between it and the State
Government. This draft FWA was considered by the Core Committee, which had been
set up to negotiate the terms with Nandi. It was also referred to the Cabinet
Sub-Committee, which suggested certain modifications to the FWA. After due
incorporation of such modifications, the Government of Karnataka approved the
FWA on 17-3-1997 and the same was signed between Nandi and the Stat$ Government
on 3-4-1997.
11.Under Clause 4.1.1 of the FWA, the State Government set up an
"Empowered Committee" headed by the Chief Secretary of the State to oversee
the Project and its implementation keeping in mind the importance of timely
completion. The Empowered Committee included technical experts and held about
ten meetings from time to time, the last one being on 24-7-2004. The main task
of the Empowered Committee was to remove administrative bottlenecks and to
ensure the smooth execution of the Project. The Empowered Committee was the
State's agent of coordination and carried out the State Government's
obligations under the FWA.
12.One of the key obligations of the State Government under the FWA was to make
available approximately 20, 193 acres of land. As set out in Schedule I to the
FWA, 6, 956 acres was Government land and the remaining 13, 237 acres was
private land, which was to be acquired by the State Government. There was also
an undertaking by the State Government under the FWA to carry out appropriate
amendments to its laws, rules and regulations so that the massive Project could
be implemented fully and within a time-bound schedule. Accordingly, the
provisions of the Karnataka Industrial Areas Development Act, 1966 ("the
KIAD Act") were amended by Act No. 11 of 1997 so that the land required
for the Project could be acquired expeditiously. The Karnataka Industrial Areas
Development Board ("KIAD Board") set up under the KIAD Act, entered
into an agreement with Nandi on 14-10-1998 for acquisition of private land.
Notifications were issued from time to time for acquiring lands for the
Project.
The Litigation in Somashekar Reddy
13.While all these frenetic activities were going on for the successful and
timely implementation of the Project, the FWA was challenged in a Public
Interest Writ Petition No. 29221 of 1997, dated 21-9-1998 (reported as H.T.
Somashekar Reddy u Government of Karnataka and Another 2000 (1) KarLJ 224
(DB): 1999 (1) KLD 500 (DB) ]) by one H.T. Somashekar Reddy, a retired
Chief Engineer. The State Government and Nandi were the two respondents
thereto. The FWA was challenged on all conceivable grounds and the writ petition
was vigorously opposed by the State Government and also by Nandi. Both the
State Government and Nandi contended that the FWA was valid and that it had
been entered into in larger public interest. It was also successfully pleaded
on the part of the State Government that it had agreed to provide the
"minimum extent of land" for the Project, which was 20, 193 acres of
land and that no excess land was being acquired.
14.The Division Bench of the Karnataka High Court hearing the said writ
petition formulated for its consideration, the following questions.-
"(a) Whether the Government has acted arbitrarily in entering into the
agreement with respondent 2?
(b).Whether agreement is illegal as being opposed to public policy?
( c) .Whether the agreement contravenes any Constitutional provisions or other
existing enactments?
(d).Whether the agreement is vitiated by mala fides?
(e).Whether the rights of any individual or groups of individuals is being
illegally affected by the execution of the agreement?
(f).Scope and extent of judicial review in matters of State Policy?"
15.For the purpose of the present litigation, it is important to note that one
of the main grounds of challenge to the FWA in Somashekar Reddy was that land
was being acquired far in excess of what was required for the Project. In fact,
it was specifically stated in the writ petition that Article 7 of the FWA (that
provides for construction of townships) was the "most damaging provision
detrimental to the owners of land". Further, it was stated in the writ
petition that the land requirement in Schedule I of the FWA was "highly
exaggerated" and would illegally create "huge profits" for
Nandi. It was prayed that the FWA be quashed and further, since the FWA was
purportedly the result of "offences of breach of trust", for
institution of a Central Bureau of Investigation (hereinafter "CBI")
enquiry into the whole project.
16.Each of the questions was answered in favour of the respondents i.e., State
of Karnataka and Nandi. It was held that the FWA was not arbitrarily entered
into by the State Government; that it was not opposed to public policy; that it
was not unconstitutional or illegal; that it was not vitiated by mala fides;
that no rights of any individual or individuals had been illegally affected by the
execution of the agreement. Finally, the Court found that it could not exercise
its power of judicial review to interfere with the FWA which was in reality a
policy choice of the Government.
17.Further, as we shall discuss subsequently, the argument of excess land being
acquired, was not acceded to by the High Court which found that the Project
envisaged, in addition to the construction of an expressway between Bangalore
and Mysore, other connected developmental activities, such as:
"(i) Development of area between Bangalore-Mysore;
(ii) Divergence of traffic from Mysore-Chennai; Chennai-Bombay;
(iii) Construction of elevated road from Sirsi Circle up to 9.4 kms.; (iv)
Construction of 2 truck terminals;
(v) Development of five identified local areas into townships with all
infrastructure for habitation and economic activities;
(vi) Utilisation of sewage water being put to no productive use by BWSSB;
(vii) Development of tourism to augment the State's revenues".
18.Thus, through an exhaustive consideration of all the background material and
documents presented to it, the High Court dismissed the writ petition by
holding against the petitioner on all the contentions urged. The judgment of
Somashekar Reddy, was challenged before this Court (in SLP (Civil) CC No. 1423
of 1999) but was dismissed in limine on 26-3-1999. The judgment in Somashekar
Reddy, thus reached finality.
The present Litigation
19.Although the writ petition in Somashekar Reddy was dismissed by the High
Court by its judgment dated 21-9-1998, it is of relevance to notice that
between November 1997, when this writ petition was filed, and when the petition
was dismissed, the work of implementing the Project was going on in view of the
stand of the State Government and Nandi. Accordingly, a number of notifications
were issued for acquisition of the land required under the FWA. Many landowners
challenged the acquisition of their lands before the High Court. Although the
issue of the landowners will be dealt with in the second part of our judgment,
it will be useful to note that the Government supported the stand of Nandi
before the Single Judge, who partially allowed the landowners' petitions. It
was during the writ appeal stage that the Government reversed its stance and
opposed Nandi.
20.Even while the said writ appeals filed in the land acquisition matters were
pending before the High Court, a second round of writ petitions challenging the
Project itself was filed before the High Court. Despite the High Court's
go-ahead for the Project in 1997, and after seven years of implementation,
suddenly in the year 2004, these petitions were filed against it in so-called
"public interest" by two Members of the Legislative Assembly
(hereinafter "MLAs") and a "social worker" (i.e. Mr. J.C.
Madhuswamy and others). This petition prayed for a CBI enquiry and to restrain
the State Government from continuing with the Project or acquiring any further
land thereunder. Perhaps inspired by Mr. J.C. Madhuswamy and others, and also
in the so-called "public interest", All India Manufacturer's
Organisation, as well as two ex-Mayors of Mysore (Mr. Dakshinamurthy and
another), moved the High Court for a direction to the State Government to
implement the Project according to the FWA.
21.The High Court in the impugned judgment (vide paragraph 18) raised the
following two questions for consideration in the three writ petitions:
"(1) Whether the FWA entered into between the Government of Karnataka and
Nandi was a result of any fraud or misrepresentation as alleged by J.C.
Madhuswamy and others and the State Government?
(2) Whether any excess land than what is required for the Project had been
acquired by the State Government and whether it is open to it to raise such a
plea?"
22.The Division Bench disposed of all the writ petitions by a common judgment
by which it dismissed Writ Petition No. 45386 of 2004 filed by Mr. J.C.
Madhuswamy and others with costs. Writ Petition Nos. 45334 and 48981 of 2004
were allowed by the Division Bench directing the State of Karnataka and all its
instrumentalities, including the KIAD Board, to execute the Project as
conceived originally and to implement the FWA in "letter and spirit".
The High Court also directed the prosecution of KK Misra, Chief Secretary of
the Government of Karnataka and M. Shivalingaswamy, Under Secretary, Department
of Industries and Commerce, as envisaged by Section 340 of the Code of Criminal Procedure, 1973, for certain offences
which came to its notice as a result of the affidavits filed by them. KK. Misra
and M. Shivalingaswamy have filed separate appeals with regard to the direction
of their prosecution with which we are not concerned at present.
The contentions of the appellants
23.The main arguments in the present Civil Appeal Nos. 3492 to 3494 of 2005 were
addressed on behalf of the State of Karnataka by Mr. Anil B. Divan, learned
Senior Counsel, whose main contentions are as under:
(1).That the dispute between the State of Karnataka and Nandi is not barred by
the principle of resjudicata, constructive resjudicata or estoppel arising from
the judgment and proceedings in Somashekar Reddy's case;
(2).That the principle of ?resjudicata cannot be inflexibly applied to Public
Interest Litigations, especially when a re-examination of decided issues might
be in public interest;
(3).To the bar of resjudicata, it would be a successful answer that fraud and
misrepresentation had vitiated the entire transaction. Hence, there would be no
question of resjudicata since the fraud was discovered subsequent to the judgment
in Somashekar Reddy's case;
(4).That the High Court erred in brushing aside the report of the Expert
Committee headed by KC. Reddy, which clearly demonstrated that there was excess
land, which in terms showed that the FWA was not a bona fide agreement and,
therefore, was against public interest;
(5).The High Court could not have granted the final relief in the impugned
judgment. The High Court's order amounted to a mandamus to specifically perform
the FWA, which is an extremely complex contract, and hence the order is
incorrect.
We shall examine the third contention first - namely of fraud,
misrepresentation and mala fides vitiating the entire project. Fraud and
misrepresentation
24.The main ground on which the matter was argued by the learned Counsel for
the State of Karnataka before the Division Bench of the High Court was that
there was fraud and misrepresentation on the part of Nandi, which vitiated the
entire transaction. It was contended before the High Court by the State
Government that this fraud came to be noticed subsequent to the judgment in
Somashekar Reddy's case. It is pertinent to note that this point was put on
record through the affidavits of KK Misra, Chief Secretary of the Government of
Karnataka, M. Shivalingaswamy, Under Secretary, Department of Industries and
Commerce, which suggested that public interest was being affected as a result
of the execution of the FWA. It appears that the main contention of the writ
petitioners Mr. J.C. Madhuswamy and others before the High Court was that the
FWA was vitiated as a result of fraud and/or misrepresentation. Presumably,
this contention was urged in order to get over the bar of resjudicata arising
from the judgment in Somshekar Reddy's case. When the matter was argued before
us, although Mr. Divan addressed some arguments on fraud, he quickly abandoned
them and expressly gave it up. Considering that this was the main thrust of the
State's argument before the High Court and has been expressly given up before
us, we could have dismissed the appeals on this narrow point alone.
Nonetheless, since Mr. Divan argued the question of resjudicata with some
persistence, we will deal with it subsequently.
25.On the merits of the argument of fraud/misrepresentation, the High Court has
gone into it at great length and has demonstrated the hollowness of this
contention. We are in complete agreement with the views expressed therein on
this issue but we wish to highlight the following aspects to illustrate how the
argument of mala fides is actually the boot on the other foot.
26.The High Court has come to the categorical conclusion that the flip-flop on
the part of the State Government occurred only because of politicians, that the
mala fides, if any, appears to be on the part of the State Government for political
reasons. The High Court has pointed out that the FWA did not materialise out of
the blue. The FWA was negotiated over several months; it came to be drafted by
considering several points that the Cabinet Sub-Committee had raised. As we
have already highlighted, it was only thereafter, when detailed deliberations
had taken place at the highest levels of the State Government that the MOU was
signed and the Project Report accepted. A Government Order (dated 20-11-1995)
was issued requiring the Public Works Department to enter into a Memorandum of
Understanding with the Consortium of three companies, VHB, SAB and Kalyani. On
9-9-1996, through the CAA, the three members of the Consortium agreed to
"... unconditionally and irrevocably transfer and assign, jointly and
severally......" to Nandi "all rights, interest and title granted to
them with respect to the Infrastructure Corridor by GOK under the Government
Order and the Memorandum of Understanding". The CAA came to be signed by
the three members of the Consortium on the one hand and Nandi on the other; the
Governor of Karnataka. on behalf of the Government of Karnataka, was shown as
the "Consenting Party". A copy of this agreement was forwarded to the
State Government along with a forwarding letter dated 21-12-1996 requesting
that the Government approve of the same and advise of its approval so that the
original agreement could be given to the State Government for its consent. This
letter was forwarded by the Public Works Department to the Law Department through
a letter dated 22-1-1997 (No. PWD 155 CRM 96) seeking an opinion on the issue.
The State Government was advised by its Law Department (through Opinion No. 182
OPN 11/97, dated 3/4-3-1997) that since the Government was finalising a
separate agreement with Nandi, there was no need to specifically consent to the
CAA. Thus, it would appear that the State Government had specifically been made
aware of the CAA and the fact that the members of the Consortium had
transferred their rights to Nandi. The argument made before the High Court that
the Government was unaware of the CAA, was defrauded to execute the FWA is,
therefore, utterly dishonest. We concur with the decision of the High Court on
this issue that the plea was lacking any bona fides and that there was neither
fraud nor misrepresentation on the part of Nandi or any member of the
Consortium.
27.Subsequently, as we have already discussed, Nandi as the assignee of the
Consortium, submitted a draft of the FWA to the State Government which was
considered by the Core Committee that had been set up to negotiate the terms
with Nandi. The Core Committee referred the draft FWA to the Cabinet
Sub-Committee which suggested various modifications to it, which were
incorporated in the FWA. Finally, the FWA was approved by the State Government
and came to be signed on 3-4-1997. Thus, it appeal's that the plea of fraud and
misrepresentation was clearly an after thought and it was conveniently raised
by the State Government through the petitioners in Writ Petition No. 45386 of
2004, who were rightly described by the High Court as the State Government's
mouth piece"
(vide paragraph 22).
28.The High Court has also totality disbelieved the affidavits of the Chief
Secretary, KK Misra and the Under Secretary, M. Shivalingaswamy on this issue.
We have refrained from commenting on the merits of their affidavits since their
appeals against prosecution for perjury are pending separately. We may,
however, point out that both the affidavits of the two senior bureaucrats are
on the issue that certain facts which had been suppressed from the Government
had come to light after the judgment in Somashekar Reddy's case, and that these
indicated fraud and misrepresentation on the part of Nandi. Indeed, this was
the central argument put forward for impugning the FWA.
29. The FWA was executed on 3-4-1997 and implemented by the parties for at
least seven years. Several obligations under the FWA were carried out by the
State Government and its instrumentalities and also by Nandi, which had invested
a large amount of money in the Project. These included monies for payment of
compensation to landowners whose lands were being acquired for the Project.
Soon after the FWA was entered into, some interested parties had raised the
issue in "public interest" that the FWA was a fraud and was nothing
but a charade for a lucrative real estate business on the part of Nandi. The
Government through the then Minister for Public Works vigilantly defended the
Project against all these allegations both inside and outside the Legislature.
30. It would appear that the change of mind on the part of the State Government
came about co-incidentally or otherwise -with a change of Government in
Karnataka in 2004. In the year 2004, while the State Government's writ appeal
was still pending before the Division Bench, a statement was made by Mr. H.D.
Deve Gowda, former Prime Minister, making serious allegations with regard to
the Project stating that it was nothing but a charade by which Nandi had
converted it into a real estate business. It was at this stage that a note [No.
PWD/E/375/2004, dated 6-7-2004] was written by the new Minister, Public Works
Department, Mr. H.D. Revanna, who is none other than the son of Mr. Deve Gowda,
to the Principal Secretary, Public Works Department. The note in terms states
that land acquisition by the State Government for the Project was to cease till
the allegation that Nandi was carrying out a real estate business was enquired
into. With this, the State Government suddenly halted/slowed all ongoing
activities for smooth implementation of the Project. Indeed, it is strange that
the State Government woke up after seven long years, and even more strangely
after a change in the State's political leadership, to the fact that there was
fraud/misrepresentation by Nandi or anyone else.
31. Pursuant to this, the Minister of the Public Works Department set up the
"Expert Committee" (headed by K.C. Reddy) to go into the allegations
of excess land acquired by the Government for implementation of the Project.
After accepting the Interim Report of the Expert Committee, the Government
withdrew its appeal filed before the High Court and the reasons for the same
are mentioned in a Government Order [PWD 155 CRM 95 BMICP Expert
Committee/2004, Bangalore, dated 7-1-2005]. As we shall see later in the
judgment, the constitution and functioning of this Committee also illustrates
the mala fides with which the State Government has approached the Project.
Thus, the utter irresponsibility with which the theory of fraud/misrepresentation
was put forward is thoroughly exposed by the High Court in its impugned
judgment. Resjudicata
32. Res judicata is a doctrine based on the larger public interest and is
founded on two grounds: one being the maxim nemo debet bis vexari pro una et
eadem causa ("No one ought to be twice vexed for one and the same
cause" (P. Ramanatha Aiyar, Advanced Law Lexicon (Vol. 3, 3rd Edn. 2005)
at page 3170)) and second, public policy that there ought to be an end to the
same litigation (Mulla, Code of Civil Procedure (Vol. 1, 15th Edn. 1995) at
page 94). It is well-settled that Section 11 of the Civil Procedure Code, 1908
(hereinafter "the CPC") is not the foundation of the principle of
resjudicata, but merely statutory recognition thereof and hence, the Section is
not to be considered exhaustive of the general principle of law (See Kalipada
De v Dwijapada Das 1930 AIR(PC) 22. The main purpose of the doctrine is
that once a matter has been determined in a former proceeding, it should not be
open to parties to re-agitate the matter again and again. Section 11 of the CPC
recognises this principle and forbids a Court from trying any suit or issue,
which is resjudicata, recognising both 'cause of action estoppel" and
'issue estoppel'. There are two issues that we need to consider, one, whether
the doctrine of resjudicata, as a matter of principle, can be applied to Public
Interest Litigations and second, whether the issues and findings in Somashekar
Reddy constitute resjudicata for the present litigation.
Explanation VI to Section 11 states:
"Explanation VI.-Where persons litigate bona fide in respect of a public
right or of a private right claimed in common for themselves and others, all
persons interested in such right shall, for the purposes of this section, be
deemed to claim under the persons so litigating".
33. Explanation VI came up for consideration before this Court in Forward
Construction Company and Others v Prabhat Mandal CRegd.), Andheri and
Others : ereinafter "Forward Construction Company"). This
Court held that in view of Explanation VI, it could not be disputed that
Section 11 applies to Public Interest Litigation, as long as it is shown that
the previous litigation was in public interest and not by way of private
grievance. Further, the previous litigation has to be a bona fide litigation in
respect of a right which is common and is agitated in common with others.
34. As a matter of fact in a Public Interest Litigation, the petitioner is not
agitating his individual rights but represents the public at large. As long as
the litigation is bona fide, a judgment in a previous Public Interest
Litigation would be a judgment in rent. It binds the public at large and bars
any member of the public from coming forward before the Court and raising any
connected issue or an issue, which had been raised/should have been raised on
an earlier occasion by way of a Public Interest Litigation. It cannot be
doubted that the petitioner in Somashekar Reddy was acting bona fide. Further,
we may note that, as a retired Chief Engineer, Somashekar Reddy had the special
technical expertise to impugn the Project on the grounds that he did and so, he
cannot be dismissed as a busybody. Thus, we are satisfied in principle that
Somashekar Reddy, as a Public Interest Litigation, could bar the present
litigation.
35. We will presently consider whether the issues and findings in Somashekar
Reddy's case, actually constitute resjudicata for the present litigation.
Section 11 of the CPC undoubtedly provides that only those matters that were
"directly and substantially in issue" in the previous proceeding will
constitute resjudicata in the subsequent proceeding. Explanation HI to Section
11 provides that for an issue to be resjudicata it should have been raised by
one party and expressly denied by the other:
"Explanation III.-The matter above referred to must in the former suit
have been alleged by one party and either denied or admitted, expressly or
impliedly, by the other".
Further, Explanation IV to Section 11, states:
"Explanation IV.-Any matter which might and ought to have been made ground
of defence or attack in such former suit shall be deemed to have been a matter
directly and substantially in issue in such suit".
36. The spirit behind Explanation IV is brought out in the pithy words of
Wigram V.C. in Henderson v Henderson( 1843 (60) AllER 378 as follows.-
"The plea of resjudicata applies, except in special case (sic), not only
to points upon which the Court was actually required by the parties to form an
opinion and pronounce a judgment, but to every point which properly belonged to
the subject of litigation and which the parties, exercising reasonable
diligence, might have brought forward at the time".
37. In Greenhalgh v Mallard 1947 Indlaw CA 21
(hereinafter "Greenhalgh"), Somervell L.J. observed thus-
"I think that on the authorities to which I will refer it would be
accurate to say that res judicata for this purpose is not confined to the
issues which the Court is actually asked to decide, but that it covers issues
or facts which are so clearly part of the subject-matter of the litigation and
so clearly could have been raised that it would be an abuse of the process of
the Court to allow a new proceeding to be started in respect of them".
(emphasis supplied)
38. The judgment in Greenhalgh, was approvingly referred to by this Court in
State of Uttar Pradesh v Nawab Hussain : Combining all these
principles, a Constitution Bench of this Court in Direct Recruit, Class II
Engineering Officers' Association and Others v State of Maharashtra and
Others : : (SC)],
expounded on the principle laid down in Forward Construction Company's case by holding that:
".... An adjudication is conclusive and final not only as to the actual matter determined but as to every other matter which the parties might and ought to have litigated and have had it decided as incidental to or essentially connected with the subject-matter of the litigation and every matter coming within the legitimate purview of the original action both in respect of the matters of claim or defence. Thus, the principle of constructive resjudicata underlying Explanation IV of Section 11 of the Code of Civil Procedure was applied to writ case. We, accordingly hold that the writ case is fit to be dismissed on the ground of resjudicata"'.
39. With these legal principles in mind, the question, therefore, arises as to
what exactly was sought in Somashekar Reddy's case, how it was decided by the
High Court in the first round of litigation, and what has been sought in the
present litigation arising at the instance of Mr. J.C. Madhuswamy and others.
In order to show that the issue of excess land was "directly and
substantially in issue" in Somashekar Reddy's case, we will first examine
the prayers of the parties, the cause of action, the averments of parties and
the finding of the High Court in Somashekar Reddy's case.
40. First, learned Counsel for the respondents has pointedly drawn our
attention to the identity of the prayers made in the previous Public Interest
Litigation by Somashekar Reddy as compared to the prayers made in the present
case of Mr. Madhuswamy. The prayers in Somashekar Reddy's petition were: (a)
for quashing the FWA; and (b) for directing an inquiry by the CBI in the matter
and to prosecute the offenders. In Mr. Madhuswamy's petition, the prayers were:
(a) to direct the CBI to conduct inquiries into various acts as enumerated by
items 1 to 16 (specifically the issue of excess land); and (b) for quashing the
various agreements, and acts done in pursuance of the Project and consequently,
to denotify the land of all farmers situated away from the peripheral road and
link road. We are therefore, satisfied that the prayers made in Somashekar
Reddy's case and in Mr. Madhuswamy's writ petitions are substantially the same.
41. Second, the cause of action in both Somashekar Reddy's case and the present case is the FWA, which includes the provisions for acquiring 20, 193 acres of land for the Project (comprising 13, 237 acres of private land and 6, 956 acres of Government land). Indeed, it was stated in Somashekar Reddy's writ petition that the land requirement in Schedule I of the FWA was "highly exaggerated" and would illegally create "huge profits" for Nandi. Somashekar Reddy thus prayed that the FWA be quashed - this prayer was, however, specifically rejected. The very same FWA that was upheld earlier has now been impugned in the present case.
42. Third, in both Somashekar Reddy and Mr. Madhuswamy's petitions, the
averment was that excess land than required for the implementation of the
Project was being acquired by the State Government at the behest of Nandi and
that the Project was nothing but a camouflage to carry out a real estate
buisness by nandi .The High Court recordds the following contention of
Somashekar reddy's counsel
"The next submission of the Counsel for the petitioner is the Government
of Karnataka though ostensible (sic - ostensibly ) purported to form an Express
Highway has in reality allowed the 2nd respondent to develop the townships as a
developer by conferring a huge largess (sic largesse) by way of giving 20,
000acres of land According to petitioner, the land required for the
construction of four lane Highway is only 2, 775 acres, whereas the remaining
land would be utilised for the purpose of development of the towns thereby
permitting respondent 2 to develop townships as a developer and earn huge
profits". (emphasis supplied)
43. The averment of Somashekar Reddy regarding excess land came to be
considered by the High Court which records some of the opposing contentions of
the respondent-State, in the following terms:
"As a mega project like the Expressway involves considerable extent of
land, answering respondent (the State) has agreed to provide the minimum extent
of land required for the project partly out of the land owned by the State and
by acquiring the balance. Second respondent will not only construct the
proposed Expressway but also link roads, peripheral road, interchanges, service
roads, toll plazas and maintenance area etc., in addition to the townships.
It is stated that the project by its very nature requires considerable extent
of land and that is why the respondent has agreed to provide the land to the
extent available with it and acquire the balance and make available the same to
the replying respondent. There are mutual obligations on both the parties under
the impugned agreement and respondent 1 is only facilitating the acquisition of
land for which the replying respondent has to pay at the existing market rates".
(emphasis supplied)
44. Crucially, two very striking findings have been made by the High Court in
Somashekar Reddy's case as follows.
"So out of 20, 193 acres, land required for the Expressway would be 6, 999
acres leaving 13, 000 acres for development of townships. Government of
Karnataka in its written statement has said that it agreed to provide minimum
extent of land for the project - out of the land owned by the Government and by
acquiring lance.
Permission has been given to develop the five "7 degree Ps instead of 7, proposed by respondent 2 to make the project viable.”
The submission that the contract was entered in a clandestine er also cannot be accepted .... Respondents in their .statement of objections have admitted that this point was ra on the floor of the house and the respondent made detailed presentation on this subject in the house... Every minute detail was explained including the scientific method adopted by the respondent for identification of the land for the Project". (emphasis supplied)
45.All of these unequivocally show that the issue of excess land! and connected issue) was specifically raised by the petitioner in Somashekar Reddy's case, and was also forcefully denied by the State. In fact the decision in Somashekar Reddy's case, went further with the High Court according its imprimatur to the land requirements under the FWA amounting to 20, 193 acres, which in not small measure, resulted from the State's successful defence that it had provided the "bare minimum of land" for the Project calculated by a "scientific method". The judgment also contains copious references to the issue of land (including the acreage), the types of land to be acquired, the land required different aspects of the Project, the scientific techniques involved in identifying the land and road alignment etc. In these circumstances it cannot be doubted that Explanation III to Section 11 squarely applies it is clear that the issue of excess land under the FWA was "directly and substantially in issue" in Somashekar Reddy's case and hence the findings recorded therein having reached finality, cannot be reopened in this case'.
46.The principle and philosophy behind Explanation IV, namely to prevent
"the abuse of the process of the Court" (as stated in Greenhalgh's
case, through reagitation of settled issues, provides yet another ground to
reject the appellant's contentions. For instance the High Court specifically
records (vide paragraph 29) of the impugned judgment that:
"It is common case of the parties that the validity of FWA had earlier
been challenged in Somashekar Reddy's case on all conceivable grounds including
the one that land in excess of what is required for the Project had been
acquired by the State Government".
47.In the face of such a finding by the High Court, Explanation Section 11
squarely applies as, admittedly, the litigation in Somashekar Reddy's case
exhausted all possible challenges to the validity of the FWA, including the
issue of excess land. Merely because the present petitioners draw semantic
distinctions and claim that the excess 1and not having been identified at the
stage of the litigation in Somashekar Reddy's case, the Project should be
reviewed, the issue does not cease to be resjudicata or covered by principles
analogous thereto. If we were to re-examine the issues that had been
raised/ought to have been raised in Somashekar Reddy's case, it would simply be
an abuse of the process of the Court, which we cannot allow.
48.As we hav epointedout the cause of action the issues raised the prayers
made, the relief sought in Somashekar Reddys petition and the findings in
Somashekar Reddy's case, and the claims and arguments in he present petitions
were substantially the same. Therefore, it is not possible to accept the
contention of the appellants-before us that the judgment in Somashekar Reddy's
case, does not operate as resjudicata for the questions raised in the present
petitions.
Excess land and the Expert Committee
49.There was considerable time taken by the learned Counsel for the appellants
in trying to persuade us that excess land had actually been delivered to Nandi
under the FWA. A subsidiary argument was that though the actual area of land
delivered might not have been in excess, since land in prime areas had
improperly been acquired for Nandi's benefit, the issue needed to be
re-examined. In our view, this argument too is not open to be agitated at this
point. As we have already pointed out, the writ petition in Somashekar Reddy's
case, was the culmination of all such allegations which had been successfully
refuted even on the floor of the Legislature. Finally, having failed on the
floor of the Legislature, a Public Interest Litigation was filed on the ground
that there was something wrong with the FWA and that it was virtually a
sell-out to Nandi. The Division Bench of the High Court considered every
argument very carefully and recorded findings on all the issues against Mr.
J.C. Madhuswamy and others. In our view, permitting the argument on excess land
to be heard again to scuttle a project of this magnitude for public benefit
would encourage dishonest politically motivated litigation and permit the
judicial process to be abused for political ends. The High Court, therefore,
has refused to answer the first part of the second question framed for
consideration on the ground that it was already answered in Somashekar Reddy's
case and as it was res judicata, it could not be re-agitated. Further, that
since this argument involved details of contractual disputes, the High Court would
not examine it in its writ jurisdiction. We are not satisfied that the High
Court was wrong in so holding.
50.The High Court's finding on this issue only gains strength if we were to
examine the factual matrix in which the State took its stand that excess land
had been acquired for the Project. As we have previously stated, pursuant to
the objections raised to the Project by the new Minister for Public Works, an
"Expert Committee" was setup in 2004 to review the Project. The
Expert Committee was conveniently headed by KC. Reddy, who was the Advisor to
the Public Works Minister. This K.C. Reddy was the same gentleman, who as a
member of the previous HLC, had scrutinised the Project threadbare and had
given it the green signal. Surprisingly however, at this stage, he appeared to
be all willing to find faults and flaws in the Project and the FWA despite the
fact that there was an Empowered Committee that was required to monitor the
implementation of the Project. The High Court rightly pointed out that the Expert
Committee was constituted virtually in supersession of Clause 4.1.1 of the FWA.
51. The Expert Committee suddenly woke up to the alleged fact that excess land
was being acquired. Like the State Government, the Expert Committee also made
flip-flops and came out with a report saying that there was acquisition of
excess land. Crucially, it left the actual identification of the excess lands
to the KIAD Board. Surprisingly, the State Cabinet in its meeting dated
26-10-2004 accepted the report but reaffirmed its support to the Project and
expressed some reservations on the acquisition of more lands than what was
necessary for the Project. In this regard, the High Court critically comments
(vide paragraph 26) that:
"By constituting this Committee the State Government has ensured that the
Project gets stalled. It is interesting to note that Sri KC. Reddy who is the
Chairman of the Expert Committee was also a Member of the HLC which had
approved the Project and was associated with it till the signing of the FWA
which provides for 20, 193 acres of land to be made available. Sri KC. Reddy
did not record his dissent in those proceedings and at no stage did he ever
point out that the land that was sought to be provided for the Project was in
excess of what was required but now as the Chairman of the Expert Committee he
has, without identifying the excess lands which he has left for the Board to
identify, opined that excess land has been acquired for the Project. We cannot
appreciate such a conduct".
52.We too cannot appreciate the conduct on the part of KC. Reddy or the State
Government. The inference drawn by the High Court is that the plea of fraud and
misrepresentation sought to be raised was not only an afterthought but also
false to the knowledge of the State Government. The High Court, therefore,
observed (vide paragraph 27):
"It is unfortunate that the petitioners and the State Government have
chosen to raise this bogie (sic bogey) to defeat the public project sub serving
public interest".
53.Interestingly, neither the interim report nor the final report of the Expert
Committee identified the excess land but in fact, left it for the KIAD Board.
The Counsel for the KIAD Board handed over a set of documents, which
purportedly identified the specific excess lands. It was the grievance of the
KIAD Board that they hand not been given the opportunity for placing these
documents before the High Court. Since the date of documents showed that they
were drawn subsequent to the act on which the High Court had delivered its
judgment, the learned Senior Counsel for KIAD Board Mr KK Venugopal candidly
admitted that this exercise was carried out after the impugned judgment had
been delivered. It is a moot point whether the person, who swore this affidavit
on behalf of the KIAD Board stating that no opportunity had been given to the
KIAD Board to place these documents on the record of the High Court, needs to
be considered for prosecution under Section 340 read with Section 195 of the Code of Criminal Procedure, 1973. We strongly deprecate
such misleading or false affidavits on the part of the KIAD Board.
54.According to Mr. Venugopal, Article 300-A of the Constitution, as well as
the KIAD Act, would be violated if the KIAD Board were to directly acquire or
acquiesce in the acquisition of land in excess of what is required for the
Project. In our view, this is nothing but a repetition of the arguments made by
the State of Karnataka. As we have elaborately discussed, that the land was not
in excess has been held by the Division Bench of the High Court on two
occasions and we agree with it. Thus, there was no question of the land being
acquired for a purpose other than a public purpose or there being any
contravention of Article 300-A. In fact, we are somewhat surprised that this
type of argument must come from the KIAD Board, which was intimately involved,
from the very beginning, with the process of acquiring land. Further, the State
and its instrumentalities (including the KIAD Board) were enjoined by Clause
5.1.1.1 of the FWA, to make "best efforts" to acquire the land
required for the Project. Indeed, till the State itself changed its stand with
regard to the Project, nothing was heard from the KIAD Board about lands being
acquired in excess of the public purpose. Further, as an instrumentality of the
State, the KIAD Board cannot have a case to plead different from that of the
State of Karnataka. Thus, we are unable to countenance the arguments of Mr.
Venugopal on behalf of the KIAD Board.
55. Considering the facts as a whole, the High Court came to the conclusion
that since the Project had been implemented and Nandi had invested a large
amount of money and work had been carried out for more than seven years, the
State Government could not be permitted to change its stand and to contend that
the land allotted for the Project was in excess of what was required. Having
perused the impugned judgment of the High Court, we are satisfied that there is
no need for us to interfere therewith. Thus, there is no merit in this contention,
which must consequently fail.
The relief granted by the High Court
56. One final argument was made by Mr. Divan as regards the relief granted by
the High Court. To appreciate the argument, it is necessary to look at the
relief granted in terms of paragraph 42(2), which is as follows.-
"Writ petition Nos. 45334 and 48981 of 2004 are allowed directing the
State of Karnataka and all its Instrumentalities including the Board to
forthwith, execute the Project as conceived originally and upheld by this Court
in Somashekar Reddy's case and implement FWA in letter and spirit.
Consequently, Government Orders dated 4-11-2004 and 17-12-2004 constituting the
Review Committee and Expert Committee are quashed. The reports submitted by
these Committees in pursuance to these orders and all subsequent actions taken
incidental thereto are also quashed. Nandi is also directed to implement the
Project as expeditiously as possible. Parties will bear their own costs in
these two cases".
57. Mr. Divan strongly urged that the relief granted was wholly beyond the
jurisdiction of the High Court under Article 226 of the Constitution, as it
would amount to granting a decree for specific performance in writ
jurisdiction. A reading of the relief granted by the High Court does not
persuade us that it is so. The High Court merely directed that the Project and
the FWA, as conceived originally and upheld by the High Court in Somashekar
Reddy's case, should be implemented "in letter and spirit". In other
words, the High Court said that there is no scope for raising frivolous and
mala fide objections for ulterior purposes. This, the High Court was folly
entitled to do. It is trite law that when one of the contracting parties is
"State" within the meaning of Article 12 of the Constitution, it does
not cease to enjoy the character of "State" and, therefore, it is
subjected to all the obligations that "State" has under the
Constitution. When the State's acts of omission or commission are tainted with
extreme arbitrariness and with mala fides, it is certainly subject to
interference by the Constitutional Courts in this country. We may refer to
Gujarat State Financial Corporation v Mis. Lotus Hotels Private Limited
1963 (3) SCC 379: , in which a statutory Corporation (the Gujarat
State Financial Corporation) arbitrarily refused to grant the sanction of loans
to entrepreneurs who had already acted on the basis of the sanction and had
incurred expenditure and liabilities. The argument that the transaction was
purely a contractual arrangement between the parties and, therefore, not
amenable to writ jurisdiction, was categorically rejected by the following
observations:
"Now if appellant entered into a solemn contract in discharge and
performance of its statutory duty and the respondent acted upon it, the
statutory Corporation cannot be allowed to act arbitrarily so as to cause harm
and injury, flowing from its unreasonable conduct, to the respondent. In such a
situation, the Court is not powerless from holding the appellant to its promise
and it can be enforced by a writ of mandamus directing it to perform its
statutory duty. A petition under Article 226 of the Constitution would
certainly lie to direct performance of a statutory duty by 'other authority1 as
envisaged by Article 12".
58. Kumari Shrilekha Vidyarthi and Others v State of Uttar Pradesh end
Others : : 1993 AIR(SCW) 77, is another authority for the
proposition that the State Government has to act reasonably and without
arbitrariness even with regard to the exercise of its contractual rights. In
Mis. Dwarkadas Marfatia and Sons v Board of Trustees of the Port of
Bombay : , the situation was one in which a lease between the
Bombay Port Trust and certain parties was terminated in exercise of contractual
rights and the lease rent was abnormally increased. It was held that there was
always an obligation on the part of public authorities in their acts of
omission and commission to be reasonable. In Biman Krishna Bose v United India
Insurance Company Limited and Another 69, the
question was whether an Insurance Company could arbitrarily and unreasonably
refuse the renewal of a policy. Considering that the Insurance Company, as a
result of State-monopoly in the insurance sector, had become "State"
under Article 12 of the Constitution, this Court held that:
" it (the insurance company) requires (sic) to satisfy the requirement of
reasonableness and fairness while dealing with the customers. Even in an area
of contractual relations, the State and its instrumentalities are enjoined with
the obligations to act with fairness and in doing so, can take into
consideration only the relevant materials. They must not take any irrelevant
and extraneous consideration while arriving at a decision. Arbitrariness should
not appear in their actions or decisions".
59. Thus, it appears that no exception could be taken to relief granted in the
judgment of the High Court impugned before us. All that the High Court has done
is to reaffirm and require the State Government and its instrumentalities, as
"State" under the Constitution, to act without arbitrariness and mala
fides, especially in the matter of land acquisition. It is pertinent to note
that the State had agreed {vide Clause 5.1.1.1 of the FWA) in respect of the
lands required under the FWA, that:
"GOK shall use its best efforts and cause its Governmental
Instrumentalities to use their best efforts, to exercise its and their legal
right of eminent domain (or other right of similar nature) under the Laws of
India to acquire the Acquired Land. Prior to acquiring any acquired land GOK
will obtain from the company, written confirmation of its willingness to
purchase such acquired land from GOK at the purchase price (whether in the form
of cash or comparable land) required under the Laws of India (the "Acquired
Land Compensation"). GOK shall offer to the expropriated owners of the
land the rehabilitation package specifically worked out for this Infrastructure
Corridor Project with mutual consultation of the consortium and the Revenue
Authorities in accordance with the applicable rules".
60. In these circumstances, we find no reason to interfere with the said
directions of the High Court. In the future also, we make it clear that while
the State Government and its instrumentalities are entitled to exercise their
contractual rights under the FWA, they must do so fairly, reasonably and
without mala fides; in the event that they do not do so, the Court will be
entitled to interfere with the same.
61. The High Court also found, justifiably in our view, that the writ
petitioners had been sponsored by the State Government to put forward its
changed stand in the garb of a Public Interest Litigation. In the opinion of
the High Court (vide paragraph 29):
"The Court cannot all its process to be abused by politicians and others
to delay the implementation of a public project which is in larger public
interest nor can the Court allow anyone to gain a political objective. These
legislators who have not been successful in achieving their objective on the
floor of the Assembly have now chosen this forum to achieve their political
objective which cannot be allowed".
82, Although this should nave really put an end to the writ petitions filed by
Mr. Madhuswamy and others, the High Court had to consider the petitions filed
by Mr. Dakshinamurthy and the All India Manufacturer's Organisation, who were
also before the Court by way of Public Interest Litigation and sought a
mandamus of the continuation of the Project. A grievance was made before the
High Court that these were persons put up by Nandi and that they were virtually
projecting the view point of Nandi. The High Court having taken note of the
same has said that despite this, larger public interest required the
implementation of the Project. We see no reason to differ with the High Court
on this point.
63. Writ Petition No. 45386 of 2004 (Mr. J.C. Madhuswamy's case), was rightly
dismissed as raising the very same issues which had been concluded by the
decision in Somashekar Reddy's case. Writ Petition Nos. 45334 and 48981 of 2004
were rightly allowed and the order to implement the Project in its letter and
spirit had been made in exercise of the writ jurisdiction of the High Court. We
refrain from dealing with the third relief granted, namely directing the
prosecution of K.K. Misra and M. Shivalingaswamy, as their appeals shall be
independently dealt with by this Court.
64. Taking an overall view of the matter, it appears that there could hardly be
a dispute that the Project is a mega project which is in the larger public interest
of the State of Karnataka and merely because there was a change in the
Government, there was no necessity for reviewing all decisions taken by the
previous Government, which is what appears to have happened. That such an
action cannot be taken every time there is a change of Government has been
clearly laid down in State of Uttar Pradesh and Another v Johri Mal[65.
: ; 2004 AIR(SCW) 3888 and in State of Haryana v State of Punjab
and Another : : , where this Court observed thus:
" in the matter of governance of a State or in the matter of execution of
a decision taken by a previous Government, on the basis of a consensus arrived
at, which does not involve any political philosophy, the succeeding Government
must be held duty-bound to continue and carry on the unfinished job rather than
putting a stop to the same".
The Land Acquisition Matters (Civil Appeal Nos. 3848 to 3884, 3889 to 4366,
4575, 4576, 5399 to 5402, 5746, 5747, 5759, 5797 to 5799, 6098, 6099, 5092,
5093, 7024 to 7040, 7591 7592 of 2005; 61, 73 to 76 of 2006 and S.L.P. No. 1562
and 1563 of 2006).
The Background
65. In all these appeals, another attempt by a side wind, was made to scuttle
the Project. The attempt, this time, was primarily on the part of the
landowners, whose lands were acquired for implementation of the Project and who
challenged the same before the High Court of Karnataka. A learned Single Judge
of the Karnataka High Court, through judgment dated 18-12-2003 (K.P.
Sachidananda and Others v State of Karnataka arid Others [ 2004 ILR(Kar)
593 : AIR 2004 NOC 238 (Kar.)]), disposed of these petitions. The learned Judge
took the view that acquisition of 60% of the land by the State Government,
insofar as it related to the formation of roads and infrastructure development
was valid, while the acquisition of the remaining 40% meant for the development
of townships and convention centres was invalid and to that extent the
acquisition was quashed. The landowners, the State Government, the KIAD Board
and also Nandi were aggrieved by the judgment of the learned Single Judge and
filed separate writ appeals challenging the judgment. The stand of the State
Government in its writ appeal was that the learned Single Judge was wrong in
quashing 40% of the acquisition of land. This was also the stand of the KIAD
Board. Nandi also challenged the said part of the order. Thus, it would appear
that the State Government, KIAD Board and Nandi were ad idem in their writ
appeals that the learned Single Judge had erred in interfering and quashing 40%
of the land as not being in public interest.
66. Sometime in August 2004, when the writ appeals came up for hearing before
the Division Bench of the High Court, the State Government and the KIAD Board
withdrew their appeals, because by then, as we have already discussed, the
State Government appeared to have second thoughts about the Project and felt
that the land acquisitions were far in excess of the Project's requirements.
Even though they were also respondents under the writ appeal filed by Nandi, they
did not contest the claim and addressed no arguments before the Division Bench
of the High Court. Those appeals were disposed of by an order dated 28-2-2005.
The appeals filed by Nandi and the Indian Machine Tools Manufacturers
Association (hereinafter "the IMTMA") were allowed, whereas those
filed by the landowners were dismissed, and the order of the learned Single
Judge was set aside and the entire acquisition was upheld.
67. Various connected appeals against the order of the learned Single Judge came
to be disposed of by orders of the High Court dated 29-6- 2005 and 18-11-2005,
in terms of the detailed judgment and order of a Division Bench of the High
Court dated 28-2-2005 (hereinafter in the Land Acquisition Matters "the
impugned judgment").
The contentions of the appellants
68. Though there are a number of appellants before us, the contentions raised
before the High Court and us were principally as under: first, that no notice was
served on the landowners under Section 28(1) of the KIAD Act; secondly, that
the notice of acquisition was vague and consequently prejudiced any effective
objection being raised by the landowners whose lands were sought to be acquired
and finally, that the land acquisition was not for a public purpose, or for a
purpose as specified in the KIAD Act, and was also in excess of the Project's
requirement.
69. Although other contentions have also been raised, we will not deal with
them here as they have already been dealt with in the first part of our
judgment.
Non-service of notice
70. The argument that no notice was served on the landowners under Section 28(1) of the KIAD Act, appears to be factually incorrect. Even the learned Single Judge who partially allowed the writ petition came to the conclusion (vide paragraph 22) in his judgment (dated 18-12-2003) that the "... petitioners in all these cases have filed objections on several grounds". Even in the appeal before the Division Bench, the High Court observed (vide paragraph 30) that it was "... not in dispute that the landowners were served with notices and the objections filed by them have been considered". Even before us, when these appeals were argued, no attempt was made by any of the learned Counsel to satisfy us that the appellants had not actually been served notice of the acquisition. Neither was the finding of the learned Single Judge or the Division Bench impugned on this point. We are, therefore, unable to accept the contention that notices were not served on the appellants as required under Section 28(1) of the KTAD Act.
Vagueness of notice of acquisition
71. The next contention is that the notice of acquisition was vague and
consequently prejudiced any effective objection being made by the landowners
whose lands were sought to be acquired. The vagueness of the notification, it
is contended, has vitiated the notice itself, according to the learned Counsel
for some of the landowners.
72. The notification in the instant case states that the lands were being
acquired for the purposes of "industrial development" i.e.,
establishing and developing industrial areas by the KIAD Board. In our opinion,
the purpose indicated in the notifications is sufficiently precise and is not
affected by the vice of vagueness as alleged. Our attention was drawn to the
judgment of this Court in Aflatoon and Others v Lt. Governor of Delhi and
Others : , where this Court pointed out as follows.-
"The question whether the purpose specified in a notification under Section
4 is sufficient to enable an objection to be filed under Section 5-A would
depend upon the facts and circumstances of each case... In the case of an
acquisition of a large area of land comprising several plots belonging to
different persons, the specification of the purpose can only be with reference
to the acquisition of the whole area. Unlike in the case of an acquisition of a
small area, it might be practically difficult to specify the particular public
purpose for which each and every item of land comprised in the area is
needed".
73. It is difficult to accept that the landowners were not aware of the purpose
of the acquisition nor can it be accepted that they were unable to file their
objections on this ground. As a matter of fact, as the High Court has
concurrently found, they did file their objections before the Competent
Authorities. We do not see any prejudice caused to them as a result of the
wordings of the notification of acquisition, The concerned authority also heard
them on the objections filed after affording them an opportunity to file such
objections under Section 28(2) of the KIAD Act. Thus there is no substance in
the contention of the appellants that the notification was vague and hence that
the State did not comply with the principles of natural justice.
Purpose of. Acquisition
74. The next contention urged on behalf of the landowners is that the lands
were not being acquired for a public purpose. The Counsel who have argued for
the landowners have expatiated in their contention by urging that land in
excess of what was required under the FWA had been acquired; land far away from
the actual alignment of the road and periphery had been acquired, consequently,
it is urged that even if the implementation of the Highway Project is assumed
to be for a public purpose, acquisition of land far away therefrom would not
amount to a public purpose nor would it be covered by the provisions of the
KIAD Act.
75. In our view, this was an entirely misconceived argument. As we have pointed
out in the earlier part of our judgment, the Project is an integrated
infrastructure development project and not merely a highway project. The
Project as it has been styled, conceived and implemented was the
Bangalore-Mysore Infrastructure Corridor Project, which conceived of the
development of roads between Bangalore and Mysore, for which there were several
interchanges in and around the periphery of the city of Bangalore, together
with numerous developmental infrastructure activities along with the highway at
several points. As an integrated project, it may require the acquisition and
transfer of lands even away from the main alignment of the road.
76. The various changes brought about to the KIAD Act, also reflect the
intention of the State's Legislature to provide for land acquisition for the
Project. The expressions "Industrial area" and "Industrial
Infrastructural facilities" as defined under the KIAD Act, definitely
include within their ambit establishment of facilities that contribute to the
development of industries. We cannot forget that, as originally enacted, the
KIAD Act had a different, narrower definition of "industrial area" in
Section 2(6). In 1997, the definition was broadened to also include
"industrial infrastructural facilities and amenities". Further,
Section 2(7-a) was added to define "Industrial Infrastructural
facilities" in a manner broad enough to take into its sweep the land
acquisition for the Project.
77. The learned Single Judge erred in assuming that the lands acquired from
places away from, the main alignment of the road were not a part of the Project
and that is the reason he was persuaded to hold that only 60% of the land
acquisition was justified because it pertained to the land acquired for the
main alignment of the highway. This, in the view of the Division Bench, and in
our view, was entirely erroneous. The Division Bench was right in taking the
view that the Project was an integrated Project intended for public purpose
and, irrespective of where the land was situated, so long as it arose from the
terms of the FWA, there was no question of characterising it as unconnected
with a public purpose. We are, therefore, in agreement with the finding of the
High Court on this issue.
Civil Appeal Nos. 7024 and 7025 of 2005
78. As regards these appeals, the impugned judgment of the High Court (vide
paragraph 32) specifically records that the appellants did not have any right
or interest in the land in question on the date that they filed the writ
petitions before the High Court. The Counsel too admitted the same before the
High Court. The High Court accordingly found that the writ petitions were not
maintainable. Since the writ petition proceeded on this footing, we cannot
permit the appellants to take a different stand before us, contrary to what had
been stated before the High Court. Since we have not been convinced otherwise,
the writ petitions were not maintainable and the High Court was justified in
the view that it took.
79. In summary, having perused the well-considered judgment of the Division
Bench which is under appeal in the light of the contentions advanced at the
Bar, we are not satisfied that the acquisitions were, in any way, liable to be
interfered with by the High Court, even to the extent as held by the learned
Single Judge. We agree with the decision of the Division Bench that the
acquisition of the entire land for the Project was carried out in consonance
with the provisions of the KIAD Act for a public project of great importance
for the development of the State of Karnataka. We do not think that a Project
of this magnitude and urgency can be held up by individuals raising frivolous
and untenable objections thereto. The powers under the KIAD Act represent the
powers of eminent domain vested in the State, which may need to be exercised
even to the detriment of individuals' property rights so long as it achieves a
larger public purpose. Looking at the case as a whole, we are satisfied that
the Project is intended to represent the larger public interest of the State
and that is why it was entered into and implemented all along.
The final orders
80. In the result, we find that the judgment of the High Court (dated 3-5-2005)
impugned before us in the Main matter, is not liable to be interfered with.
There is no merit in the appeals and they are hereby dismissed. Considering the
frivolous arguments and the mala fides with which the State of Karnataka and
its instrumentalities have conducted this litigation before the High Court and
us, it shall pay Nandi costs quantified at Rupees Five Lakhs, within four weeks
of this order.
81. Appellants in C.A. No. 3497 of 2005 (J.C. Madhuswamy's case), in addition
to the costs already ordered by the High Court, shall pay to the Supreme Court
Legal Services Authority costs quantified at Rupees Fifty thousand within four
weeks of this order. A copy of this order be sent to the Member-Secretary of
the Supreme Court Legal Services Authority for his/her information.
82. In the land acquisition matters, the appeals challenging the judgments of
the High Court dated 28-2-2005, 29-6-2005 and 18-11-2005 are dismissed as
without substance. However, in the circumstances, there shall be no order as to
costs.
J