SUPREME COURT OF INDIA
Centrotrade Minerals and Metal. Inc
Vs
Hindustan Copper Limited per S.B. Sinha
Civil Appeal No. 2562 of 2006 [Arising Out of S.L.P. (C) No. 18611 of 2004] With Civil Appeal No. 2564 of 2006 [Arising Out of S.L.P.(C) No. 21340 of 2004]
(S. B. Sinha and Tarun Chatterjee, JJ)
09.05.2006
S. B. SINHA, J.
Leave granted.
Interpretation of an agreement containing a two tier arbitration vis-a-vis the
applicability of Part I or Part II of the Arbitration and
Conciliation Act, 1996 (for short, "the 1996 Act") is in
question in these appeals which arise out of a judgment and order dated
28.07.2004 passed by a Division Bench of the Calcutta High Court in A.P.O.T.
No. 182 of 2004.
FACTS:
2. M/s. Centrotrade Minerals and Metal Inc. (for short,
"Centrotrade"), Appellant in SLP (C) No. 18611 of 2004 and the
Hindustan Copper Limited (for short "HCL"), Appellant in SLP (C) No.
21340 of 2004 entered into a contract for sale of 15, 500 DMT of Copper
Concentrate to be delivered at Kandla Port in the State of Gujarat in two
separate consignments.
3. The said goods were ultimately required to be used at the Khetri Plant of
HCL situated in the State of Rajasthan. The seller in terms of the contract was
required to submit a quality certificate from an internationally reputed
assayer, mutually acceptable to the parties. After the consignments were
delivered, the payments therefor had been made. However, a dispute arose
between the parties as regard the dry weight of concentrate copper.
4. Clause 14 of the contract contained an arbitration agreement which reads as
under:
"All disputes or differences whatsoever arising between the parties out
of, or relating to, the construction, meaning and operation or effect of the
contract or the breach thereof shall be settled by arbitration in India through
the arbitration panel of the Indian Council of Arbitration in accordance with
the Rules of Arbitration of the Indian Council of Arbitration. If either party
is in disagreement with the arbitration result in India, either party will have
the right to appeal to a second arbitration in London, UK in accordance with
the rules of conciliation and arbitration of the International Chamber of
Commerce in effect on the date hereof and the results of this second
arbitration will be binding on both the parties. Judgment upon the award may be
entered in any court in jurisdiction."
5. Centrotrade invoked the arbitration clause. The Arbitrator appointed by the
Indian Council of Arbitration made a NIL award. Centrotrade thereupon invoked
the second part of the said arbitration agreement on or about 22nd February,
2000. An award was made pursuant thereto.
SUIT BY HCL:
6. HCL, during pendency of the proceedings before the arbitrator, filed a suit
in the court at Khetri in the State of Rajasthan questioning initiation of the
second arbitration proceeding before International Chamber of Commerce inter
alia contending that the provision for second arbitration was void and a nullity.
No interim order was passed therein despite having been prayed for, whereupon
an appeal was preferred by HCL before the District Judge, which was also
dismissed. In a revision filed by HCL, the High Court granted an injunction. In
the meanwhile the sole arbitrator had commenced arbitration proceedings.
Centrotrade filed a special leave application before this Court questioning the
said order of injunction passed by the Rajasthan High Court and by an order
dated 8lh February, 2001, the said order of interim injunction was vacated.
ARBITRATION PROCEEDING:
7. Mr. Jeremy Cooke, Arbitrator held his sittings in London. HCL, in a series
of letters to the International Court of Arbitration and to the Arbitrator,
maintained that the arbitration agreement was void being opposed to public
policy. Despite the same, they, through their attorney, consulted about the
procedural aspects of the arbitration and had asked for their submissions in
relation to the procedure, progress and substance of the dispute. HCL also
received copies of all correspondence passed between Centrotrade and the
Arbitrator and of all submissions made. They had been given every opportunity
to take any point which they wished to take in their defence. Centrotrade
served their submissions and supporting evidence by the orders made by the
Arbitrator on 2O'h December, 2000, 19lh January, 2001 and 3rd May, 2001. When
no defence submission or supporting evidence was produced by HCL within the
time prescribed, a fax was sent to them by the learned Arbitrator on 30lh July,
2001 giving it one last opportunity to inform him by return of any intention on
their part to put in a defence and to seek an extension of time for doing so. A
further fax was sent on 9lh August, 2001 whereby the Arbitrator informed the
parties that he was proceeding with the award. On 11lh August, 2001, the
Arbitrator received a fax from Fox & Mandal (representing HCL) requesting
for extension of time for one month to put in a defence, pursuant whereto on
16lh August, it was directed that any submission in support of an application
for extension of time for a defence and any submissions on the substantive
merits of the dispute together with any evidence relied in relation to the
application and any submissions made thereupon should be received by him by
31s1 August, 2001 in absence whereof he would not give any consideration
thereto. On 27lh August, 2001, Fox & Mandal sought for a further three
weeks' extension of time for making their submissions and serving supporting
evidence, pursuant whereto a time for filing those submissions of evidence was
extended until 12lh September, 2001. Submissions containing about seventy five
pages were received by the Arbitrator on 13lh September, 2001 without any
supporting evidence or any justification for not complying with the earlier
orders passed by him. The Arbitrator, however, considered the submissions made
by HCL in making the award.
AWARD:
8. An award was passed by the said Arbitrator on 29'h September, 2001 holding :
(1) the arbitration clause contained in clause 14 of the agreement is neither
unlawful nor invalid.
(ii) the Arbitrator had jurisdiction to decide his own jurisdiction in terms of
Article 8.3 of the ICC Rules as also Section 16 of the 1996 Act.
(iii) the claim of Centrotrade based on the report of Inspectorate Griffith was
just. The arbitration award dated 15'h June, 1999 was obviously wrong. There is
no dispute about the actual figure of loss claimed by Centrotrade. There is no
dispute as to the demurrage owing which, in accordance with Clause 9.2 of the
contract, is to be calculated on the basis of a discharging rate of 1600 MT per
WWD of 24 consecutive hours.
(iv) Centrotrade is entitled to interest as well as costs.It was directed:
"(1) HCL do pay Centrotrade the sum of $152, 112.33, inclusive of interest
to the date of the Award in respect of the purchase price for the first
shipment.
(2) HCL do pay Centrotrade the sum of $15, 815.59, inclusive of interest to the
date of this Award in respect of demurrage due on the first shipment.
(3) HCL do pay Centrotrade the sum of $284, 653.53, inclusive of interest to
the date of this Award in respect of the purchase price on the second shipment.
(4) HCL do pay Centrotrade their legal costs in this arbitration in the sum of
$82, 733 and in addition the costs of the International Court of Arbitration,
the Arbitrator's fees and expenses totaling $29, 000.
(5) HCL do pay Centrotrade compound interest on the above sums from the date of
this Award at 6% p.a. with quarterly rests until the date of actual
payment."
PROCEEDINGS BEFORE THE COURTS:
9. HCL filed an application purported to be under Section 48 of the 1996 Act in
the Court of District Judge Alipore, Calcutta. HCL also filed a suit before the
Civil Judge, Senior Division, Alipore which was marked as T.S. No. 78 of 2001
praying for a declaration that the ICC award is void and a nullity, as also for
permanent injunction and damages.
ENFORCEMENT OF AWARD:
10. Centrotrade, in the meanwhile, filed an application for enforcement of the
said award dated 29th September, 2001 in the Court of the District Judge,
Alipore which was numbered as Execution Case No. 1 of 2002. Upon an application
made in terms of Clause 13 of the Letters Patents of the Calcutta High Court by
Centrotrade, the said execution case was transferred to the Calcutta High
Court.
11. A learned Single Judge of the said court by a judgment and order dated 10lh
March, 2004 allowed the said execution petition. Aggrieved by and dissatisfied
therewith, HCL preferred an appeal which was allowed by reason of the impugned
order dated 2O'b May, 2004. Both the parties are before us questioning the
correctness of the said judgment.
HIGH COURT JUDGMENT:
12. In its judgment, the High Court held:
(i) Although successive arbitration is not impermissible in India, but two
successive awards are mutually destructive.
(ii) In his award, Mr. Cooke did not make any statement that he was overruling
or setting aside or in any manner altering the Indian award.
(iii) Although the second award is binding on the parties but is not
enforceable having regard to the first award.
(iv) The second award is not a foreign award within the meaning of Sec. 44 of
the 1996 Act and, thus, Sec. 34 thereof would apply thereto in the facts and
circumstances of the case.
(v) Neither Part II of the Act nor Sec. 51 thereof states anywhere either
expressly or by necessary implication, that the definition of 'Foreign Award'
contained in Section 44 would apply notwithstanding the proper law of the
contract being Indian Law.
SUBMISSIONS:
13. Mr. S. Sarkar, learned senior counsel appearing on behalf of Centrotrade
submitted that:
(i) In a two-tier arbitration, the second arbitration proceedings having taken
place in London, the award of
Mr. Cooke was a foreign award within the meaning of Section 44 of the Act.
(ii) The learned Single Judge was satisfied that the HCL was not enable to
present his case in the arbitration proceedings within the meaning of Section
48(1 )(b) of the Act which finding having not been reversed by the Division
Bench, no case has been made out for setting aside the award. Even otherwise
refusal of an adjournment by an Arbitrator is not a ground for challenging an
arbitral award.
14. Mr. Debabrata Ray Choudhury, learned counsel appearing on behalf of the
HCL, on the other hand, submitted that:
(i) The definition of an award as contained in Section 2(2) of the 1996 Act
must be read with the other provisions thereof, viz., Sees. 2(5), 2(6) and 2(7)
as also Section 42 thereof in view of the fact that the Indian law was
applicable in relation to the contract in question.
(ii) Indian law in relation to enforcement of the terms and conditions of the
contract being applicable, both the awards are governed by the Indian law.
(iii) The second part of the arbitration agreement contained in Clause 14 of
the agreement is void and of no effect being opposed to public policy. Having
regard to the fact that the first award was made in terms of the Indian law,
reference to the second arbitrator was impermissible inasmuch as the 1996 Act
envisages only one award.
(iv) The object of the Act being to provide an integral framework and the
parties having chosen Indian law, even assuming that Part II of the Act
applies, Section 44 clearly makes an exception therefor in view of the decision
of this Court in Bhatia International v. Bulk Trading S.A. and another .
(v) In any event, the Arbitrator did not give adequate opportunities of hearing
and as the procedures prescribed under the ICC Rules were not followed, the
award is liable to be set aside. The Arbitrator, having proceeded to prepare an
award without the pleadings of the parties before him and considering only the
first part of the written statement without waiting for the second part,
misconducted himself at the proceeding. Had an opportunity been given, HCL
could have cross-examined the expert on whose report, the award has been made.
(vi) Neither any issue was raised, nor any date was fixed for hearing and, as
the parties were not given an opportunity to examine the witnesses, the award
is liable to be set aside in terms of Section 48(l)(b) of the 1996 Act.
(vii) The judgment of the High Court to the extent that the arbitration clause
has been held to be valid is erroneous.
VALIDITY OF THE AGREEMENT:
15. So far as the question of validity of the arbitration agreement between the
parties is concerned, we may at the outset notice that the said question was
specifically raised by HCL both before the learned Single Judge and the Division
Bench of the High Court.
16. Both the learned Single Judge and the Division Bench held the said
arbitration agreement to be valid. The Arbitrator as also the High Court in
support of their findings on the said question relied upon the decisions of the
Calcutta High Court in Hiralal Agarwalla & Co. v. Jokin Nahopier & Co.
Ltd.[ 1927 AIR(Cal) 647, the Bombay High Court in Fazalally Jivaji Raja
v. Khimji Poonji and Co.[ AIR 1934 Bom] and the Madras High Court in M.A. Sons
v. Madras OH & Seeds Exchange Ltd. and another 1965 AIR(Mad) 392.].
17. We, at the outset, would notice the decisions and the authorities which had
been relied upon by the learned arbitrator as also by the High Court in support
of the proposition that a two tier arbitration constitutes a valid agreement.
18. The question primarily before us is as to whether the validity of such
arbitration agreement can be upheld having regard to the provisions of the 1996
Act.
19. In Hanskumar Kishan Chandv. The Union of India , interpretation of Sec.
19 of the Defence of India Act, 1939 fell for consideration. Section 19(1)
provides for payment of compensation if any action is taken of the nature
described in sub-sec. (2) of Section 299 of the Government of India Act, 1935.
Section 19(l)(a) provided for the amount of compensation being fixed by the
agreement whereas Section 19(l)(b) provided for reference to arbitrator in the
event such an agreement cannot be reached whose qualification was laid down
under sub-section (3) of Section 220 of the said Act for appointment as a Judge
of a High Court. Section 19(1 )(b) reads as under:
"Where no such agreement can be reached, the Central Government shall
appoint as arbitrator a person qualified under sub-section (3) of Section 220
of the abovementioned Act for appointment as a Judge of a High Court."
20. Section 19(l)(c) provided for appointment by the Central Government of a
person having expert knowledge as to the nature of the property acquired and
for the nomination of an assessor by the person to be compensated for the
purpose of assisting the arbitrator. Section 19(l)(e) contemplated that the
arbitrator in making his award shall have regard to the provisions of
sub-section (1) of Section 23 of the Land Acquisition Act,
1894 so far as the same can be made applicable. In terms of Section
19(l)(f), an appeal shall lie to the High Court against an award of the
arbitrator except in cases where the amount thereof does not exceed an amount
prescribed in this behalf by rule made by the Central Government. Section
19(l)(g) provided that save as provided in the said section and in any rules
made thereunder nothing in any law for the time being in force shall apply to
arbitrations under that section. Construing the aforementioned provisions, this
Court held:
"14. The principles being thus well-settled, we have to see in the present
case whether an appeal to the High Court under Section 19(l)(f) of the Act
comes before it as a Court or as arbitrator. Under Section 19(l)(b), the
reference is admittedly to an arbitrator. He need not even be a Judge of a
Court. It is sufficient that he is qualified to be appoints a Judge of the High
Court. and under the law, no appeal would have laid to the High Court against
the decision of such an arbitrator. Thus, the provision for appeal to the High
Court under Section 19( 1 )(f) can only be construed as a reference to it as an
authority designated and not as a Court. The fact that, in the present case,
the reference was to a District Judge would not affect the position. Then
again, the decision of the arbitrator appointed under Section 19(l)(b) is
expressly referred to in Section 19(l)(f) as an award. Now, an appeal is
essentially a continuation of the original proceedings, and if the proceedings
under Section 19(T)(b) are arbitration proceedings, it is difficult to see how
their character can suffer a change, when they are brought up before an
Appellate Tribunal. The decisions in The Special Officer, Salsette Building
Sites v. Dossabhai Bezonji. The Special Officer Salsette Building Sites v.
Dassabhai Basanji Motiwala, Manavikraman Tirumalpad v. The Collector of the
Nilgris and Secretary of State for India in Council v. Hindusthan Co-operative
Insurance Society Limited proceed all on the view that an appeal against an
award continues to be part of, and a further stage of the original arbitration
proceedings. In our view, a proceeding which is at the inception an arbitration
proceeding must retain its character as arbitration, even when it is taken up
in appeal, where that is provided by the statute."
(Emphasis supplied)
21. In Hiralal Agarwalla (supra), Ghose, J. speaking for a Division Bench of
the Calcutta High Court dealing with almost an identical matter, was of the
opinion that a committee of appeal can hold a second round of arbitration,
whether
described as a fresh set of arbitration or not, as the substance of the matter
has got to be looked at, and giving to the sections of the Indian Arbitration
Act, the very best consideration will the learned Judge find in it which would
prevent an award by a committee being the final award contemplated by the
parties in certain eventualities being filed in the High Court. It was observed
that, 'in other words, the contract contains as it were two submissions or a
submission within a submission'. Ghose, J., however, did not go into the
question as to whether the first award could be filed in court. Buckland, J.,
concurring with the said judgment stated the law thus:
"The procedure whereby the dispute comes before the committee is called an
appeal. What it is called is of no consequence; the fact remains that the
committee is a body other than a Court of justice to whom the parties have
agreed to refer their dispute. Such a proceeding is known to the law as an
arbitration and those in whom the arbitration is lodged are known as
arbitrators or an umpire..."
22. In Fazcilally Jivaji Raja (supra), the Bombay High Court followed Hiralal
Agarwalla (supra). It also referred to a judgment of another learned Single
Judge of the said High Court wherein it was observed:
"...It is as much an award in respect of which the parties can seek relief
under the Arbitration Act as an ordinary award made by arbitrators as
contemplated by that Act from which there is no appeal to any Board as in the
present case. This point is covered by the decision of the Court of appeal in
1893 (1) QB 405, which has been referred to in the judgment of the lower
Court. It is a decision under the English statute of 1889, corresponding to the
Arbitration Act, and the point that has been argued by Mr. Desai on behalf of
the appellants here was raised in that case and disallowed."
23. Yet again in M.A. Sons (supra), a Division Bench of the Madras High Court
following Hiralal Agarwalla (supra), observed:
"...An award made pursuant to a proper arbitration agreement is final,
subject, of course, to the consequences of any such term of the contract. Here,
the agreement provided that the parties would abide by any modification or
alteration in the bylaws as governing the contract when it subsisted or was in
issue between the parties. We must, therefore, hold that the second respondent
had a right of appeal."
24. In "The Law of Arbitration' 7lh Edition by S.D. Singh at page 359, it
is stated:
"31. Hearing before Appeal Committees. Rules of certain Chambers provide
for an appeal against an award to an Appeal committee constituted under
arbitration rules of those Chambers, Managing Committees of these Chambers
themselves act as appeal committees and the rules also provide for the quorum of
these committees to hear appeals against an award. When provision is made for
such appeals, proceedings for the hearing of an appeal against an award are
part of the proceedings in the reference."
29. It is not necessary for us to comment on the correctness or otherwise of
the said decisions except observing that they were decided having regard to the
provision of the 1940 Act and not the 1996 Act. Question is whether the said
arbitration would be valid in terms of the provisions of the 1996 Act and in particular
when two awards of the Arbitrators are governed by two different parts thereof.
THE 1996 ACT:
26. The United Nations Commission on International Trade Law (UNCITRAL) adopted
in 1985 the Model Law on International Commercial Arbitration. The General
Assembly of the United Nations recommended that all countries give due
recognition thereto. The 1996 Act, as noticed hereinbefore, seek to consolidate
and amend the law relating to domestic arbitration, international commercial
arbitration, enforcement of foreign arbitral awards and to define the law
relating to conciliation taking into account the said UNCITRAL Model Law and
Rules.
27. The "United Nations Convention on the Recognition and Enforcement of
Foreign Arbitral Awards (New York, 10 June, 1958)", the New York
Convention in common legal parlance, has been ratified by India on 13lh July,
1960. By virtue of its Article VII, the Geneva Protocol on Arbitration Clauses
of 1923 and the Geneva Convention on the Execution of Foreign Arbitral Awards
of 1927 ceases to have effect between the contracting States. Considering that
the New York Convention has been ratified by 108 nations and less than five
sovereign contracting states of the Geneva Convention have not become
signatories to the New York Convention, Chapter II of Part II of the 1996 Act
already has minimal applicability and may soon have none at all, reducing that
Chapter to a surplus age.
28. Prior to coming into force of the 1996 Act, all matters relating to
arbitration, both domestic and foreign, was governed by several statutes, viz.,
the Arbitration Act, 1940 (for short "the 1940
Act"), Arbitration (Protocol and Convention) Act, 1937
and the Foreign Awards (Recognition and Enforcement) Act,
1961 (for short "the 1961 Act"). India is a signatory to the
UN Convention. The 1996 Act was enacted pursuant to the commitment of the
Government of India to make an appropriate legislation amending and
consolidating the law in terms of UNCITRAL Model Law and Rules.
29. Chapter 1 Part I applies where the place of arbitration is in India, as
would appear from sub-section (2) of Section 2 of the 1996 Act. In terms of
sub-section (3) of Section 2, the said part would not affect any other law for
the time being in force by virtue of which certain disputes may not be
submitted to arbitration. Sub-section (4) of Section 2 reads as under:
"This Part except sub-section (1) of Section 40, Sections 41 and 43 shall
apply to every arbitration under any other enactment for the time being in
force, as if the arbitration were pursuant to an arbitration agreement and as
if that other enactment were an arbitration agreement, except in so far as the
provisions of this Part are in consistent with that other enactment or with any
rules made thereunder."
30. Sub-section (7) of Section 2 provides that arbitral award made under the
said Part shall be considered as a domestic award. The interpretation clause
contained in Section 2 uses the words 'unless the context otherwise requires'.
Section 2(b) of the 1996 Act defines an "arbitration agreement" to
mean an agreement referred to in Section 7. Section 7 defines an arbitration
agreement for the purpose of Chapter I to mean an agreement by the parties to
submit to arbitration all or certain disputes which have arisen or which may
arise between them in respect of a defined legal relationship whether
contractual or not. In Section 2(c) arbitral award has been defined to include
an interim award whereas in Section 44, foreign award has been defined to mean
an arbitral award on differences between persons arising out of legal
relationships, whether contractual or not, considered as commercial under the
law in force in India in pursuance of an agreement in writing for arbitration
to which the Convention set forth in the First Schedule applies. An arbitrator
is appointed in terms of Section 11 of the Act, providing inter alia, therein
that the parties are free to agree on a procedure for appointing the arbitrator
or arbitrators subject to subsection (6) thereof, wherewith we are not
concerned in this case. Section 12 lays down the grounds for challenging an
award; sub-section (3) whereof provides:
"(3) An arbitrator may be challenged only if
(a) circumstances exist that gives rise to justifiable doubts as to his
independence or impartiality, or
(b) he does not possess the qualifications agreed to by the parties."
31. Section 13 provides that the parties are free to agree on a procedure for
challenging an arbitral award, in terms whereof the jurisdiction of an
arbitrator on the grounds specified under sub-section (3) of Section 12 can be
questioned before the arbitrator himself. Section 16 authorizes the arbitral
tribunal to rule on its own jurisdiction. Chapter 6 of the Act lays down the
rules applicable to the substance of a dispute, in terms whereof the arbitral
tribunal is required to decide the dispute submitted to arbitration in
accordance with the substantive law for the time being in force in India.
32. Sub-section (2) of Section 28 of the Act provides that the arbitral
tribunal shall decide ex aequo et bono or as amiable compositeur only if the
parties have expressly authorized it to do so. Sub section (3) thereof enjoins
a duty upon the arbitral tribunal to decide all cases in accordance with the
terms of the contract and to take into account the usages of the trade
applicable to the transaction. Section 31 provides for the form and contents of
the arbitral award. Section 32 provides for termination of proceedings; in
terms of sub-section (1) whereof the arbitral proceedings shall be terminated
by the final arbitral award or by an order of the arbitral tribunal under
sub-section (2).
33. An application for setting aside an arbitral award can be filed in terms of
Section 34 which occurs in Chapter VII of the 1996 Act. Sub-section (2) of Sec.
34 lays down the grounds upon which such arbitral award can be set aside. Such
an application is required to be filed within three months from the date on
which the parties making that application had received the arbitral award. The
court, however, has-jurisdiction to entertain such an application within a
further period of thirty days, but not thereafter
34. Section 35 postulates finality of an arbitral award. Such an award is
binding not only on the parties but also on persons claiming under them
respectively. Section 36 of the 1996 Act reads as under:
"Enforcement.- Where the time for making an application to set aside the
arbitral award under section 34 has expired, or such application having been
made, it has been refused, the award shall be enforced under the Code of Civil Procedure, 1908 (5 of 1908) in the same
manner as if it were a decree of the Court."
35. The expression 'Arbitral Award has not been defined in Part I, but the
expression 'foreign award' has been defined in Section 44 of Part II, which
reads as under:
"44. Definition.- In this Chapter, unless the context otherwise requires,
"foreign award" means an arbitral award on differences between
persons arising out of legal relationship, whether contractual or not,
considered as commercial under the law in force in India, made on or after the
11th day of October, 1960
(a) in pursuance of an agreement in writing for arbitration to which the
Convention set forth in the First Schedule applies, and in one of such
territories as the Central Government, being satisfied that reciprocal
provisions have been made may, by notification in the Official Gazette, declare
to be territories to which the said Convention applies."
Whereas Part I deals with the domestic arbitration, Part II deals with the
enforcement of certain foreign awards.
36. We may notice that Section 9(b) of the 1961 Act contained that nothing in
that Act would apply to any award made on an arbitration agreement governed by
the law of India. Part II of the 1996 Act makes an exception to the effect that
unlike Section 9(b) of the 1961 Act, it makes the position absolutely clear
that the character of an award is determined by the place where it is made.
37. Section 48 provides for conditions for enforcement of foreign awards.
Section 49 lays down that where the court is satisfied that the foreign award
is enforceable under the said chapter, the award shall be deemed to be a decree
of that court.
38. The 1996 Act contains a coherent and model framework. It envisages only one
award under one set of rules. It does not contemplate multi-layer awards
governed by different sets of rules. It has introduced several changes of which
three are worth taking note of: (i) fair resolution of a dispute by an
impartial tribunal without any unnecessary delay or expenses; (ii) Party
autonomy is paramount subject only to such safeguards as are necessary in
public interest; and (iii) The arbitral tribunal is enjoined with a duty to act
fairly and impartially.
39. The important shortcomings that are very much apparent from bear reading of
the Arbitration and Conciliation Act, 1996 can be
said as follows:
(i) No provision is made for expediting awards or the subsequent proceedings in
Courts where applications are filed for setting aside awards.
(ii) An aggrieved party has to start again from the District court for
challenging the award.
In this respect it would be pertinent to mention about Arbitration and
Conciliation (Amendment) Bill, 2003. It was based on the comprehensive review
of the Arbitration and Conciliation Act, 1996
undertaken by the Law Commission of India in its 176th Report. Few of the
salient features of the Bill are:
(i) it provides that where the place of arbitration is in India, Indian Law will
apply whether the arbitration is between the Indian Parties or an International
arbitration in India.
(ii) it also provides for the Arbitration Division in the High Courts and also
for its jurisdiction and special procedure for enforcement of awards made under
the Arbitration Act, 1940 including awards made
outside India.
DIFFERENCE BETWEEN THE 1996 ACT AND THE 1940 ACT:
40. The 1996 Act makes a radical departure from the 1940 Act. It has embodied
the relevant rules of the modern law but does not contain all the provisions
thereof. The 1996 Act, however, is not as extensive as the English Arbitration
Act.
41. Different statutes operated in the field in respect of a domestic award and
a foreign award prior to coming into force of the 1996 Act, namely, the 1940
Act, the Arbitration (Protocol and Convention) Act, 1937
and the Foreign Awards (Recognition and Enforcement) Act,
1961. All the aforementioned statutes have been repealed by the 1996 Act
and make provisions in two different parts, namely, matters relating to
domestic award and foreign award respectively.
42. The Scheme of 1996 Act is absolutely distinct and different from the 1940
Act as also the 1961 Act.
43. In the 1940 Act, no reason was required to be stated in the award unless
otherwise agreed upon. In the 1996 Act, reasons are required to be stated
unless agreed to otherwise by the parties. The court's intervention is sought
to be minimized under the provisions of the 1996 Act not only having regard to
the concerns expressed in the international community as regard delay in the
arbitration proceedings but also in view of the fact that an award under the
1996 is to be a reasoned one. In a large number of judgments, this Court has
emphasized that the extent of power of the court's intervention in relation to
a reasoned award and unreasoned one would be different. Whereas in relation to
an unreasoned award, the court's jurisdiction to interfere with the award was
absolutely limited, a greater latitude had been given in relation to a reasoned
award.
44. After the 1996 Act came into force, under Section 16 of the Act the party
questioning the jurisdiction of the arbitrator has an obligation to raise the
said question before the arbitrator. Such a question of jurisdiction could be raised
if it is beyond the scope of his authority. Such a question was required to be
raised during arbitration proceedings or soon after initiation thereof as a
preliminary issue. Such a decision would be subject to challenge under Section
34 of the Act. In the event, the arbitrator opined that he had no jurisdiction
in relation thereto an appeal thereagainst was provided for under Section 37 of
the Act.
45. In terms of the 1940 Act, an award was required to be made a rule of court.
In such a proceeding, an objection in terms of Section 30 of the 1940 Act would
be entertained. Sub-section (2) of Section 30 of the 1996 Act enjoins a duty
upon the Arbitrator to promote settlement. Such an application was required to
be filed within the period specified therefor under the Limitation
Act, 1963.
46. Section 31 of the 1996 Act is in tune with Article 31 of the Model Law. The
requirements contained therein, most of which are mandatory, are specified
therein. Whereas under the 1940 Act only an interim award or final award could
be made; four types of awards are contemplated under the 1996 Act, viz.,
interim award, additional award, settlement or agreed award and final award.
47. Section 33 of the 1996 Act clearly postulates that the Arbitrator has the
jurisdiction to correct and interpret an award in terms whereof, he may amend
his core award.
AWARD UNDER THE 1996 ACT:
48. Section 34 of the Act provides for the mode and manner in which an arbitral
award can be questioned. Such a course can be taken only by filing an
application which shall be in accordance with sub-section (2) and sub-section
(3). An award in the Indian part of the award, thus, could be set aside only by
filing an application. The law, therefore, does not contemplate that despite
the rigour of Section 34 of the Act, an award which although not challenged and
becomes enforceable and executable still can be subject matter of a foreign
award. An award as soon as it becomes enforceable, it becomes final and binding
in terms of Section 35 of the Act.
49. The award, which is finally being either made by way of partial award or
final award, after the expiry of a period of thirty days becomes a decree in
terms of Sectibn 36 of the 1996 Act. When an award has been made, signed and
delivered to the parties, it is final and binding on the parties and persons
claiming under them respectively.
50. By reason of Section 36 of the 1996 Act, a legal fiction has been created
to the effect that on expiry of the period prescribed for setting aside an
award as envisaged under Section 34 of the Act, the award becomes capable of
being executed and enforced. The concept of provision for an appeal before
another forum from an award and that too when a part of the award would be a
domestic award and another part would be a foreign award is not contemplated
under the 1996 Act.
51. An appeal as against an award in terms of an agreement may be or may not be
filed within the time specified under Section 34 of the Act. Even the appellate
arbitrator (if we may use the said term) would have no jurisdiction to pass an
order of injunction staying the operation of the original award of the
arbitrator. The 1996 Act does not contemplate that only because an appeal has
been filed against the award, the time envisaged under Section 34 shall cease
to run. If during pendency of the so- called appeal an award becomes a decree,
the appellate arbitrator cannot set aside the said decree. An appeal
contemplates that the procedure before both the authorities would be the same.
An appeal is a continuation of the same proceeding. It does not comprehend two
different procedures, two separate sets of evidences. An appeal does not take
away the nature of the award. In other words, two different nature of the
awards is not contemplated; only because there is a provision for appeal. We
are not oblivious of the fact that rules of some chambers contemplate such a
provision but in such an event the one that is made by the first arbitrator
does not become final. The appeal committee follows the same procedure, relies
upon the same evidence unless additional evidence either by consent of the
parties or otherwise is permitted. By reason of such a procedure applicability
of different set of rules is not envisaged. It is within the same jurisdiction.
It does not contemplate two different and distinct jurisdictions. But in the
present case, parties were not bound by any such agreement of trade or
community association. As the parties were individual companies and only guided
by their agreement, the above situation may not be applicable.
52. It is not in dispute that the provisions contained in Part I and Part II of
the 1996 Act are distinct and different. Procedures for enforcing such awards
are different. Consequences of the awards made under two different parts are
absolutely different.
53. What can be contemplated under the UNCITRAL Model Rule is Med-Arb contracts
or similar such contracts and not a contract of present nature.
54. According to Section 34(3) of the I 1996 Act, the maximum period of
limitation for making an application is three months from the date on which the
applicant had received the arbitral award or the request under Section 33 was
disposed of and another thirty days from the last day of the third month.
Section 34 which refers to "challenge to arbitral award" strives to
balance between the party autonomy and judicial control of the arbitral result
with the object of speed and efficiency. The balance has to come down strongly
in favour of finality, and against judicial review, except in few circumstances.
So, the main object of the provision is to determine the whether the award has
become final and binding or not. Thus, the section depicts a position whereby
an arbitral award can be challenged for the purpose of setting aside of the
same at the first instance without much delay. The Court would set aside the
award only on certain circumstances. Thereby, it is the legislative intention
that such a matter is settled without much delay or much intervention of court.
So, the finality of the challenged award would be decided by Court under
Section 34 of the 1996 Act and appeals are allowed against certain orders of
courts or tribunals on certain grounds under Section 37 of the Act
[Furthermore, Section 37(3) provides that no second appeal shall lie from an
order passed in appeal, although it does not take away the right to appeal in
Supreme Court]. Throughout, the provisions nowhere it is mentioned that an
appeal can be made or an application can be filed against the award to a
separate arbitration board or forum. So, the finality and legality has to be
determined by the Court if it is so challenged. Otherwise, reference to a
second arbitration panel would consume more time as arbitrators would decide
the matter after listening the dispute afresh. Presuming that the reference to
the arbitrator is made for second time and subsequently arbitrator gives an
award, it would be more time consuming and complex if validity of the first
award is challenged along with second award. So, following the scheme of the
1996 Act, it is more viable and convenient to accept the first award without
opting for second time arbitration and then to decide it, if the award is
challenged
55. There can be a situation where an appeal is made against foreign award
decided and settled abroad and the appeal will be made in India according to
our domestic statute. For example, when one of the parties is an international
company or organisation, first the arbitration will be done according to New
York Convention in foreign country and thereafter, if there is any grievance
against the award challenge can be made in India under the Act of 1996.
56. Even the principles analogous to Order XLI, Rule 1 of the Code of Civil
Procedure envisages that filing of an appeal shall automatically not mean stay
of the operation of the decree. In that view of the matter, mere filing of an
appeal would not make the award unenforceable. No prayer for stay of the
operation of the award had been prayed for nor the appellate arbitrator had
directed stay of the operation of the award. The 1996 Act does not contemplate
that the arbitrator would be entitled to sit in appeal over an executable
decree. Even the doctrine of merger shall not apply inasmuch as the said
doctrine contemplates an appellate authority who can pass the same type of
order which could be passed by the original authority. If by fiction of law an
award becomes a decree without the intervention of the court, the nature of an
award which can be passed by the appellate arbitrator, would loose 'he character
of an award. The doctrine of merger, therefore, would not apply. A decree,
whether by reason of a statute or a legal fiction created under the statute,
would have different and distinct connotation vis-a-vis an award. By agreement
of the parties, a private adjudicator cannot sit in appeal over an enforceable
decree. A decree passed by a court of law may be set aside by that court itself
in exercise of its review jurisdiction or by an appellate court created in
terms of a statute. A private adjudicator, it will bear repetition to state,
cannot overturn a decree created by a legal fiction. A legal fiction, it is
well settled, must be given its full effect. [See Bhavnagar University v.
Palitana Sugar Mill (P) Ltd. and others 4.],
Ashok Leyland Ltd. v. State of T.N. and another[. nd Bharat Petroleum
Corporation Ltd. v. P. Kesavan and another .
57. A domestic award, in view of the statutory scheme, is subject to the
supervision of a court of law. Its jurisdiction encompasses within its purview
over the entire process of arbitration. An award is finally subject to a party
agreeing to take recourse to the provisions of Section 34 of the 1996 Act and
it becomes a decree. An award can be set aside only if the court comes to the
conclusion that one or the other grounds contained in Section 34 of the Act
exist. A challenge to the domestic award can, thus, be made only before a
national court designated by the Act itself and on the grounds specified in
Section 34 of the Act. A fortiori, the validity of a domestic award cannot be
questioned before any other forum including the forum chosen by the parties, if
any
58. We may also notice that Section 66 of the English Arbitration Act provides
for obtaining leave from the court for enforcing an award. The Indian law does
not contain such a provision. Therefore, if a leave is not granted, a claimant
may pursue an independent cause of action which accrues when an award is not
honoured. Sub-section (3) of Section 66 of English Arbitration Act provides
that leave to enforce shall not be given where, or to the extent that, the
person against whom it is sought to be enforced shows that the tribunal lacked
substantive jurisdiction to make the award. Section 34 of the Indian
Arbitration Act does not make such a provision. But, the Indian law is also to
be construed in the light of the Model Rule. Model Rules being referred to as
the 1996 Act does not contain any specific provision in this behalf where,
thus, the domestic law is silent, the court may interpret a provision in the light
of the international conventions. [See Liverpool & London S.P. & 1
Asson. Ltd. v. M. V. Sea Success 6 P, Pratap
Singh v. State ofJharkhand 2005 (2) SCC 551 = 2005 (2) SCJ 70 and Zee
Telefilms Ltd. v. Union of India = 2005 (2) SCJ 121, UNCITRAL Model
Rule does not contemplate such a situation.
JURISDICTION ISSUE:
59. An award made on the basis of an invalid agreement would be a nullity. Such
an award would be coram nonjudice. [See Smith v. East Elloe Rural District
Council 1956 Indlaw HL 23. The law in this
behalf in India is clear and explicit. An order passed by a Tribunal lacking
inherent jurisdiction would be a nullity. Where such a lack of jurisdiction is
established, the same goes to the root of the matter. [Balvant N. Viswamitra
and others v. Yadav Sadashiv Mule (Dead) Through LRS. and others.
60. The 1996 Act, puts domestic awards and foreign awards in two different and
distinct compartments, subject of course to certain overlapping provisions as
has been noticed in some decisions of this Court.
61. It may not, therefore, be possible to hold that the 1996 Act contemplates
that an arbitration award can be an admixture of domestic award and foreign
award.
62. The 1996 Act in no uncertain terms speaks of an arbitration agreement, as
would appear from the interpretation clause contained in clause 2(b) as also
Section 7 thereof, which excludes the concept of two tier arbitration capable
of being enforced under two different chapters.
63. A multi-tier arbitration may be held to be operative and valid when it was
governed solely by the 1940 Act or the 1961 Act inasmuch as in such an event,
the procedure laid down therein could have been followed. The 1996 Act,
however, on the other hand, repeals and replaces not only the 1940 Act but also
the 1961 Act and provides for different forums and different procedures for
resolution of a dispute through an arbitrator. It is inconceivable that one
part of the arbitration agreement shall be enforceable as a domestic award but
the other part would be enforceable as a foreign award. An award made in terms
of one arbitration agreement can either be a domestic award or a foreign award;
wherefor different procedures have been laid down, even when the consequences
from such award are different and when the grounds thereof are also different
and distinct. The fundamental legislative policy brought out by the 1996 Act,
thus, being not in consonance with having two tier arbitration which had two
different statutes governed by two different provisions and would be subject to
different procedures, in our opinion, is not valid. Whereas, in the decisions
and authorities relied upon by Mr. Cooke, the second arbitration was also
before the same institution governed by the laws of the same country, in the
instant case, the Indian law would be applicable in relation to the first part
of the arbitration, namely, the Indian Council of Arbitration, whereas second
part thereof would be governed by International Chamber of Commerce, Paris
Rules. Both parts of the arbitration proceeding, therefore, have not been
carried out under the same institution. An arbitration agreement envisioning
different procedures at different stages cannot be countenanced under the 1996
Act. Had the appeal been provided within the set-up of Indian Council of
Arbitration, subject to the compliance of time frame, probably the agreement
would have been valid. But, it is not so. As observed in Hiralal Agarwalla
(supra), such a submission must be within a submission. In such an event the
first award may not be capable of being filed in court to which question Ghosh,
J. did not go into.
64. A person may waive his right. Such waiver of right is permissible even in
relation to a benefit conferred under the law. But it is trite that no right
can be waived where public policy or public interest is involved. Jurisdiction
on a tribunal/ court is a creature of statute. Jurisdiction on Arbitration can
be conferred by agreement between the parties. But, the contract between the
parties must be in obedience to law and not in derogation thereof. Contracting
out is permissible provided it does not deal with a matter of public policy. An
agreement under no circumstances can violate the Public Policy.
65. The appellate Arbitrator, therefore, could not have made an award in terms whereof
a deemed decree passed by a court of India capable of being enforced in terms
of Section 34 of the 1996 Act would stand set aside. The said award, therefore,
is contrary to the legislative policy in India.
66. A jurisdictional issue can be raised in two ways. A party to an arbitration
proceeding may take part in arbitral proceedings and raise the question of
jurisdiction before the arbitral tribunal. He may also challenge the
jurisdiction of the arbitrator without participating in the arbitral proceedings.
67. Under the English Arbitration Act, an appeal on jurisdiction would involve
rehearing of the matter by the court at which the party can adduce evidence and
reargue the entire issue of evidence. There is absolutely no reason as to why
the said principle shall not apply to India. If a jurisdictional issue can be
raised before the court even for the first time, the court would be entitled to
take on records even the fresh hearing, it goes without saying that it would
also be entitled to determine the jurisdictional fact.
68. In Primetrade AG v. Ythan Ltd 2006 (1) AllER 367, jurisdictional issue
based on interpretation of documents executed by the parties fell for
consideration having regard to the provisions of the Carriage of Goods by Sea
Act, 1992. It was held that as the appellant therein did not become holder of
the bills of lading and alternatively as the conditions laid down in Section
2(2) were not fulfilled, the arbitrator had no jurisdiction to arbitrate in the
disputes and differences between the parties.
PUBLIC POLICY:
69. Lord Mustill had once said that "The great advantage of arbitration is
that it combines strength with flexibility
Flexible because it allows the contestants to choose the procedure which fit
nature of the dispute and the business context in which it occurs."
Arbitration was meant to be a speedy, expeditious and cost-effective method of
dispute reconciliation. So, the primary object of ADR movement is avoidance of
vexation, expense and delay and promotion of the ideal of "access to
justice".
70. But, then the contract must be within the legal framework.
71. In terms of the laws of India governing the field, the parties cannot
contract out of the statute and take recourse to such a procedure which would
for all intent and purport make the provisions of Sections 34 and 36 of the
1996 Act nugatory by entering into contractual arrangement or otherwise. The
1996 Act does not postulate that the parties can contract out of the provisions
thereof. The arbitration agreement of the parties, therefore, must be made
strictly in terms of the provisions of the 1996 Act.
72. The Arbitration Act, 1991 (the Statute of Canada) which is amended by the
Statutes of Ontario, 2006 expressly provide for "Contracting Out" under
which the parties to an arbitration agreement may agree, expressly or by
implication, to vary or exclude any provision of this Act except few
circumstances, like, equality and fairness, setting aside of award, enforcement
of award, etc.
73. Contracting out of the appeals procedure is possible before any dispute
arises in all cases under the Arbitration Act, 1996 (U.K.). The Act contains
express provision that every award shall contain reasons unless it is an agreed
award or the parties have expressly agreed to dispense with the reasons
(Section 52). The parties may want to dispense with reasons if neither side is
contemplating an appeal and they do not want to incur the additional costs
involved. Thus control over whether reasons should be given will be placed in
the hands of the parties, rather than in the hands of the arbitral tribunal or
the court.
74. The Act confers a number of powers on the arbitral tribunal unless parties
otherwise agree. For example, under Section 48, under Section 35, and under
Section 39. There are also powers conferred on the court but which are
nevertheless subject to the contrary agreement of the parties, such as to
entertain appeals on questions of law in limited arbitration, also to take
certain other steps short of dismissal where a party fails to comply with a
peremptory order Section 47 to make awards on different issues.
75. But Indian statute, i.e., the 1996 Act does not provide such
"contracting out" provision so that parties can fix / determine, by
their terms of agreement, the procedure of appeal after the award is made.
76. Such a contractual arrangement, having regard to the provisions contained
in Section 23 of the Indian Contract Act shall be void being opposed to public
policy. The parties, it is trite, cannot by contract or otherwise confer
jurisdiction on a forum which is prohibited by law in force in India. The law
in force in India does not permit to limit or avoid the operation of the
statutory provisions.
77. The expression 'public policy' in India has been used for three different
situations, namely, (i) an arbitral award may be set aside under Section
34(2)(b) of the 1996 Act if it is in conflict with the public policy of India;
(ii) enforcement of a foreign award (New York Convention Award) may be refused
under Sec. 48(2)(b) if the enforcement of the award would be contrary to the
public policy of India; and (iii) a foreign award (Geneva Convention Award) may
be enforceable under Section 57(1 )(b) if the enforcement of the award is not
contrary to the public policy or law of the India.
78. The expression 'public policy' will have the same connotation in respect of
an arbitration agreement or an award. The judicial intervention in such matters
has never been free from difficulty. Whereas refusing enforcement of an
arbitral award has been viewed with much skepticism, the English Courts are
more often than not have refused to enforce a foreign award on public policy
ground holding that common law recognizes that English public policy is
paramount. In some jurisdiction even serious procedural defects in the arbitral
proceedings had been held to provide for enough justification for refusal to
afford foreign award. [Russell on Arbitration, 22nd edition, 2003, page 389,
para 8-046 and Chitty on Contract, 29th edition, 2004, page 961, para 16-045].
We do not see any reason as to why the Indian law should be held to be
different.
79. Even under the 1940 Act, this Court in Renusagar Power Co. Ltd. v. General
Electric Co.[ 1 laid down that the arbitral
award can be set aside if it is contrary to:
(a) fundamental policy of Indian Law,
(b) the interests of India; or (c) justice or morality. A narrower meaning to
the expression 'public policy' was given therein by confining the scope of
judicial review intervention of the arbitral award only when the aforementioned
three grounds set forth therein. An apparent shift can, however, be noticed
from the decision of this Court in Oil and Natural Gas Corporation Ltd. v. Saw
Pipes Ltd. (for short 'ONGC')[ . 17. . This Court therein referred
to an earlier decision of this Court in Central Inland Water Transport
Corporation Ltd. v. Brojo Nath Ganguly" wherein the applicability of the
expression 'public policy' on the touchstone of Sec. 23 of the Indian Contract
Act and Article 14 of the Constitution of India came to be considered. This
Court therein was dealing with unequal bargaining power of the workmen and the
employer and came to the conclusion that any term of the agreement which is
patently arbitrary and/ or otherwise arrived at because of the unequal
bargaining power would not only be ultra vires Article 14 of the Constitution
of India but also hit by Section 23 of the Indian Contract Act. In ONGC
(supra), this Court apart from the three grounds stated in Renusagar (supra)
added another ground thereto for exercise of the court's jurisdiction in
setting aside the award if it is patently arbitrary stating:
"...What is for public good or in public interest or what would be
injurious or harmful to the public good or public interest has varied from time
to time. However, the award which is, on the face of it, patently in violation
of statutory provisions cannot be said to be in public interest. Such
award/judgment/ decision is likely to adversely affect the administration of justice.
Hence, in our view in addition to narrower meaning given to the term
"public policy" in Renusagar case it is required to be held that the
award could be set aside if it is patently illegal. The result would be -award
could be set aside if it is contrary to:
(a) fundamental policy of Indian law; or
(b) the interest of India; or
(c) justice or morality, or
(d) in addition, if it is patently illegal.
Illegality must go to the root of the matter and if the illegality is of
trivial nature it cannot be held that award is against the public policy. Award
could also be set aside if it is so unfair and unreasonable that it shocks the
conscience of the court. Such award is opposed to public policy and is required
to be adjudged void."
80. By referring to the aforementioned decisions, we do not mean to say that we
agree with the law laid down therein but we have referred thereto only for the
purpose of finding out whether the expression 'public policy' is construed
narrowly or broadly. It does not, however, make any substantial difference for
determining the question in the sense that arbitration agreement contained in
clause 14 is opposed to public policy as it is violative of the Indian
statutes.
81. Section 23 of the Indian Contract Act, 1872
embodies the doctrine of public policy as evolved by the common law. It takes
within its sweep transactions:
(i) the consideration or object whereof is forbidden by law; or
(ii) of such a nature, if permitted, would defeat the provisions of any law; or
(iii) if fraudulent or involves or implies injury to the person or property of
another where the court regards it immoral, or opposed to public policy.
82. In various decisions, this Court has taken into consideration some of the
well- known authorities for determining the question as to whether the
executive can be given a power to decide as to what would be a public policy.
83. In Godawat Pan Masala Products I.P. Ltd. v. Union of India .], it was
held that it is always in the domain of the judiciary to interpret what is
morality at a given point of time.
84. The doctrine of public policy undoubtedly is governed by precedents. Its
principles have been crystalised under different heads. [See Gherulal Parakh v.
Mahadeodas Maiya , Central Inland Water Transport Corpn. Ltd. v. Brojo
Nath Ganguly[20. , Zoroastrian Coop. Housing Society Ltd. v. District
Registrar, Coop. Societies (Urban)[ = 2005 (3) SCJ 590 and State
of Rajas than and others v. Basant Nahata 2005 (2) SCC 77 = 2005 (6)
SCJ 552.
85. In the 1940 Act, there was no specific provision for setting aside the
arbitration award on the ground that the same was in conflict with the public
policy in India. Section 30(c) was held to be wide enough to cover the heads
generally comprehended by the expression "public policy".
86. In Dharma Prathishthanam v. Madhok Construction Pvt. Ltd = 2004
(3) ArbLR 432 (SC).], a 3-Judge Bench of this Court held that where the
appointment of an arbitrator and the reference of a dispute to him is void ab
initio, the resulting award would also be liable to be set aside being totally
incompetent or invalid. Thus, if an award is set aside to be enforced, the same
may be declined for the reason that it is nullity, incapable of being enforced.
87. An agreement which is illegal would vitiate the arbitration agreement as
also an award, but in some cases an arbitration agreement may be valid or even
the arbitrator may determine the question of illegality of the contract. [See
Harbour Assurance Co (UK) Ltd v. Kansa General International Co Ltd.[
(1993)3A1I.E.R. 897] What would, however, be the nature of the illegality would
depend upon the law in force of the country.
88. An arbitration agreement must satisfy the requirements of its definition as
contained in Section 7 of the Arbitration Act. Within the meaning of Section 7,
an arbitration agreement must mean a valid arbitration agreement. Section 44 of
the Arbitration Act defines a foreign award. The said definition, however,
would not apply where 'unless the context otherwise requires' clause is
attracted.
89. A definition clause, therefore, does not necessarily apply in all possible
contexts in which the word may be found therein. The expression came to be
considered in a decision of this Court in Bennett Coleman and Co. (P) Ltd. v.
Punya Priya Das Gupta wherein it was held that the definitions of 'a
newspaper employee' and 'a working journalist' have to be construed in the
light of and subject to the context unless otherwise required.
90. An award made outside India, even if governed by Indian law, may be a
foreign award but it must satisfy two conditions, viz., that it is made (i) in
pursuance of an agreement in writing for arbitration to which the New York
Convention applies and (ii) in one of such territories which the Central Government
has notified in the Official Gazette to be a territory to which the New York
Convention applies. In this case, it appears that New York Convention does not
apply in its entirety in the sense that the first part of the award would be
governed by the ICA Rules whereas the second part would be governed by Paris
Rules.
91. The question as regard the legislative policy vis-a-vis the arbitration
agreement, therefore, will have to be considered from the said angle.
92. In Montrose Canned Foods Ltd. v. Eric Wells (Merchants) Ltd.[ (1965)
Lloyd's Rep. 5971], where buyers alleged various procedural defects in
arbitration proceedings, and applied to the court for an order setting aside or
remitting the award, Magaw, J. held that he had the jurisdiction to make an
order despite the existence of an appeal procedure and he exercised his
discretion to remit the award. Magaw J proceeded on the basis that there was no
contractual provision requiring the buyers to exhaust appeal procedure before
applying to the court for review. This may raise the question whether it is
permissible to exclude any right of access to the courts pending the hearing of
an appeal. Megaw J assumed that such provision would be valid. But there should
be question whether riles of that type can survive the public policy rule that
the parties cannot oust the jurisdiction of the courts.
93. In Brace Transport Corporation of Monrovia, Bermuda v. Orient Middle East
Lines Ltd., Saudia Arabia and others[(1965) Lloyd's Rep. 5971]', this Court
held that when a court is asked to enforce an award, its legal effect must not
only be recognized but legal sanctions must also be granted to ensure that it
is carried out. If an award is a nullity, question of its enforcement would,
thus, not arise.
94. It is of some significance to note that in terms of Section 45 of the 1996
Act, the court may refer the parties to arbitration unless it finds that the
said agreement is null and void. Thus, if a court while exercising its jurisdiction
under Section 45 of the 1996 Act is required to arrive at a finding as regards
validity of the arbitration agreement, there is absolutely no reason as to why
it cannot do so while enforcing an award.
95. If the parties did not expressly make a choice of the law governing the
arbitration agreement, a presumption would arise that the proper law governing
the arbitration would be the same as law of the country in which arbitration is
agreed to be held. Subsection (2) of Section 2 of the 1996 Act categorically
states that Part I would apply where the place of arbitration is in India and,
thus, by necessary implication, ousts the applicability thereof if the place of
arbitration is outside India, subject, may be, to just exceptions.
96. Clause 16 of the agreement reads as under:
"16. Construction:
The contract is to be constructed and to take effect as a contract made in
accordance with the laws of India."
97. In the instant case, indisputably, the law which would govern the
arbitration agreement is, in view of Clause 16 of the agreement, the Indian
Law.
98. We are not unmindful that the decision of this Court in Oil & Natural
Gas Corporation Ltd. v. Saw Pipes Ltd. [supra] had invited considerable adverse
comments but the correctness or otherwise of the said decision is not in
question before us. It is only for a larger Bench to consider the correctness
or otherwise of the said decision. The said decision is binding on us. The said
decision has been followed in a large number of cases. [See The Law and
Practice of Arbitration and Conciliation by O.P. Malhotra, Second edition, page
1174.]
99. In the said treatise, the learned author has considered the correctness of
ONGC (supra) from a large conspectus and opined at page 1184-1185:
"This survey of the contemporary English and Indian authorities reveals no
justification to fault ONGC. It is carefully calibrated judgment supported by
research into comparative law and sound rationale. This decision only modifies
and expands the scope of public policy of India as adumbrated in Renusagar. It
adds one more head, i.e., patent illegality of the award provided that the
illegality goes to the root of the matter or is so unfair and unreasonable that
it shocks the conscience of the court. Contrarily, it supports Renusagar in
letter and spirit. If the court had not so modified the law, it would have
failed in its duty to prevent subversion of societal goals and endangering the
public good.."
100. One may agree with the said view of the learned author or may not but, as
at present advised, we have to abide by the decision in ONGC (supra) and, thus,
the doctrine of public policy must be held to be a ground for setting aside an
arbitration agreement and consequently an award.
101. Such patent illegality, however, must go to the root of the matter. The
public policy, indisputably, should be unfair and unreasonable so as to shock
the conscience of the court. Where the Arbitrator, however, has gone contrary
to or beyond the expressed law of the contract or granted relief in the matter
not in dispute would come within the purview of Section 34 of the Act.
102. What would be a public policy would be a matter which would again depend
upon the nature of transaction and the nature of statute. For the said purpose,
the pleadings of the parties and the materials brought on record would be
relevant so as to enable the court to judge the concept of what was a public
gqod or public interest or what would otherwise be injurious to the public good
at the relevant point as contradistinguished by the policy of a particular
government. [See State of Rajasthan v. Basant Nahata (supra)].
103. It is not in dispute that the conditions precedent for applying Part II of
the 1996 Act have not been fulfilled in the instant case. Section 51 thereof to
which reference has been made provides for a saving clause in relation to a
right which had accrued to a party. A fine distinction exists between 'to
determine proper law' and 'to determine proper forum of court'. The effect of a
foreign award is different from the effect of the domestic award. In terms of
Section 46 of the Act, the foreign awards are binding.
PRECEDENTS:
104. We may at this juncture notice some of the decisions cited at the Bar.
In National Thermal Power Corporation v. The Singer Company and others ,
this Court was construing the provisions of the 1961 Act. What would be the
proper law in the context of an arbitration proceeding was stated, thus:
"Proper law is thus the law which the parties have expressly or impliedly
chosen, or which is imputed to them by reason of its closest and most intimate
connection with the contract. It must, however, be clarified that the
expression 'proper law' refers to the substantive principles of the domestic
law of the chosen system and not to its conflict of laws rules. The law of
contract is not affected by the doctrine of renvoi. (See Dicey, Vol. II, p.
1164.)"
105. In Sumitomo Heavy Industries Ltd. v. ONGC Ltd. and others[. 7 this Court was dealing with a case prior to coming into
force of the 1996 Act. This Court in that case noticed the provisions contained
in Section 47 of the 1940 Act and Section 9(b) of the 1961 Act stating:
"17...By reason of Section 9(b), the 1961 Act does not apply to any award
made on an arbitration agreement governed by the law of India. The 1961 Act,
therefore, does not apply to the arbitration agreement between the appellant
and the first respondent. The 1940 Act applies to it and, by reason of Section
14(2) thereof, the courts in India are entitled to receive the award made by
the second respondent. We must add in the interests of completeness that it is
not the case of the appellant that the High Court at Bombay lacked the
territorial jurisdiction to do so."
106. In Bhatia International v. Bulk Trading S.A. and another [supra] this
Court was considering a pre-award situation. Therein the court was concerned
with the power of the court to issue interim order and in that context it fell
for consideration whether Sections 9 and 17 occurring in Part I of the 1996 Act
would apply to the arbitration proceedings falling under Part II. It was
opined:
"26...The general provisions will apply to all Chapters or Parts unless
the statute expressly states that they are not to apply or where, in respect of
a matter, there is a separate provision in a separate Chapter or Part. Part II
deals with enforcement of foreign awards. Thus Section 44 (in Chapter I) and
Section 53 (in Chapter II) define foreign awards, as being awards covered by
arbitrations under the New York Convention and the Geneva Convention
respectively. Part II then contains provisions for enforcement of "foreign
awards" which necessarily would be different. For that reason special
provisions for enforcement of foreign awards are made in Part II. To the extent
that Part II provides a separate definition of an arbitral award and separate
provisions for enforcement of foreign awards, the provisions in Part I dealing
with these aspects will not apply to such foreign awards. It must immediately
be clarified that the arbitration not having taken place in India, all or some
of the provisions of Part I may also get excluded by an express or implied
agreement of parties. But if not so excluded the provisions of Part I will also
apply to "foreign awards". The opening words of Sections 45 and 54,
which are in Part II, read "notwithstanding anything contained in Part
I". Such a non obstante clause had to be put in because the provisions of
Part I apply to Part II." [Emphasis supplied]
107. Although correctness of the said decision is open to question, we need not
go into the same as at present advised.
108. In Furest Day Lawson Ltd. v. Jindal Exports Ltd , this Court opined
that "Once the court decides that the foreign award is enforceable, it can
proceed to take further effective steps for execution of the same. There arises
no question of making foreign award a rule of court/decree again"; but
enforceability thereof would depend upon the validity of the arbitration
agreement.
109. In Sundaram Finance Ltd. v. NEPC India Ltd.[ 9.
32. this Court held :
"The 1996 Act is very different from the Arbitration
Act, 1940. The provisions of this Act have, therefore, to be interpreted
and construed independently and in fact reference to the 1940 Act may actually
lead to misconstruction. In other words, the provisions of the 1996 Act have to
be interpreted being uninfluenced by the principles underlying the 1940 Act. In
order to get help in construing these provisions, it is more relevant to refer
to the UNCITRAL Model Law rather than the 1940 Act."
110. In Sundaram Finance (supra), this Court categorically held that an interim
order can be passed under the 1996 Act in terms of Section 9 only during the
arbitral proceedings or before the arbitral proceedings; whereas under the 1940
Act, the party could have applied for appointing arbitrator even when no matter
was pending before the court.
111. In Thyssen Stahlunion GMBH v. Steel Authority of India Ltd[ 9. 32. it was held :
"Present-day courts tend to adopt a purposive approach while interpreting
the statute which repeals the old law and for that purpose to take into account
the objects and reasons which led to the enacting of the new Act. We have seen
above that this approach was adopted by this Court in M.M.T.C. Ltd. case.
Provisions of both the Acts, old and new, are very different and it has been so
observed in Sundaram Finance Ltd. case. In that case, this Court also said that
provisions of the new Act have to be interpreted and construed independently
and that in fact reference to the old Act may actually lead to misconstruction
of the provisions of the new Act. The Court said that it will be more relevant,
while construing the provisions of the new Act, to refer to the UNCITRAL Model
Law rather than the old Act. In the case of Kuwait Minister of Public Works v.
Sir Frederick Snow and Partners the award was given before Kuwait became a
party to the New York Convention recognised by an Order in Council in England.
The House of Lords held that though a foreign award could be enforced in
England under the (U.K.) Arbitration Act, 1975 as when the proceedings for
enforcement of the award were initiated in England Kuwait had become a party to
the Convention. It negatived the contention that on the date the award was
given Kuwait was not a party to the New York Convention."
112. At this juncture, we may notice a decision in Adam v. Cape Industries33,
wherein, although the court was dealing with the enforcement of foreign
judgments, it laid down the principles relevant to the enforcement of New York
Convention awards stating that where it was alleged that a New York Convention
award should not be enforced because such enforcement would do substantial
injustice and, therefore, was contrary to public policy in respect whereof the
following had, normally, to be included amongst the relevant considerations :
the nature of the procedural inj ustice;
? whether the party resisting enforcement had invoked the supervisory
jurisdiction of the seat of the arbitration;
? whether a remedy was available under that jurisdiction;
? whether the courts of that jurisdiction had conclusively determined the
complaint in favour of upholding the award;
? if the party resisting enforcement had failed to invoke that remedial
jurisdiction, for what reason and, in particular, whether it was acting
unreasonably in failing to do so.
ANALYSIS:
113. It is not in dispute that the contention of HCL from the beginning was
that the provision contained in the second part of the arbitration is void ab
initio and of no effect. As noticed hereinbefore, it even filed a suit prior to
entering into the reference by the Arbitrator. Even after the award was passed,
proceedings before appropriate courts had been initiated. In its written
statement filed before the arbitral tribunal, the question as regards the
jurisdiction of the arbitrator was questione by it. The learned arbitrator had,
relying on or on the basis of the decisions, referred to hereinbefore, and also
an opinion rendered by a former judge of this Court held that such an
arbitration agreement is valid in law. In terms of Section 16 of the 1996 Act,
the arbitrator, keeping in view the fact that the question as regard his
jurisdiction had been raised was bound to decide the same before entering into
the merit of the matter. Only in the event, it came to the conclusion that the
arbitral tribunal had the requisite jurisdiction, it could have proceeded to
determine the merit of the matter. We say so in view of the fact that in the
event an arbitrator was of the opinion that he had no jurisdiction in the
matter, the arbitration clause being invalid in law, Centrotrade could have
preferred an appeal in terms of sub-sec. (2) of Section 37 of the 1996 Act
114. The question as regard lack of inherent jurisdiction on the part of the
arbitrator in view of the second part of the arbitration clause being opposed
to the public policy could have been raised by HCL in terms of Section 34 of
the 1996 Act.
115. Even if it is held that two tier arbitration is permissible, under the
1996 Act it might lead to an incongruity. A two tier arbitration is invalid in
law in the context of the 1996 Act having regard to Section 23 of the Contract
Act as statutory jurisdiction cannot be waived by contract. It is, thus, amply
clear that the very scheme of the 1996 Act does not contemplate a two tier
arbitration agreement of this nature.
116. Conditions as regard non-existence or invalidity of an arbitration agreement can, in our opinion, be raised while resisting enforcement of a foreign award. Section 4 of the 1996 Act contemplates existence of an arbitration agreement which would mean a valid arbitration agreement. If the arbitration agreement is void and of no effect, it is non est in the eye of law and, thus, cannot be enforced. An arbitrator derives its jurisdiction from a reference which would mean a dispute and difference to be adjudicated upon in pursuance of or in furtherance of a valid arbitration agreement. It is not in dispute that the parties agreed that the Indian law shall apply. The validity or legality of a contract, thus, must be judged on the touch-stone of Section 23 of the Indian Contract Act. If a contract is opposed to a public policy, the same is void and of no effect.
CONCLUSION:
117. It is doubtful whether the decisions of the Calcutta, Bombay and Madras
High Court could have been held to be valid if a situation of the present
nature had arisen therein, namely, both the 1940 and 1961 Acts are applicable
in relation to two different awards made at two different point of time. The
said decisions, therefore, might have been held to be good only in terms of the
provisions of the 1940 Act or the 1961 Act but the ratio thereof cannot be
extended to the cases falling under both the parts of the 1996 Act.
118. To bring clarity in the matter, we may notice the dichotomy arising
herein. If the first award was to be enforced (although no occasion arose
therefor), it could have been done only in terms of Part I of the Act. Despite
invocation of second part of the arbitration agreement, it would not cease to
be a decree in terms of Section 36 of the Act unless the operation thereof was
directed to be stayed. In other words, the first award of the arbitral
tribunal, on the expiry of the period specified for challenging the award,
became a decree despite invocation of the second part thereof. It is difficult
to comprehend iiiat despite a part of the award becoming a decree of the court,
the same would not be binding upon the arbitral tribunal. Section 34 of the
1996 Act provides for setting aside a domestic Indian award. It unlike the
English Arbitration Act does not permit the parties to limit or avoid the
operation of the statutory provisions.
119. Furthermore, the grounds for questioning a domestic award and a foreign
award are different. In the context of the 1996 Act, an arbitration agreement
which would otherwise be contrary to the provisions of the laws governing the
contract between the parties would be void being opposed to public policy.
120. The High Court's judgment, therefore, in my considered view, cannot be
sustained.
121. It is, thus, not necessary for us to advert to other questions raised at
the Bar. Although we do not agree with the reasons assigned by the High Court,
but we uphold the conclusion thereof on different grounds.
122. For the reasons aforementioned, Civil Appeal arising out of SLP (Civil)
No. 18611 of 2004 filed by M/s Centrotrade Minerals and Metal Inc., is
dismissed and Civil Appeal arising out of SLP (Civil) No.21340 of 2005
preferred by Hindustan Copper Ltd. is allowed. In the peculiar facts and
circumstances of the case, the parties shall pay and bear their own costs.
JUDGMENT (per Tarun Chatterjee, J.)
I have had an opportunity to go through the judgment delivered/proposed by my
learned brother S.B. Sinha, J. I am unable to agree with the conclusion as well
as the reasons of my learned brother and in that view of the matter I would
prefer to give my own reasons. In my view, the judgment and order of the
Division Bench and the learned Single Judge of the Calcutta High Court should
be set aside and the matter be sent back to International Chamber of Commerce
arbitrator for fresh disposal of the arbitration proceedings in London in the
manner indicated herein after.
Leave granted in both the SLPs.
2. These are two appeals which arise from the judgment or order of a Division
Bench of the Calcutta High Court reversing a judgment or order of a learned
Single Judge of the same High Court whereby and whereunder the Hindustan Copper
Limited (in short HCL) was directed to make payment to Centrotrade Minerals
& Metals Inc. (in short "Centrotrade").
3. Centrotrade is incorporated in United States of America dealing with sale
and purchase of non-precious metals including copper. Whereas HCL is a
Government of India undertaking and its business includes purchase of copper
concentrate. They entered into an agreement on 16th of January, 1996 where
Centrotrade was the seller and the HCL was the purchaser of copper concentrate.
Clause 14 of the agreement provides for arbitration in case any differences or
disputes arise between the parties. Clause 14 of the agreement reads as under:
"14. Arbitration –
All disputes and differences whatsoever arising between the parties out of, or
relating to the construction meaning and operation or effect of the contract or
the breach thereof shall be settled by arbitration in India through the
arbitration panel of the Indian Council of Arbitration in accordance with the
Rules of arbitration of the Indian Council of Arbitration. If either party is
in disagreement with the arbitration result in India, either party will have
the right to appeal to a second arbitrator in London, U.K. in accordance with
the rules of conciliation and arbitration of the International Chamber of
Commerce in effect on the date hereof and the result of this second arbitration
will be binding on both the parties. Judgment upon the award may be entered in
any Court of Jurisdiction".
4. The only other relevant clause of the agreement which is required to be
taken note of is Clause 16 which runs as under: -
"16. CONSTRUCTION:
The contract is to be constructed and to take effect as a contract made in
accordance with the laws of India."
5. Disputes arose between the parties to the agreement during December 1998 and
January 1999 and pursuant to clause 14 of the agreement, disputes were referred
to Indian Council of Arbitration where Centrotrade was the claimant. The Indian
Council of Arbitration appointed an arbitrator before whom Centrotrade claimed
an award for a sum of US $ 383, 442.90 (equivalent to Indian Rupees 1, 36, 73,
573.00 calculated at the exchange rate of Rs. 35.66 as prevailing on May 10,
1997) in respect of the goods shipped on board the vessels "M.V. MARITIME
MASTER" and "M.V. LOK PRITI", and for interest pendent lite at
such rate as Centrotrade was entitled to under the law and also for interest on
the sum awarded until decree was prounced in terms of the award. The arbitrator
appointed by the Indian Council of Arbitration, however, made a 'NIL' award
dated 15lh June, 1999. Disagreeing with the award passed by the arbitrator
appointed by the Indian Council of Arbitration, and relying on the second part
of Clause 14 of the agreement, Centrotrade approached the International Chamber
of Commerce (in short 'ICC') on 22nd February, 2000. The arbitrator appointed
by the ICC passed an award on 29lh of September, 2001 in favour of the
Centrotrade in the following mannen-
"a. HCL do pay Centrotrade the sum of $152, 112.33, inclusive of interest
to the date of this award in respect of the purchase price for the first
shipment.
a. HCL do pay Centrotrade the sum $ 15, 815.59, inclusive of interest to the
date of this Award in respect of demurrage due on the first shipment.
b. HCL do pay Centrotrade the sum of $ 284, 653.53, inclusive of interest to
the date of this Award in respect of the purchase price on the second shipment.
c. HCL do pay Centrotrade their legal costs in this arbitration in the sum of $
82, 733 and in addition the costs of the International court of Arbitration,
the arbitrator's fees and expenses totaling $ 29, 000.
d. HCL do pay Centrotrade compound interest on the above sums from the date of
this Award at 6% p.a. with quarterly rests until the date of actual
payment."
6. After the award was passed by the ICC arbitrator, an application was filed
by HCL seeking declaration of the award passed by the ICC as void and not
enforceable. At the same time, Centrotrade filed an application for enforcement
of the ICC Award. These applications were transferred to the original side of
the Calcutta High Court which were heard and disposed of by the judgment and
order of the learned Single Judge of that Court on 10th March 2005. The learned
Single Judge held that the ICC Award was enforceable in law and therefore
direction was made to HCL to make payment to Centrotrade. While making this
direction, it was inter alia held by the learned Single Judge as under: -
(a) The ICC award was a foreign award under Section 44 of the Arbitration and Conciliation Act, 1996 (in short 'the
Act') as it satisfied all the conditions mentioned thereunder, namely,
(i) There was commercial relationship between the parties;
(ii) The award was made in U.K. - a Convention country; and
(iii) The award was made in pursuance of a written agreement between the
parties.
(b) the plea of HCL that it was not given proper opportunity to present their
case before the arbitrator appointed by the ICC was liable to be rejected. In
this connection, the learned Judge observed that HCL had full knowledge of the
proceedings and proper opportunity to present their case was duly given to HCL
and therefore the plea of HCL that proper opportunity was not given, was rejected.
It was also held that some papers had in fact reached the arbitrator after the
stipulated time and the arbitrator also considered the submissions of HCL
before making the award.
(c) Under the Indian Law it was not impermissible to have an appellate arbitration
forum where the agreement provided for it, following the judgments in the cases
of Heeralal Agarwalla & Co. v. Joakim Nahapiet & Co.[ 1927
AIR(Cal) 647, Fazalally Jivaji Raja v. Khimji Poonji & Co.[ 1934
AIR(Bom) 476 and M.A. & Sons v. Madras Oil and Seeds Exchange Ltd?, and a
decision of this Court in Garikapatti Veeraya v. N. Subbaiah Choudhury .].
(d) The award passed by the ICC Arbitrator is the relevant 'award under the
Act.
(e) The question of the award of the Indian arbitrator becoming final and
binding on the parties did not arise at all.
(f) In view of second Part of Clause 14 of the Agreement it was only the ICC
award that was binding on the parties.
g) The ICC award was not contrary to public policy. Accordingly the claim of
the HCL that Indian award was a deemed decree of the court under Section 36 of
the Act and therefore a provision for appellate forum and an award passed by
it, are against public policy of India insofar as they undermine powers of
Indian Courts under Sections 34, 35 and 36 of the Act, was rejected.
7. However, on appeal, a Division Bench of the High Court, in substance, held
as under:
(a) The Second part of Clause 14 of the contract allowing a second arbitration
is valid. Relying on the decisions of Heeralal Agarwalla & Co. v. Joakim
Nahapiet & Co. (supra) Fazalally Jivaji Raja v. Khimji Poonji & Co.
(supra) MA. & Sons v. Madras Oil and Seeds Exchange Ltd., (supra), the
Division Bench held that an appellate arbitration forum or a second arbitration
was not impermissible under the Indian Law. Therefore, the award by the
arbitrator appointed by the ICC who is a second arbitrator is valid.
(b) The ICC award was not a 'foreign award' within the meaning of Section 44 of
the Act, as according to the Division Bench, mere fulfillment of conditions of
Sec. 11 of the Act did not make the award a 'foreign award'. This conclusion
was arrived at by the Division Bench on the ground that the conditions under
Section 44 are qualified by the expression - 'unless the context otherwise
requires'. According to it, if the context otherwise requires, then an award
which fulfills the conditions of Section 44 becomes a domestic award. According
to the Division Bench, a contract being governed by Indian laws in one such
context. Therefore, the Division Bench concluded that since the present case
where the law governing the contract was Indian law, the ICC Award though made
outside India, was not a "foreign award".
(c) On the interpretation of Clause 14 of the arbitration agreement, the Division
Bench held that the second arbitration in London was not in the nature of an
appeal against the award of the Indian Council of Arbitration. Therefore, the
ICC award cannot overrule the award passed by the Indian Arbitrator and thus it
was not enforceable due to the operation of the Indian award.
8. On the above observations and findings made by the Division Bench the
judgment of the learned Single Judge was set aside. Aggrieved thereby,
Centrotrade has filed Special Leave Petition against the aforesaid judgment of
the Division Bench of the Calcutta High Court and at the same time HCL has also
filed another Special Leave Petition against the same judgment. In both the
Special Leave Petitions notices were issued and they were taken up for final
hearing together for decision.
9. We have heard Mr. Sarkar learned senior counsel appearing for Centrotrade
and Mr. Debabrata Ray Choudhury learned senior counsel for HCL. I have also
examined the entire material on record including the arbitration agreement, the
awards and judgments of the Division Bench as well as the learned Single Judge.
Before us, the following issues were raised by the learned counsel for the
parties for decision in the appeals:-
(1) Whether second part of Ciause 14 of the agreement providing for a two tier
arbitration was valid and permissible in India under the Act?
(2) If it is valid, on the interpretation of clause 14 of the agreement, can it
be said that the ICC Arbitrator sat in appeal against the award of the Indian
Arbitrator?
(3) Whether the ICC award is a foreign award or not?
(4) Whether HCL was given proper opportunity to present its case before the ICC
arbitrator?
10. Issue No. 1 - Whether second part of Clause 14 of the agreement providing for
a two tier arbitration was valid and permissible in India under the Act? So far
as this issue is concerned, before Igo into it, it would be appropriate to
state that both the Division Bench and the learned Single Judge held that a
two-tier agreement was valid and permissible in India under the Act.
11. In my view, a two tier arbitration entered into before or after the coming
into force of the Act is valid and permissible in India. A two-tier arbitration
was permissible and valid in India under both, the 1899 Act and the 1940 Act,
is now well settled. In the case of Hiralal Agarwalla v. Jokin Nahopier &
Co. (supra), before coming into force of the present Act, it was held that the
agreement by parties to submit to more than one arbitration on the same dispute
was permissible. Applying the principles laid down in Hiralal's case (supra),
Bombay High Court in Fazalally Jivaji Raja v. Khimji Poonji & Co. (supra)
answered the issue saying that a two-tier arbitration is valid and permissible
in India. While answering this question, after considering the provisions of
the Indian Arbitration Act, 1890, Bombay High Court observed as follows:-
"The intention of the parties is to be sole guide for determining the mode
of working out the submission and reaching a final decision till the law of
arbitration is based upon the principles of withdrawing the disputes from the
ordinary Courts and enabling the parties to substitute a domestic tribunal.
Once a Tribunal reaches a final decision, as contemplated or agreed upon by the
parties, the Arbitration Act as it was enforced came to the help to the parties
to enforce the same decision."
12. This view of the Calcutta High Court and the Bombay High Court was also
accepted by the Madras High Court in the case of M.A. & Sons v. Madras Oil
& Seeds Exchange Ltd. (supra). I need not deal with the issue of validity
of two-tier arbitration in respect of disputes arising before the coming into
force of the Act any further.
13. In my view this position of law has remained the same as I do not find any
prohibition or ban being introduced by the Act from entering into an agreement
providing for a two-tier arbitration and that at the time of introduction of
the Act, it was well known to the legislature that it was consistently held and
approved by courts of India that two-tier arbitration was permissible in India.
14. However, it was submitted by Mr. Rai Choudhary learned senior counsel
appearing for HCL that use of the word "only" in Section 34 of the
Act would show the legislative intendment that the domestic award cannot be
challenged in any manner except in the manner provided by Sec. 34 of the Act.
This is not the position in the present case in view of second Part of clause
14 of the agreement. In this case the parties consciously agreed to have the
domestic award followed by the foreign award. In any view of the matter, the
provisions of Section 34 of the Act are not intended to curtail the powers of
the contracting parties to contract in the manner they desire
15. For the reasons aforesaid, I am in agreement with the conclusions of the
learned Single Judge as well as the Division Bench of the Calcutta High Court
that a two-tier arbitration agreement, even after coming into force of the
present Act, is valid and permissible in India. Before I switch over to the
other issues, I may point out that a question arose before us that this two
tier agreement under the instant case was opposed to public policy.
16. Coming to the issue of the agreement being against the public policy of
India, I wish to differ with the findings of my learned brother S.B. Sinha, J.
I agree that it is well settled that any contractual arrangement negating the
statutory provisions is invalid as being opposed to public policy. My learned
brother has held in his judgment, that the contractual arrangement entered into
by the parties in this case, in particular, second part of clause 14 of the
agreement would in all intent and purport made the provisions of Sections 34
and 36 of the 1996 Act nugatory. I disagree with this finding of my learned
brother. After a careful consideration of the 1996 Act, I find nothing in it
prohibiting the parties from entering into an agreement providing for a
two-tier arbitration. According to my learned brother, the part of the agreement
providing for two-tier arbitration is invalid under the 1996 Act and that
validity of an award can only be questioned before a court under Section 34 and
before no other forum chosen by the parties. In my view, however, the award
that must be considered by the court for its enforcement or on the question of
validity is the final award that has been passed following the procedure agreed
upon by the parties.
17. As already held, the reasoning adopted in the decisions, as noted herein
earlier, in the cases of Heeralal Agarwalla & Co. v. Joakim Nahapiet &
Co. (supra), Fazalally Jivaji Raja v. Khimji Poonji & Co. (supra) and M.A.
& Sons v. Madras Oil and Seeds Exchange Ltd. (supra), squarely apply to the
present Act as well. Just as there was no express prohibition on the appellate
arbitration in 1899 and 1940 Acts, so there is no express prohibition in the
1996 Act. The relevant section of 1996 Act is Section 35 which only provides
that "subject to this part of arbitral award shall be final and binding on
the parties and persons claiming under them respectively". Similarly, I
find that Condition No. 7 of the First Schedule of the 1940 Act provided that
"the award shall be final and binding on the parties and persons claiming
under them respectively". In M.A. & Son's case (supra) the Madras High
Court while dealing with this aspect of the matter made the following
observations:
"Naturally, these words have to be construed as subject to any right of
appeal, which might be provided for either by the contract itself, or by any
by-law governing the parties... No doubt, except upon grounds specified in Sec.
30 of the Act, an award is not liable to be set aside, and is final between the
parties. But, what is the award that is final between the parties, when the
procedure governing the parties itself makes provision for an initial award on
arbitration, and an appeal which may be instituted by either party aggrieved?
... As observed by the Supreme Court... the legal pursuit of successive
remedies will make them all proceedings 'connected by an intrinsic unity' and
'to be regarded as one legal proceedings". In that sense, it is the award
by the appellate Tribunal, if an appeal is preferred which becomes the final
award that governs the parties...".
18. The reasoning given by the Madras High Court in the aforesaid decision in
my view equally applies to the 1996 Act, since it is based on the meaning to be
given to the term "award" in the case of successive arbitration. In
view of the discussions made herein earlier, and considering the above
decisions, I am, therefore, of the view that Section 35 is not a bar to
appellate arbitration. In my view this section only comes into operation once
the arbitration proceedings as a whole which must include appellate
arbitrations, if any, have ended.
19. In my view allowing the appellate arbitrations is fully in consonance with
the objects of the 1966 Act.
20. Before parting with this aspect of the matter, we may make into
consideration the question whether an arbitration clause that leads to both
domestic and foreign awards on the same dispute, i.e., an arbitration clause
providing for two different modes of arbitration, is valid or not under the
Act. In His Lordship's view even if a two-tier agreement is valid under the
1996 Act, it cannot be such that one award is governed by Part I of the Act and
the award in the second tier governed by Part II of the 1996 Act, as the
procedure applicable to the arbitration proceedings as well as for enforcement
of the awards is different under different parts. In my view, there is nothing
under the 1996 Act prohibiting the parties from entering into an agreement
whereunder the first arbitration proceeding is conducted under Part I of the
1996 Act and the appeal therefrom is conducted under Part II of the 1996 Act.
In fact, earlier, two separate legislations, i.e., the 1940 and 1961 Act, dealt
with domestic awards and foreign awards respectively. However, the legislature
keeping in mind the necessity to have similarly in administration of domestic
awards as well as foreign awards, has consolidated the laws relating to
domestic and foreign awards in the 1996 Act, in effect making both the types of
awards enforceable under the same Act. Keeping this in mind, and also that
parties' autonomy is paramount, I am of the view that it is not impermissible
under the 1996 Act to have one part of the award governed by Part I and the
other part by Part II. Further, an appeal is an intrinsic part of the original
proceeding and it is the final award that comes out after an appeal is
preferred from the first award, that is relevant for the purpose of 1996 Act.
Thus is follows that nothing in the 1996 Act prohibits the parties from
providing a two-tier arbitration wherein one tier is dealt with under Part I
and the other under Part II of the 1996 Act. Such an agreement does not violate
the provisions of Sections 34 and 36 of the 1996 Act and it cannot be said to
be invalid as being opposed to public policy of India. Therefore, in my view,
the second part of clause 14 of the agreement and the ICC arbitration in its
furtherance, are not invalid as being opposed to public policy of India
21. It is well recognized as my learned brother S.B. Sinha, J. had pointed out
that party autonomy is a paramount consideration of the 1996 Act subject only
to such safeguards as are necessary in the public interest. Therefore, so long
as an agreement between the parties to enter into an appellate arbitration does
not derogate from the public interest, it is always permitted. The object of
Section 35 of the Act as observed in the 176th Report of the Law Commission, is
to limit the ambit of court intervention in arbitral awards and this object is
not affected by allowing appellate arbitrations. In this connection, it may be
noted that even in foreign jurisdiction such as U.K., the appellate
arbitrations are permitted. (See Russel on Arbitration 22nd Edition page 393).
22. That apart, even two-tier arbitrations wherein the original arbitration
proceeding is domestic and thus governed by Part I of 1996 Act, and the
appellate proceeding is foreign and thus governed by Part II of the Act can be
permitted. The judgment of my learned brother S.B. Sinha, J. that such
proceedings are opposed to the public policy of India because the Act provides
different procedures in respect of domestic and foreign awards appears to be
based on his views that the final award in such a case would be "an
admixture of domestic and foreign awards", such that "one part of
arbitration agreement shall be enforceable as a domestic award but the other
part would be enforceable as a foreign award."
But we must keep it in mind that the doctrine of merger equally applies in
cases of appellate arbitrations, such that on the issuance of appellate award,
the original award merges with it and only the appellate award is valid and
capable of enforcement. This was also the intention of the parties while
incorporating Part II of Clause 14 of the agreement, which clearly says that
only the award that would be passed by the ICC arbitrator would be binding on
the parties and the judgment upon that award may be entered in any court of
jurisdiction. Therefore, I am unable to agree that such two-tier arbitration
proceedings culminate into an admixture of two different types of awards, as
there is eventually only one award that subsists.
23. For the reasons aforesaid, I, therefore, conclude that the second Part of
Clause 14 of the agreement is valid and permissible in India under the Act.
24. Issue No. 2:- Whether the ICC Arbitrator sat in appeal against the award of
the Indian arbitrator or not?
In my view, to decide Issue No. 2, it is appropriate for us to read clause 14
of the agreement in depth and to find out from the same the intention of the
parties. In order to come to a proper conclusion on this issue, let us again
reproduce Clause 14 of the arbitration agreement.
"14. Arbitration -All disputes and differences whatsoever arising between
the parties out of, or relating to the construction meaning and operation or
effect of the contract or the breach thereof shall be settled by arbitration in
India through the arbitration panel of the Indian Council of Arbitration in
accordance with the Rules of arbitration of the Indian Council of Arbitration.
If either party is in disagreement with the arbitration result in India, either
party will have the right to appeal to a second arbitrator in London, U.K. in
accordance with the rules of conciliation and arbitration of the International
Chamber of Commerce in effect on the date hereof and the result of this second
arbitration will be binding on both the parties. Judgment upon the award may be
entered in any Court of Jurisdiction."
25. It appears that the first part of the arbitration agreement deals with
arbitration in accordance with the Rules of Arbitration of the Indian Council
of Arbitration. This part of Clause 14 of the arbitration agreement does not
say that the results of the arbitration will be binding on both the parties.
Nor it says that the judgment upon the award of the first arbitration may be
entered in any court of jurisdiction. On the other hand, the second Part of
Clause 14 of the agreement, as quoted above, clearly states that if a party is
in disagreement with the arbitration result in India then the aggrieved party
would have a right to appeal to a second arbitration in London, U.K. The word
'appeal', in my view, in this part of Clause 14 of the agreement has
significance. If the phrase 'in disagreement with the arbitration result in
India' and the word 'appeal' are read together, we may come to inevitable
conclusion that the ICC arbitrator would act as an appellate arbitrator based
in London, U.K. Moreover, if the second arbitration is not treated as an
appeal, then it would be pointless for a party dissatisfied with a 'NIL' Award
in India to refer the matter for a second arbitration in London, U.K. as the
'NIL' Award would always prevail over the ICC Award. Accordingly, this would
defeat the object of the provision in the second part of clause 14 which
clearly states that 'the results of this second arbitration will be binding on
both the parties'.
26. That part it is now well established that original and appellate
proceedings are not distinct legal proceedings, but only constitute stages of
the same legal proceedings, which are connected by an intrinsic unity.
27. Further, while passing the ICC Award, the ICC arbitrator in his award dated
29lh of September, 2001, had observed that the award passed by the Indian
Arbitrator was wrong. For clarity of factual situation, I refer to paragraph 18
of the award of the International Arbitrator and in my view the said paragraph
needs to be reproduced:-
"It is clear therefore that the dry weight, determined in accordance with
clause 6 at the discharge port is the final and binding basis for payment to be
made by HCL to Centrotrade. The Arbitration Award of 15lh June 1999 held
otherwise, but, in my view, this was obviously wrong. In that Awrd, the
arbitrator found that clause 4, and particularly clause 4.4 of the agreement
was the 'dominant clause' when that clause specifically dealt with the quality
certificate to be submitted with the shipping documents which would form the
basis for acceptance of the shipping documents under the letter of credit. When
in the context of the contract as a whole, it is plain that this part of the
terms relating to provisional payment, made on the basis of load-port quantity
and quality whereas the final amount due was to be determined by certificates
issued at the discharging port in relation to quantity and quality. In so far
as the first stage arbitrator found that there was no express promise given by
HCL to pay Centrotrade in respect of Centrotrade's claim, he appears to have
ignored the clear terms of the contract. Nor can there be any question of
applying any public policy of India "because copper is a valuable material
for the growth of Industrial development in the developing economy of
India", in order to influence the decision on this point, whether the
claim is framed in contract or for unjust enrichment".
28. As seen from the above quoted passage, the ICC arbitrator dealt with the
correctness of the first award and was not acting as a mere second arbitrator
but rather as an appellate forum.
29.1 have already held, because of the use of the word 'appeal' in the second
part of the arbitration clause it can be said that the intention of the parties
was that the second arbitration was in the nature of an appeal and that the
second award would take precedence over the first award. It is therefore amply
clear that the intention of the parties to the agreement was that if the
parties are dissatisfied with the first award and if approach was made to the
ICC arbitrator, in view of second Part of Clause 14 of the agreement, then the
first arbitration award would not be binding on the parties nor there would be
any existence of the same after the ICC award was made.
30. Thus, it cannot be said that the proceeding before the ICC arbitrator was
an independent proceeding nor it could be said that it was merely a second arbitration
in London, U.K. Therefore, I am unable to agree with the views expressed by the
Division Bench of the Calcutta High Court saying that the ICC arbitration was
not in the nature of appeal. Accordingly, the findings of the Division Bench of
the High Court on this issue are set aside.
31. Issue No. 3: Whether the ICC award is a Foreign Award or not?
The next question is whether the ICC award is a foreign award or not. The
learned Single Judge held that it is a foreign award, whereas, the Division Bench
of the Calcutta High Court held it not to be so and that it was in fact a
domestic award. Section 44 of the Act, deals with "foreign award". To
appreciate whether a particular award is a foreign award or not, it would be
appropriate for us to refer to Section 44 which reads as under:-
"44. Definition:- In this Chapter, unless the context, otherwise requires,
"foreign award" means an arbitral award on differences between person
arising out of legal relationships, whether contractual or not, considered as
commercial under the law in force in India, made on or after the 1 l'h day of
October, 1960
(a) in pursuance of an agreement in writing for arbitration to which the
Convention set forth in the First Schedule applies, and
(b) in one of such territories as the Central Government, being satisfied that
reciprocal provisions have been made may, by notification in the Official
Gazette, declare to be territories to which the said Convention applies".
32. From a bare perusal of Section 44 of the Act, it appears that in order to
come to a conclusion that a particular award is a foreign award, the following
conditions have to be satisfied.
(1) The legal relationship between the parties must be commercial.
(2) The award must be made in pursuance of an agreement in writing.
(3) The award must be made in a convention country.
33. In the present case, it cannot be disputed that the aforesaid three
conditions were satisfied, that is to say, there exists a commercial
relationship between the parties, the ICC award was made in pursuance of an
agreement in writing between the parties and the award was made in a Convention
Country (London, U.K.). In spite of all these conditions having been fully
satisfied, the Division Bench of the Calcutta High Court differed with the
views of the learned Single Judge by holding that it was a domestic award.
34. Section 44 of the Act, as quoted herein above, therefore, makes an award
foreign, if the above mentioned criteria are fulfilled, 'unless the context
otherwise requires'. The Division Bench, however, laid heavy stress on this
phrase to say that, even though the ICC award fulfils conditions under Section
44 of the Act, it cannot be considered to be a "foreign award".
According to the Division Bench one of the situations to which the phrase
"unless the context otherwise requires" is applicable, is when the
law governing an arbitration agreement is Indian law. Thereby, saying, that if
the law governing the "otherwise foreign award" is Indian, the award
becomes a domestic award. While coming to this decision, the Division Bench
relied on the decisions of this Court in Sumitomo Heavy Industries Limited v.
ONGC Ltd 7 and National Thermal Power
Corporation v. Singer Company[(. 6. . However, the aforesaid two
decisions of this Court were based on Section 9(b) of the repealed Foreign Awards (Recognition and Enforcement) Act, 1961.
Under the repealed Foreign Awards (Recognition and
Enforcement) Act, 1961, Section 9(b) expressly provided that its
provisions would not be applicable to any award made on an arbitration
agreement governed by the law of India. However, on repeal of this 1961 Act, by
Section 85 of the Act, no corresponding provision to Section 9(b) of the 1961
Act has been made. In other words, the position of law under Sec. 9(b) of the Foreign Awards (Recognition and Enforcement) Act, 1961 was
deliberately not inc6rporated in the present Act. Therefore, under the present
Act, an award in pursuance of an arbitration agreement governed by Indian Law,
if the conditions under Section 44 are satisfied, will not cease to be a
foreign award, merely because the arbitration agreement is governed by the law
of India. Accordingly, in my view, the aforesaid two decisions of this Court on
which strong reliance was placed by the Division Bench of the Calcutta High
Court can easily be distinguished. The Division Bench of the Calcutta High
Court also held that Section 48(1) (e) of the Act is one such provision which
attracts the first part of Section 44 i.e., the phrase "unless the context
otherwise requires". Section 48(1) (e) reads as under:-
"48. Conditions for enforcement of foreign awards.-
(1) Enforcement of a foreign award may be refused, at the request of the party
against whom it is invoked, only if that party furnishes to the court proof
that-
(2) The award has not yet become binding on the parties, or has been set aside
or suspended by a competent authority of the country in which, or under the law
of which, that award was made."
35. From a bare reading of this Section, it is evident that Section 48 (1) (e)
deals with the grounds for refusal of the enforcement of a Foreign Award.
Production of proof that such an award has been set aside or suspended by a
competent authority of the country in which, or under the law of which, that
award was made, cannot change a foreign award to a domestic award, but merely
makes it a foreign award which may not be enforced. In Sumitomo Heavy
Industries Limited v. ONGC Ltd. (supra) it was however held, in substance, by
this Court, where the contract is governed by Indian law and the seat of the
arbitration is elsewhere, wherein arbitrability of the dispute is established,
procedural law of the country of seat of arbitration governs the conduct of the
arbitration proceedings iill the award is delivered. Therefore, the phrase
"or under the law of which that award was made" used in Section 48(1)
(e) refers to the law of the country in which the arbitration had its seat
rather than the country whose law governs the substantive contract. It is true that
the contract and the agreement clause is governed by the substantial law of
India. It is an admitted position that the seat of the second arbitration was
in U.K. Therefore, relying on Sumitomo Heavy Industries v. ONGC Ltd. (supra)
the relevant country was U.K. under the procedural law of which the award was
made. Thus, Section 48(1) (e) does not by itself contemplate attracting First
part of Section 44 of the Act.
36. In this connection, the next question is whether the expression
"unless the context otherwise requires" as used in Section 44 of the
Act ever comes into play. This question can be looked into by the following
illustration where the expression takes relevance.
37. Let us consider a contract, including the arbitration agreement, governed
by Indian Law and under it the seat of arbitration is mentioned as U.K.
However, before the commencement of the arbitration proceeding, the parties
agree that though the physical seat of arbitration is in U.K., for all purposes
the seat of arbitration shall be deemed to be India and the arbitral
proceedings shall be conducted under the curial law of India. In this
situation, though all the conditions under Section 44 were satisfied the award
by the arbitrator cannot be said to be a foreign award. In such a situation, the
expression "unless the context otherwise requires" in Section 44
takes meaning and becomes applicable and relevant.
38. There is yet another aspect in this matter on the question whether the
award that was passed by the ICC arbitrator was a foreign award or not.
According to the Division Bench, as noted herein earlier, the award passed by
the ICC arbitrator was not a foreign award. Sub-section (2) of Sec. 2 of the
Act clearly says that Part I of the Act shall apply where the place of
arbitration is in India. Sub-section (7) of Section 2 of the Act says that an
arbitral award made under Part I shall be considered as a domestic award. In
view of sub-sections (2) and (7) of Section 2 of the Act read with Section 44,
in respect of which I have already dealt with, there cannot be any doubt that
the Division Bench was wrong in its conclusion that the award passed by the ICC
arbitrator was a domestic award. As noted herein earlier, we should also keep
in mind that Section 9(b) of the Foreign Awards
(Recognition and Enforcement) Act, 1961 which provided that it did not
apply to an arbitral award made pursuant to an arbitration agreement governed
by law of India, has been clearly omitted by Section 51 of the 1996 Act. In
this connection, reference may be made to a decision of this Court in Shreejee
Traco (I) Pvt. Ltd. v. Paperline International Inc.7.
39. In this view of the matter and in view of the discussions made herein
above, I am of the firm opinion that the award of the ICC arbitrator was not a
domestic award but a foreign award as rightly held by the learned Singled Judge
of the High Court.
40. Issue No. 4: Whether HCL was given proper opportunity to present its case
before the ICC arbitrator?Under Section 48(1) (b) enforcement of a foreign
award can be refused if:
"(b) the party against whom the award is invoked was not given proper
notice of the appointment of the arbitrator or of the arbitral proceedings or
was otherwise unable to present his case."
41. In the case at hand, HCL had the knowledge of appointment of the
arbitrator. In fact, it had approached the Indian courts to stall the ICC
arbitral proceedings. On a Special Leave Petition filed by Centrotrade against
the order of the Rajasthan High Court staying the ICC arbitral proceedings, an
order was passed by this Court by which the stay order of the Rajasthan High
Court was vacated on 8th February 2001 and directions were given for the ICC
proceedings to continue in accordance with law.
42. It is true, in his award, Mr. Jeremy Lionel Cooke, the ICC arbitrator has
noted that he was appointed by ICC on 7lh June and that HCL refused to
participate in the arbitral proceedings on the ground that the second
arbitration clause in the contract was null and void. He directed Centrotrade
and HCL to file submissions and supporting evidence through orders dated 20lh
December 2000, 19th January and 3rd May 2001. However, HCL did not comply with
these orders. On 30th July 2001, he sent a fax to HCL to find out whether they
intended to file their defence. He sent a further fax on 9th August 2001
informing them that he was proceeding with the Award. Then on 11th August 2001,
the ICC arbitrator received a reply seeking extension of time. He granted time
till 31s1 August, 2001. He received another request from HCL's representatives
on 27111 August 2001 for further extension of time. He granted extension till
12th September 2001. He received the first set of submissions filed by HCL,
without supporting evidence, on 13th September 2001. He considered those
submissions and took them into account while making the award. He has further
recorded in his award that:
"I made plain in my orders that no further material provided thereafter
would be taken into account, and I have not done so".
This last statement indicates that he received further material from HCL, which
he did not consider while making the award. On the face of it, it seems that
HCL was given sufficient opportunity to present its case by the arbitrator.
However, this question must be looked into from the then existing situation.
42. It must be noted that this Court vacated the stay on the proceedings on 8th
February 2001. The first direction of the ICC arbitrator to the parties, after
the order of this Court on 8lh February 2001, to serve submissions to him was
made on 3rd May 2001, i.e., after a time gap of nearly 3 months, Co-operation
of HCL was next requested only on 30lh July 2001, i.e., after a time gap of
nearly 2 months. Then the communication on 9Ih August 2001 stated that the
arbitrator was proceeding with the award. This time there was a response from
HCL. Upon there requests, a time limit of nearly one month ending on 12lh
September 2001, was given to HCL. The arbitrator received first set of
submissions filed by HCL on 13th September 2001. Then he made the award 16 days
later on 29th September 2001. It seems that between 13th and 29th September
2001, he did receive further material from HCL wh:"h he did not consider
while making the award on the ground that they were received after the time
limit granted by him to HCL had lapsed.
43. It is clear from the above lay out of facts that there have been delays in
the arbitral proceedings right from the beginning when Centrotrade approached
the ICC on 22nd February 2000. Most of the delays were due to HCL's refusal to
participate in the proceedings. However, there were some delays which cannot be
related to HCL's conduct. For instance, the period from the 8lh February 2001
when the order of this Court was made to 3rd May 2001 when the first direction
of the arbitrator was made. The whole arbitral proceeding was conducted in a
manner indicative of lack of urgency. Further, I find merit in the submission
of HCL that due to the total dislocation of air traffic caused by the terrorist
attack of 11lh September 2001, the materials sent by HCL to the ICC arbitrator
reached late. Under these circumstances, a delay of few days in serving their
submissions with supporting evidence, after having accepted to participate in
the arbitral proceedings, seems excusable and should have been excused.
Considering the overall picture of the circumstances and the delays, refusal of
the arbitrator to consider material received by him after 13th September 2001
and before 29th September 2001, seems to be based on a frivolous technicality. The
arbitrator ought to have considered all the material received by him before he
made the award on 29th September 2001. Considering the decisions in Hariom
Maheshwari v. Vinit Kumar Parikh 4 and
Minmetal Germany GmbH V. Ferco Steel Ltd.[ 1999 (1) AllER(Comm) 315, it
is true that where a party is refused an adjournment and where it is not
prevented from presenting its case, it cannot, normally, claim violation of
natural justice and denial of a fair hearing.
However, in the light of delays, some of which were not attributable to HCL's
conduct, it was only fair to execuse HCL's lapse in filing the relevant
material on time. Therefore, it can be said that HCL did not get a fair hearing
and could not effectively present its case.
44. For the reasons aforesaid, I am of the view that HCL could not effectively
present its case before the ICC arbitrator and therefore enforcement of the ICC
award should be refused in view of Section 48 (1) (b) of the Act. Accordingly,
the judgment of the Division Bench and also the judgment of the learned Single
Judge of the Calcutta High Court must be set aside and the matter be remitted
back to the ICC arbitrator for fresh disposal of the arbitral proceedings in
accordance with law after giving fair and reasonable opportunity to both the
parties to present their cases before him. In view of the fact that I have set
aside the award of the ICC arbitrator on the ground that HCL was unable to
effectively present its case before the ICC arbitrator, in compliance with
Section 48(1) (b) of the Act, I direct the ICC arbitrator to pass a fresh award
within three months from the date of commencement of the fresh arbitral
proceedings.
45. Accordingly, both the appeals are disposed of. There will be no order as to
costs.