SUPREME COURT OF INDIA
State of Maharashtra and Others
Vs
Gosikhurd Prakalpgrast Kalyankari Samiti and Others
Civil Appeal No. 3175 of 2006
(B. P. Singh and Altamas Kabir, JJ)
27.07.2006
B. P. SINGH, J.
1. Heard counsel for the parties.
2. This appeal is directed against the interim order of the High Court dated
November 24, 2004 whereby the High Court directed the State of Maharashtra to
pay compensation to the persons possession of whose lands have been taken in
connection with the execution of Gosikhurd Project, and further directed that
the lands
3. In respect of which awards have been made but possession not taken,
immediate steps be taken to take possession of the lands in question and to pay
compensation within two weeks.
4. Counsel for the State of Maharashtra submitted before us that the aforesaid
Gosikhurd Project was inaugurated in the year 1983 with a view to provide
irrigation facilities to the districts of Bhandara, Chandrapur and Nagpur which
fall within the Vidarbha region of the State of Maharashtra. It was originally
planned that the project shall be executed within 10 years but on account of
financial difficulties and other problems of the State, nothing could be done
immediately. In fact, bonds were issued and between 1997-2000, some amount was
also collected for the project. On 24-11-1998 Section 4 Notification under the
Land Acquisition Act was issued.
However, since the response to the bonds was not encouraging between the years
2000-2003, though the lands were acquired in the sense that awards were made,
the possession was not taken and consequently, the land owners were not paid
the compensation.
5.A public interest litigation was filed before the High Court which is pending
final disposal before the Nagpur Bench of ; the High Court. In the said public
interest litigation the High Court made the impugned order directing the State
to complete the acquisition proceeding and to pay compensation payable to the
land owners within the stipulated time frame.
6. We are informed by the State of Maharashtra that all the acquisitions have
been completed, awards made, possession taken and compensation paid and/or
deposited with the Land Acquisition Officer.
7. In a sense, nothing remains to be considered and decided by us except the
direction with regard to payment of interest at the rate of 12%. While issuing
notice on the Special Leave Petition we had granted stay of the impugned order
of High Court to the extent it directed the State of Maharashtra to take
possession of the lands of which possession had not been taken and for payment
to the landowners. However, since the State has deposited the full amount of
compensation payable to the landowners, the only question that remains to be
considered is with regard to the payment of interest at the rate of 12% as
directed by the High Court.
8. We record the statement of the Counsel for the State that Rs. 453 Crores
have been deposited with the Land Acquisition Collector and possession of the
lands acquired has been taken.
9. The State of Maharashtra came to this Court contending that the impugned
order may act as a precedent in other cases. It is submitted that having regard
to Section 16 of the Land Acquisition Act the discretion of the State to take
possession at the appropriate time cannot be curtailed by such a judicial
order. We notice from the judgment of the High Court that such a question was
not even considered by the High Court. Perhaps it was not so argued before the
High Court. We do not consider it appropriate in the facts of this case to go
into that question and therefore, we leave that question open to be considered
in an appropriate case.
10. We are informed that the main Writ Petition is to be heard and disposed of
shortly. We, therefore, direct that the parties may urge their contentions with
regard to payment of interest before the High Court hearing the Writ Petition,
and the High Court, having regard to the provisions of the Land Acquisition Act
will decide the said question in accordance with law. The directions regarding
payment of interest at the rate of 12% per annum is stayed.
Counsel for the respondent states that the claimants have not been paid the amount of compensation payable to the land owners. Land Acquisition Officer is directed to take immediate steps to make the payment. We direct accordingly.
This appeal is accordingly, disposed of. No orders as to cost.
J