Challenge in these appeals is to the judgment of a Division Bench of the
Kerala High Court holding that quantification of damages done and demanded from
the respondent No.1 cannot be legally sustained and accordingly they were set
aside. The writ petition was directed to be placed before the Division Bench by
a learned Single Judge. But the question referred by taught Single Judge i.e.
question of limitation was left open to be adjudicated by the appropriate
authority in accordance with law.
The background facts in a nutshell are as follows:-
The respondent No.1 had entered into Ext. P1 agreement with the
appellant-Kerala State Science and Technology, Thiruvananthapuram which is a
society registered under the Travancore Cochin Literary and Scientific
Societies Registration Act, 1995, on 16.05.1988 for the construction of
planetarium building of the Kerala State Science and Technology Museum and
allied Civil Works. Dispute having arisen between the parties the agreement
came to be terminated by Ext. P2 termination notice dated 03.11.1989 issued by
the appellant. Ext. P2 was followed by Ext. R1(c) letter from the managing
Partner of the respondent No.1 allegedly admitting the breach of contract. Suit
notice dated 06.11.1990 issued by the appellant to the respondent No.1 which
was replied by it as per Ext. P3 dated 31.12.1990 repudiating the alleged
breach and raising a counter-claim. According to the respondent No.1 there was
a long silence after Ext. P3 which was broken on 12.01.1998 on which date it
received Ext. P4 demand notice from the Deputy Tahsildar (RR),
Thiruvananthapuram under Section 34 of the Revenue Recovery Act 1968 calling
upon it to remit an amount of Rs.22, 10, 303/- with future interest at the rate
of 12% from 01.04.97. On receipt of Ext. P4 the respondent No.1 moved the High
Court with Arbitration Request No.2/98 under Section 11 of the Arbitration and
Conciliation Act, 1996 for the appointment of an arbitrator for resolution of
all disputes and differences between the parties concerning the performance of
the work under Ext. P1 agreement. The request was resisted by the appellant
contending, inter-alia, that there is no provision for arbitration in Ext. P1
agreement. It was also contended that as per clause 54 of Ext P1 agreement,
there is a specific exclusion of resolution of disputes by arbitration and the
Civil Courts at Thiruvananthapurarn alone are clothed with jurisdiction to
resolve the disputes arising between the parties out of Ext.P1 agreement. In
other words, not only Ext. P1 does not contain an arbitration clause, on the
contrary, Ext. P1 specifically rules out arbitration as a mode of settlement of
disputes or claims arising out of Ext. P1. Accepting the said contentions the
High Court rejected the request. After the said order was passed by the High
Court, the respondent No.1 filed writ petition, being O.P. No. 22633/98 to
quash Ext. P4 demand notice and for other reliefs which came to be disposed of
by judgment dated 17.11.98 directing the District Collector to consider and
pass orders on the representation preferred by the respondent No.1 within one
month from the date of receipt of a copy of the judgment. Pending issuance of
orders by the District Collector as aforesaid, the demand notice as evidenced
by Ext. P4 was stayed. As a sequel to the judgment, the District Collector
passed an order rejecting Ext. P8. Upon rejection of Ext.P8 by District
Collector's order Ext.P4 was revived and the respondent No.1 was called upon to
pay the amount mentioned therein being the loss suffered by the appellant in
re-arranging the work at the risk and cost of the respondent No.1. It was at
this stage, that the said respondent moved the High Court by filing a writ
petition praying for the issuance of a writ of certiorari or any other
appropriate writ, direction or order quashing the order and Ext.P4 demand
notice as illegal and arbitrary and for the issuance of a writ of mandamus
declaring that revenue recovery proceedings may be initiated against the
respondent No.1 only after prior adjudication by a court of law or any other
independent judicial/quasi-judicial body and other reliefs.
When the writ petition came up for hearing before learned Single Judge, it was
contended by the learned counsel for the writ-petitioner that since breach of
contract is not admitted, the first respondent (present appellant), standing in
the position of another party to the contract, cannot unilaterally assess the
damage alleged to have sustained by it on account of the alleged default on the
part of the writ-petitioner. It was also contended that the amount demanded as
per Ext. P4 is time barred. Further contention of the writ-petitioner was that
since the entire proceedings are barred, a time barred debt cannot be recovered
by recourse to revenue recovery proceedings. Stand of the first respondent
(present appellant) it is a society owned by the State and, therefore, Article
112 of the Limitation Act, 1963 (in short the 'Limitation Act') is applicable
and in that view, the demand raised is well within time. In view of the nature
of the contentions raised, learned Single Judge felt that the matter should be
placed before a Division Bench.
The Division Bench proceeded on the basis as if the main question that arose
for consideration was where a breach of conditions of a contract is not
admitted, whether is open for the contractee to adjudicate upon the disputed
question of breach as well as to assess the damages arising from the breach.
Though the High Court take note of the fact that the appellants placed reliance
on the document Ex.RI (C) to contend that there was admitted breach of contract
which resulted in termination of the contract, the respondent No.1 disputed the
position and submitted that no breach of contract can be spelt out as seen from
the document Ex.P3. High Court came to the conclusion that one of the
contracting parties cannot adjudicate upon a disputed question of breach as
well as assess the damage arising from the breach. It, however, noted that the
position would be different where there is no dispute or there is consensus
between the contracting parties regarding breach of conditions. In such a case
an officer of the State even though a party to the contract will be well within
its right in assessing the damages in view of the specific terms of clause 12
of the Contract.
In support of the appeals, learned counsel for the appellants submitted that
there was no dispute about breach of contract. In fact, in the letter dated
14.2.1990 Ex.R1(C) it was accepted that there was breach of contract. The
relevant portions of the document read as follows:
"We fully realize that the above demand put forth by the then General
Manger Sreekumar asking for enhancement of rates is against the spirit of the
agreed contract and that is why the museum and the Government took the decision
to rearrange the work through some other agency at out risk and cost.
We therefore, humbly request you to kindly permit us to withdraw the company's
letter referred above and offer the said work by our company.
1. We are ready to complete the work without any change in the rates for all
times of work that we have agreed previously.
2. We are ready to complete the work in all aspects without even giving us any
Mobilisation advance by the museum.
3. We request for an extension of 12 months time to complete the work in all
respects and we will strive our level best to finish the same much in
advance."
It was further submitted that before the learned Single Judge it was not
disputed that there was a breach of contract. In fact, the only point urged
before learned Single Judge related to the question whether the claim was
barred by time. Stand was that a time barred demand cannot be enforced through
revenue recovery proceedings. That was the issue which forms subject-matter of
dispute and considering the importance of that matter, learned single judge
felt that the matter should be heard by a Division Bench. It was submitted that
when a reference is made by learned Single Judge to the Division Bench on a
particular issue, the Division Bench cannot travel beyond that issue and decide
other matters.
In response, learned counsel for the respondent No.1 submitted that in fact
there was no reference by learned Single Judge, who only held that considering
the importance of the matter the case should be heard by a Division Bench. It
is also submitted that there was dispute regarding breach of conditions of
contract.
It is fairly well settled that when reference is made on a specific issued
either by a learned Single Judge or Division Bench to a larger Bench i.e.
Division Bench or Full Bench or Constitution Bench, as the case may be, the
Larger Bench cannot adjudicate upon an issue which is not the question
referred. (See: Kesho Nath Khurana v. Union of India and Others ,
Samaresh Chandra Bose v. The District Magistrate, Burdwan and Others and
K.C.P. Ltd. v. State Trading Corporation of India and Another . In the
instant case, there was no reference to Division Bench. Learned Single Judge
felt that in view of the contentions, a Division Bench should hear the case.
We find that before learned Single Judge there was practically no dispute that
there was breach of conditions of contract. In fact learned Single Judge noted
the position as follows:
"The question of termination of contract with effect from 25.11.1989
is not disputed. Petitioner did not challenge the termination order. As per the
terms of the contract, if it is re-tendered, the difference in the re-tender
amount and the loss suffered have to be paid by the petitioner apart from the
liquid damages." $
(Underlined for emphasis)
The learned Single Judge also noted that the main contention of the writ
petitioner was that the amount demanded was time barred. Reference was made to Section
71 of the Kerala Revenue Recovery Act, 1968. Therefore, it was contended before
learned Single Judge that when the matter is time barred even if the demand is
correct it cannot be enforced through revenue recovery proceedings. Stand of
the appellants on the contrary was that the society is owned by the State and,
therefore, Article 112 of the Limitation Act, 1963 is applicable and the demand
was raised within time.
Considering the rival submissions learned Single Judge held that in view of the
nature of contention the matter should be heard by a Division Bench.
Unfortunately the Division Bench did not consider the contentions which were
raised before the learned Single Judge. It also did not record any positive
finding as to whether the document relied upon by the appellant clearly
established admission of a breach of contract. The portion of the order of
learned Single Judge, quoted above, suggests that there was no dispute when
read in the context of the letter dated 14.2.1990.
As rightly contended by learned counsel for the appellant the basic issue
related to the question whether the demand was barred by limitation. As noted
above the Division Bench of the High Court did not examine this question.
Above being the question we set aside the order of the Division Bench and remit
the matter back for fresh consideration limiting the examination to the
question whether the demand by barred by limitation. Interim order dated
1.10.1999 shall be operative till the disposal of the matter by the Division Bench.
We make it clear that merely because interim protection has been given that
shall not be considered to be expression of opinion on merits.
The appeals are disposed of accordingly. No costs.