SUPREME COURT OF INDIA
Union of India
Vs
Messrs Shring Construction Company Private Limited
Appeal (Civil) 4516 of 2006 (Arising Out of S.L.P.(C) No.26627 of 2005)
(G. P. Mathur and A. K. Mathur, JJ)
17.10.2006
A. K. MATHUR, J.
Leave granted.
The short question involved in this appeal is whether Section 14 of the
Limitation is applicable to the Arbitration and
Conciliation Act, 1996 ( hereinafter to be referred to as the "Act
") or not ?
This appeal is directed against the judgment and order passed by the Division
Bench of High Court of Uttaranchal at Nainital in First Appeal No.67 of 2005 on
17.8.2005 whereby the Division Bench has affirmed the order dated 6.8.2005
passed by the District Judge, Dehradun in Arbitration Case No.170 of 2005
dismissing the application filed by the appellant under Section 34 of the Act
for setting aside the arbitral award on account of being barred by time.
Brief facts which are necessary for disposal of the present appeal are that the
appellant Union of India entered into a contract i.e. No. CEB/DDN/14 of 1993-94
( for a value of Rs.82, 34, 789/-) with the respondent herein through the Chief
Engineer, Bareilly Zone for construction of residential accommodation for
Officers and staff of Defence Accounts Department at Lansdowne. The work was to
be completed by the respondent in three phases by the dates specified in the
contract. However, the respondent failed to complete the contract work within
the stipulated period despite grant of extension of time by the appellant-
Union of India. However, the final bill of the respondent was duly settled.
Subsequently, the respondent raised a dispute and filed an application before
the High Court of Uttaranchal at Nainital for appointment of an arbitrator. The
High Court by its order dated 21.7.2003, appointed Justice K.D.Shahi ( former
Judge of Allahabad High Court) as the arbitrator. The award was published on
30.11.2004 and a copy thereof was received by the appellant on 3.12.2004. As
per the award, a sum of Rs.28, 94, 720/- was awarded in favour of the
respondent to be paid by the appellant- Union of India with interest at the
rate of 18% per annum. The appellant being aggrieved with the aforesaid award
filed a writ petition i.e. Writ Peition No.283 of 2005 challenging the award
before the High Court of Uttaranchal, at Nainital under a bona fide belief that
since the arbitrator had been appointed by the High Court, the award could be
challenged in the High Court by filing writ petition. However, the writ petition
was dismissed on 4.4.2005 in limine being not maintainable on the ground that
the award ought to have been challenged under Section 34 of the Act by filing
objections in the court of District Judge, Dehradun. Hence, an objection under
Section 34 of the Act was filed before the District Judge, Dehradun along with
an application for condonation of delay and the same came to be registered as
Arbitration Case No.170 of 2005. According to sub-section (3) of Section 34 of
the Act for setting aside an arbitral award, an application may be made within
three months from the date on which the party making application had received
the arbitral award or if a request had been made under Section 33, from the
date on which that request had been disposed of by the arbitral tribunal. There
is further proviso to sub-section (3) of Section 34 that the period for filing
the application can be extended if the applicant could show that he was
prevented by sufficient cause from making the application within the said
period of three months by further 30 days but not thereafter. In the present
case, admittedly the application was filed beyond even the extended period of
30 days. Hence, the District Judge dismissed the application for condonation of
delay as well application for setting aside the award being barred by time. The
first appeal preferred against that order before the High Court by the
appellant was also dismissed. Aggrieved against that order, the present appeal
has been filed.
Mr.B.Dutta, learned Additional Solicitor General for the appellant submitted
that it is true that Section 5 of the Limitation Act will have no application
in these proceedings because period of limitation has already been prescribed
under section 34(3) of the Act but Section 14 of the Limitation Act has not
been excluded from its ambit. It is pointed out that the impugned award was
challenged by filing a writ petition before the High Court but later on it was
found that the writ petition was not maintainable and accordingly, after
dismissal of the writ petition the present application was filed under section
34 of the Act along with application under section 5 of the Limitation Act. It
appears that the question with regard to applicability of Section 14 of the
Limitation Act was not examined by the High Court as well as the District
Judge. In fact, it was bona fide error on the part of the Union of India to
have approached the High Court. It was a misplaced impression that since the
High Court has appointed the arbitrator , therefore, its award can be challenged
before the High Court only. This Court recently in the case of State of
Goa v. Western Builders reported in has taken a view that applicability
of Section 14 of the Limitation Act is not excluded from the Act of 1996. This
Court in Western Builders (supra) has observed as follows :
" By virtue of Section 43 of the Act of 1996, the Limitation Act
applies to the proceedings under the Act of 1996 and the provisions of the
Limitation Act can only stand excluded to the extent wherever different period
has been prescribed under the Act of 1996. Since there is no prohibition
provided under Section 34, there is no reason why Section 14 of the Limitation
Act should not be read in the Act of 1996, which will advance the cause of
justice."
Therefore, Mr.Dutta, learned ASG submitted that the application filed by the
appellant for condonation of delay contending that the appellant was
prosecuting remedy before the High Court by filing writ petition should have
been considered and delay should have been condoned. This question seems not to
have been examined by the trial court as well as by the High Court. In view of
the decision in the Western Builders (supra) we think it just and proper to
remit this matter back to the trial court to decide whether the application for
setting aside the award under section 34 of the Act filed by the appellant
could be considered to be within the period of limitation i.e. after deducting
the period spent by the appellant in prosecuting the remedy before the High
Court.
As a result of our above discussion, we allow this appeal and set aside the
impugned order of the High Court and that of the District Judge and remit the
matter before the District Judge. The learned District Judge is directed to
examine the matter in the light of the decision in Western Builders (supra) and
dispose of the application filed by the appellant as expeditiously as possible
on its merit, without prejudice to any observation made in this order. There
would be no order as to costs.