SUPREME COURT OF INDIA
State of Arunachal Pradesh
Vs.
Messrs Damani Construction
(A.K.Mathur and V.S.Sirpurkar,JJ.,)
28.02.2007
JUDGMENT
A.K.Mathur,J.
1. Leave granted in both the Special Leave Petitions.
2. Since the question of law involved in both the appeals is common, they are
disposed of by this common judgment. For the sake of convenience, the facts
stated in Civil Appeal arising out of S.L.P.(c) No.14804 of 2005 are taken into
consideration.
3. This appeal is directed against the order passed by learned Single Judge of
the Gauhati High Court, Itanagar Bench in Writ Petition No.408 of 2004 whereby
learned Single Judge set aside the order dated 15.9.2004 passed by the Deputy
Commissioner cum District Judge, Papum Pare, District, Yupia in Miscellaneous
Application No.10 of 2004 condoning the delay in making application under
Section 34 of the Arbitration and Conciliation Act, 1996(hereinafter to be
referred to as 'the Act' ), being not maintainable. Hence, the order dated
15.9.2004 was set aside and the writ petition was allowed. Aggrieved against
this order passed by the High Court of Gauhati, Itanagar Bench, State of
Arunachal Pradesh has preferred the present appeal.
4. Brief facts which are necessary for disposal of this appeal are that the respondent
herein entered into a contract agreement bearing No.DD/03 of 1992-93 with the
State of Arunachal Pradesh in Public Works Department for executing the
contractual work of construction of road bridges. The value of the work in
question although was initially fixed at Rs.77.43 lakhs but on the basis of the
post tender negotiation by and between the parties, the price of the work was
re-fixed at Rs.1.15 crores. The work was to be completed within two calendar
years from the date of commencement of the work. The work commenced on
10.4.1993 and it was completed in March, 1999. According to the
petitioner-respondent herein the delay in execution of the work was due to
deviation from the original scope of work and several obstructions and
difficulties including delay in approval of the design and drawings and also in
making payment against running accounts bills from time to time. The respondent
herein raised bill for the contractual work which according to the respondent
was refused to be paid due to certain arbitrary and untenable reasons. Such
refusal gave rise to a dispute and accordingly, need arose for arbitration. The
respondent then approached the Court under section 11(6) of the Act which was
numbered and registered as Arbitration Case No.21 of 2000 and the same was
disposed of by the High Court appointing an arbitrator to adjudicate the
dispute between the parties. One arbitrator was appointed on 18.10.2001 but
subsequently that arbitrator was changed by the present arbitrator. On
12.10.2003 the arbitrator passed an interim award awarding Rs.65, 52, 878/-
with simple interest to be calculated if the award amount was not paid within
60 days from the date of the award. However, the period of limitation
prescribed under Section 34 (3) of the Act for setting aside the award expired
in the meantime. The appellant then wrote a letter to the arbitrator for review
of the award and also sought clarification in respect of the award on 2.4.2004.
On 10.4.2004 the arbitrator by his letter stated that he had no jurisdiction to
entertain the request for review of the award and also informed that the award
dated 12.10.2003 was in fact a final award pertaining to the issues involved.
On 21.6.2004 the respondent- petitioner filed an application for execution of
the interim award dated 12.10.2003 before the Deputy Commissioner. On 6.8.2004
the appellant filed an application under Section 34 of the Act for setting
aside the award dated 12.10.2003 together with an application under Section 5
of the Limitation Act, 1963 read with Section 34(3) of the Act for
condonation of delay in filing the application for setting aside the award. The
said application was entertained and was fixed for hearing on condonation of
delay after 15 days. Aggrieved against this order, a writ petition was filed by
the respondent herein but the same was disposed of by the High Court with the
observation that as the matter was pending before the court below it would not
be appropriate to interfere at this stage and left the Deputy Commissioner to
decide the matter. The Deputy Commissioner, Papum Pare, Itanagar by the
impugned order dated 15.9.2004 decided the application condoning the delay in
preferring the application under Section 34 of the Act by the appellant.
Aggrieved against this order, the present writ petition was filed by the
respondent herein. It is the legality of this order which was challenged before
the High Court. Learned Single Judge of the High Court after hearing both the
parties came to the conclusion that the order passed by the Deputy Commissioner
in condoning the delay was not correct and it took the view that under section
34 of the Act, there was a delay of seven months from the date of first order
and a delay of six months from the date of second order.
5. The plea of the appellant- State before the court below was that the award
was passed on 12.10.2003 and a copy was received on 23.10.2003. As such, the
period of limitation started from 23.10.2003. Since the letter was sent by the
appellant to the arbitrator on 2.4.20043 for review of the award and a reply
thereof was received on 10.4.2004 whereby the matter was clarified by the
arbitrator, therefore, the cause of action accrued in favour of the appellant
on 10.4.2004 and application under Section 34 of the Act was filed on 6.8.2004
i.e. within three months and the extended period of one month, therefore, it
was within limitation. Though this contention prevailed before the trial court
but the same failed before the High Court on the ground that the cause of
action accrued to the appellant on 23.10.2003 when the appellant received the
copy of the award and the letter which was written on 2.4.2004 was totally
misconceived. The interim award was final with regard to the claims raised
therein, therefore, the whole exercise undertaken by the appellant was totally
misconceived. Hence, learned Single Judge allowed the writ petition and set
aside the order of the trial court. Aggrieved against this order passed by the
learned Single Judge, the present appeal was filed.
We have heard learned counsel for the parties and perused the record. Learned
counsel for the appellant tried to persuade us that in fact the cause of action
has arisen to the appellant on 10.4.2004 when the letter was received from the
arbitrator and therefore, the appellant was entitled to count the period of
limitation from the date of receipt of the letter from the arbitrator and if
the limitation was to start from 10.4.2004 then the appellant has a right to
move an application for setting aside of the award under section 34 of the Act
within three months and the extended period of one month and the appellant
having filed the application on 6.8.2004, therefore, it was within time. The
submission of learned counsel for the appellant is totally misconceived and it
cannot be accepted. A perusal of the interim award passed by the arbitrator
clearly shows that it was final to the extent of the claims decided therein and
it may be relevant to refer to the concluding portion of the award which reads
as under:
" I further direct that the awarded amount is indicated above along with
the interest, wherever shown till the date of interim award amounting to Rs.65,
52, 878.00 (Rupees Sixty five lakhs fifty two thousand Eight hundred seventy
eight only), shall be paid by the Respondents to the Claimant within 60 days
from the date of the award, failing which a simple interest on the unpaid
amount @ 18% (Eighteen percent) per annum shall be payable to the Claimant by
the respondents after 60 days of this interim award."
6. Therefore, this interim award which did not mince any word and determined
the amount after discussing the claims in detail and finally calculated the
amount under each of the claims. Therefore, there was no confusion in this
award. It was absolutely thoughtlessness on the part of the appellant to have
written a letter after six months i.e. on 2.4.2004 seeking review of the
interim award to the following effect:
“While submitting the request for reviews the case, it is also requested that
your honour may kindly consider (sic.) the following points regarding mode of
payments, if at all, the payment is to be made, as the award given by your
honour is for the interim payment.
(a) Whether payment is to be made directly to M/s. Damani Construction Co. or
through honourable court.
(b) In case, the payment is to be made directly to M/s.Damani Construction Co.,
an equivalent Bank Guarantee Bond from any Nationalized Bank shall be required
from the Contractor since it will be an interim payment and final verdict
awaited.
Submitted for your kind consideration please."
7. Firstly, the letter had been designed not strictly under section 33 of the
Act because under Section 33 of the Act a party can seek certain correction in
computation of errors, or clerical or typographical errors or any other errors
of a similar nature occurring in the award with notice to the other party or if
agreed between the parties, a party may request the arbitral tribunal to give
an interpretation of a specific point or part of the award. This application which
was moved by the appellant does not come within any of the criteria falling
under Section 33(1) of the Act. It was designed as if the appellant was seeking
review of the award. Since the Tribunal had no power of review on merit,
therefore, the application moved by the appellant was wholly misconceived.
Secondly, it was prayed whether the payment was to be made directly to the
respondent or through the Court or that the respondent might be asked to
furnish Bank guarantee from a nationalized Bank as it was an interim award,
till final verdict was awaited. Both these prayers in this case were not within
the scope of Section 33. Neither review was maintainable nor did the prayer
which had been made in the application have anything to do with Section 33 of
the Act. The prayer was with regard to the mode of payment. When this
application does not come within the purview of Section 33 of the Act, the
application was totally misconceived and accordingly the arbitrator by
communication dated 10.4.2004 replied to the following effect.
“However, for your benefit I may mention here that as per the scheme of the Act of 1996, the issues/ claims that have been adjudicated by the interim award dated 12.10.2003 are final and the same issues cannot be gone into once again at the time of passing the final award."
8. Therefore, the reply given by the arbitrator does not give any fresh cause of action to the appellant so as to move an application under Section 34 (3) of the Act. In fact , when the award dated 12.10.2003 was passed the only option with the appellant was either to have moved an application under Section 34 within three months as required under sub-section (3) of Section 34 or within the extended period of another 30 days. But in stead of that a totally misconceived application was filed and there too the prayer was for review and with regard to mode of payment. The question of review was totally misconceived as there is no such provision in the Act for review of the award by the arbitrator and the clarification sought for as to the mode of payment is not contemplated under Section 33 of the Act. Therefore, in this background, the application was totally misconceived and the reply sent by the arbitrator does not entitle the appellant a fresh cause of action so as to file an application under Section 34(3) of the Act, taking it as the starting point of limitation from the date of reply given by the arbitrator i.e. 10.4.2004.
9. Thus, in this background, the view taken by learned Single Judge appears to
be justified and there is no ground to interfere in this appeal. Consequently,
there is no merit in both the appeals and the same are dismissed with no order
as to costs.