SUPREME COURT OF INDIA
BOC India Limited
Vs
Bhagwati Oxygen Limited
(Dr. AR. Lakshmanan and Tarun Chatterjee, JJ)
JUDGMENT
TARUN CHATTERJEE, J.
Leave granted.
This is an appeal from a judgment of a Division Bench of the Calcutta High Court
dismissing an appeal which was filed against the judgment of a learned Judge
refusing to accept the objection filed by the appellant under Section 30 read
with Section 33 of the Arbitration Act, 1940
(hereinafter referred to as the "Act"). The brief facts of this
appeal are as follow:
BOC Ltd. being the appellant herein and one Nippon Sansa K.K. (NSKK) entered
into an agreement in order to facilitate the respondent to import components
for setting up a 25 tons per day Oxygen plant at Ghatsila, Bihar (now in the
State of Jharkhand). In the month of April/May 1990 the appellant and the
respondent entered into a contract for erection, installation and commission of
the aforesaid plant at Ghatsila, Jharkhand. On 5th June 1990 a tripartite
meeting between the representatives of the appellant and the respondent and
NSKK were held where the letter of intent was signed and purchase orders were
issued by the respondent in favour of the appellant. The respondent awarded a
turnkey contract on 6th June, 1990 to the appellant for manufacture, supply,
erection and commission of the said plant. Vide letter dated 18th December
1990, the respondent had agreed to pay interest on margin money and reimburse
the same to the appellant. The appellant thereafter on 31st March 1992 raised
final invoices and subsequently on 13th April 1992 the respondent raised claims
and sought refund from the appellant. By a letter dated 9th March 1993 the
appellant informed the respondent indicating therein the interest payable by
them to the respondent. Finally, when the prior invoice and letter were not
responded to, on 13th September 1993 the respondent again raised claims and
sought refund from the appellant. When the refund was not made by the
appellant, the respondent made an application under Sections 8 and 33 of the
Act for the appointment of an arbitrator on 24th November 1995 in the High
Court at Calcutta.
In the meantime, on 21st September 1995 the High Court directed the appellant
to release the spares to the respondent on payment of Rs. 10, 19, 000/- by
them. A lawyer was thereafter appointed as Arbitrator by consent of the parties
and the said arbitrator subsequently was replaced on 12th February, 1996 by
Late Arbitrator Shri P.K. Roy. On 29th July 2000, Late Shri Roy had passed his
award in favour of the respondent for a sum of Rs. 24, 92, 165/- with an
interest of 12 per cent on the amount. However, the counter claim of the
appellant was rejected. On 30th October, 2000, the appellant filed an
application for setting aside the award passed by the arbitrator under Section
30 of the Act before the High Court at Calcutta. In the said application, the
appellant raised objection to the effect that the award in question suffered
errors apparent on the face of it. It was alleged that the arbitrator erred in
awarding the claim of the respondent for a sum of Rs. 17, 95, 710/- relating to
claim no. 9 although the learned arbitrator held issue no. 4 in favour of the
appellant. It was also alleged that since the appellant had not realised any sum
in excess of Rs. 50 lacs against indigenous supply, the award of the learned
arbitrator to the effect that the respondent was entitled to receive back from
the appellant, the said sum of Rs. 17, 95, 710/-, was not only erroneous on the
face of the award but also contradictory and inconsistent with the findings of
the arbitrator against issue no. 4. It was further alleged by the appellant
under Section 30 of the Act that the learned arbitrator committed error
apparent on the face of the award and had acted in excess of his jurisdiction
by awarding the aforesaid sum of Rs. 17, 95, 710/- in favour of the respondent
as the award was contrary to the findings made by the learned arbitrator
himself and therefore was liable to be set aside. We are not dealing with the
other objections taken by the appellant in its objection under Section 30 of
the Act as noted herein after. A learned Judge of the High Court by a detailed
judgment had rejected the objection filed under Section 30 of the Act and had
refused to set aside the award passed by the arbitrator on the ground that on
the materials on record, the award was not liable to be set aside on such
grounds.
Feeling aggrieved by the judgment of the learned Single Judge, the appellant
filed an appeal before the Division Bench of the High Court which was also
dismissed against which the present Special Leave Petition was filed in respect
of which leave has been granted.
We have heard Mr. Soli J. Sorabjee, learned senior counsel appearing for the
appellant and Mr. Bhaskar P. Gupta, learned senior counsel appearing for the
respondent. We have also considered the award passed by the Sole Arbitrator
Late Mr. P.K. Roy and the objection raised against such award under Section 30
of the Act and also the judgment of the learned Single Judge as well as the
Division Bench of the High Court in detail.
Before we proceed further, as noted herein earlier, we keep it on record that
before the Division Bench of the High Court, the appellant restricted his
grounds for setting aside the award in respect of Claim No.9 of the statement
of claim only and prayed for the same. Before us, Mr. Sorabjee also restricted
his submissions only in respect of Claim No.9 of the statement of claim and
also prayed for setting aside the award restricted to Claim No.9 only. In view
of this stand taken by the appellant, we need not dwell upon other questions
and are concentrating only on the issue raised before us by the learned senior
counsel appearing for the appellant.
As noted, we may reiterate that the respondent placed Purchase Order (P.O.)
dated 6th of June, 1990 to the appellant for supply, installation and
commissioning of oxygen plant at a lump sum price of Rs.347.40 lacs. This fixed
price was, however, subject to variation only in respect of imported components
of supply on account of exchange rate variation and customs duty variation.
This would be evident from clause 1.1 of the P.O. as quoted herein after. It is
not in dispute that the job was completed in June/July, 1992.
Due to variation in exchange rate and also in customs duty, the lump sum price
of Rs.347.40 lacs increased to Rs.4, 62, 60, 543. The appellant submitted its
bill inclusive of taxes as per the contract and the break up which is as
follows:
“A. Annexure 1 Invoice No. 3224 - Rs.4, 62, 60, 543/-
B. Invoice dated 31.3.1992 Rs. 5, 91, 625/-
C. Taxes paid as per contract (as mentioned in Invoice No.3225 and 3227) - Rs.
6, 25, 984/-Total-Rs.4, 74, 78, 152/-"
As stated herein earlier, in view of the arbitration clause accepted by the
parties, the respondent had raised a dispute after payment and the matter was
referred to arbitration. The respondent submitted its claim before the
arbitrator under 12 heads for a total amount of Rs.1, 79, 76, 716/-. The
appellant also submitted its counter claim. The sole arbitrator Late Shri
P.K.Roy passed an award on 29th of July, 2000, as noted herein earlier and
allowed the claim of the respondent in respect of the following items:
"A. Claim No.1: Interest on margin money -Rs.1, 80, 000/-
B. Claim No.3: Bank charges and interest - Rs.3, 10, 932/-
C. Claim No.7: Refund on REP Licence Rs. 35, 000/-
D. Claim No.8 : Foreign Technician fees, Air fare, hotel expenses- Rs. 1, 70,
523/-
E.Claim No.9 Indigenous Supply- Rs.17, 95, 710/-
Rs.24, 92, 165/-"
As noted herein earlier, the arbitrator, however, dismissed all other claims of
the respondent and also the counter claim of the appellant.
Mr. Sorabjee contended that since the award in question was contrary to the
findings of the learned arbitrator himself, the learned arbitrator in passing
the award had misconducted himself and accordingly the award was arbitrary and
liable to be set aside in respect of claim No.9 of the respondent.
Mr. Sorabjee had drawn our attention to the purchase order, which contained
price for manufacture and supply of plant and equipment comprising both
imported and indigenous components for installation, erection and commissioning
thereof. He had also drawn our attention to the fact that a lump sum of
Rs.379.49 lacs was fixed as a price for doing the job. The 'basis of price' is
mentioned in Clause 1.1. of the contract which is as follows :-
"Basis of price includes
1.1.1 -The value of the imported components will be 128.66 million YEN CIF
Calcutta.
1.1.2 Customs duty @ 80% of CIF value based on 'Project Import".
1.1.3 Stevedoring, port handling, customs clearance, inland transportation and
transit insurance from port to site @ 5% of CIF Value.
1.1.4 Exchange rate has been taken at 100 yen Rs.10.9.
1.1.5 The price includes excise duty towards supply wherever applicable as on
date, but does not include sales tax, entry tax, income tax on foreign
technicians and other Govt. impositions, if any, which will be paid extra, as
applicable.
1.1.6 Any variation in 1.1 to 1.1.5 except 1.1.3 indicated above will be
adjusted.
1.1.7 The premium of Rs.5 lakhs towards purchase of REP Licences is the maximum
amount payable by us. Any decrease below RS.5 lakhs will be passed on to us.
1.1.8 The above price is also subject to 'General Conditions of sale and
installation of Plant and Equipment'. In the event of any conflict between the
clauses, one mentioned herein shall prevail. Where General Conditions are not
applicable, have been marked accordingly and initiated by competent authority."
Clause 4 of the contract contains Terms of Payment. Indigenous supply is
included in clause 4.4 which reads as following-
"Supply Portion-Rs.50 lacs.10% advance against order.10% advance within
3 months.80% advance against proforma invoice before dispatch.4.5 For Erection
and Rs.15 lakhs. Commissioning 10% advance against order 10% advance on opening
of site 70% pro rata on monthly basis. 10% on completion of erection and
commissioning."
In the statement of claim, as made by the respondent, the value of projected
imported components worked out to Rs.264.44 lacs in the order shown below :-
"(i) CIF value of JY 128.66 million Rs.1, 40, 23, 940/-
(ii) Handling charges @ 5% of CIF- Rs. 7, 01, 198/-
(iii) Import Duty @ 80% (based on Project Import) Rs.1, 12, 19, 152/- (iv) REP
Licence premium Rs. 5, 00, 000/-
Total - Rs.2, 64, 44, 290/-"
In the said statement of claim the total value of the order worked out as
imported components (Rs.264.44 lacs) plus indigenous components (Rs.50 lacs)
plus erection and commissioning (Rs.15 lacs) comes to Rs.329.44 lacs. But the
value was kept at Rs.347.40 lacs, i.e., a cushion money of Rs.18 lacs
approximately was provided for securing the forward cover for foreign exchange
and other variations.
In paragraph 21 of the said statement of claim, the respondent stated that
under the aforesaid order, the appellant was required to supply indigenous
components plants and machinery as set out in Clause 2.1.2 to 2.3.4 of the
order for a sum of Rs.50 lacs. The appellant further stated that the indigenous
supply was not subjected to variation as per the order. The appellant contrary
to and in breach of the said order raised invoices for a sum of Rs.67, 95,
710/- against indigenous supply and realized an excess amount of Rs.17, 95,
710/- from the respondent. Therefore, the respondent claimed refund of Rs.17,
95, 710/- from the appellant.
According to Mr. Sorabjee, the learned Arbitrator had misconducted himself in
passing the award under Section 30(1)(a) of the Act and thus the award was
liable to be set aside so far as Claim No.9 (Award No.9) of the Arbitrator is
concerned. According to Mr. Sorabjee, the award in respect of Award No.9 is
contrary to the findings of the learned Arbitrator and liable to be set aside
as it amounted to judicial misconduct. As noted herein earlier, purchase order
dated 5th June, 1990 provided for a lump sum price of Rs.347.40 lacs subject to
variation of importation of the contract and exchange rates. He further
submitted that since price was a lump sum amount no specific price could be
allotted to a particular item. He contended that the value of Rs.50 lacs and
Rs.15 lacs mentioned against indigenous supply under Clause 4.4 of the P.O. and
against erection and commissioning mentioned in Clause 4.5 of the P.O. was not
appearing as a component of price but appearing as "terms of payment"
(4.0 of P.O.). Accordingly, Mr. Sorabjee sought to contend that the Arbitrator
had gone beyond his jurisdiction in awarding Rs.50 lacs and Rs.15 lacs, mentioned
against indigenous supply and against erection and commissioning, as the same
was not appearing as 'component of price'. Therefore, he had misconducted
himself in awarding the amount in respect of Award No.9 (Claim No. 9 of the
Statement Of Claim). In support of this contention, Mr. Sorabjee relied on a
decision of this Court in K.P. Poulose vs. State of Kerala, Â . Mr.
Sorabjee particularly relied on para 6 of the judgment and submitted that the
Arbitrator was guilty of legal misconduct as he had gone beyond his jurisdiction
to pass an award on Claim No.9.
This submission of Mr. Sorabjee was contested by Mr. Bhaskar P. Gupta, learned
Senior Counsel, appearing on behalf of the respondent. Mr. Gupta contended that
considering the terms of the contract, it cannot be said that the Arbitrator
had acted beyond his jurisdiction in passing the award in respect of Claim
No.9. So far as the decision of this Court, relied on by Mr. Sorabjee, is
concerned, Mr. Gupta submitted that this decision cannot be applied in the facts
and circumstances of the present case. In that decision, according to Mr.Gupta
documents produced before the Arbitrator were contrary to the award passed. In
this connection, Mr. Gupta had also drawn our attention to the fact that the
arbitrator in that case had ignored two very material documents resulting in
miscarriage of justice. If we read para 6 of this decision carefully we will
find that the principle which was laid down in the decision was that an award
could be set aside on the ground that the arbitrator had misconducted himself
when it was found that the arbitrator on the face of the record arrived at an
inconsistent decision even on his own finding or arrived at a decision by
ignoring very material documents which throw abundant light on the controversy
to help in arriving at a just and fair decision. Keeping this principle in
mind, this court held that the arbitrator had misconducted the proceedings in
that case.
This is not the position in the present case. For deciding this question, it
would be necessary for us to look into the P.O. Clause 4.0 contains "terms
of payment". Clause 4.4 of the P.O. contains the indigenous supplies which
clearly indicates Rs.50 lacs would be the advance at the rate of 10% against
the date of order within 30 days and 10% advance within three months and 80%
advance against proforma invoice before dispatch. Clause 4.5 of the terms of
payment provides for erection and commissioning which indicates Rs.15 lacs in
respect of which 10% advance against order, 10% advance on opening of site, 70%
on pro rata on monthly basis, 10% on completion of erection and commissioning.
The Arbitrator had taken into consideration the claim of the respondent on
indigenous supplies. He had also taken into consideration the total value of the
contract which was Rs.347.40 lacs.
A bare perusal of the award of the Arbitrator would show that he had considered
the figure of 17, 95, 710/- which is included in the lump sum contract price as
consideration payable to the respondent for services rendered by it towards
importation of plants components. From the award it will also be evident that
in respect of the claim of Rs.17, 95, 710/- against indigenous supply attention
was drawn to the works given in para 10 [a], 10 [b] and 10 [c] of the statement
of claim. If we assign individual value to the individual jobs, the total works
out to Rs.3, 29, 44, 290/- leaving a balance of Rs.17, 95, 710/-. The learned
Arbitrator in his award also considered that the break-up was an admitted
position which would appear from para 10[c] of the Statement of Claim and the
sum of Rs.17, 95, 710/-, the appellant had recovered under the bill issued
against indigenous supply and the respondent paid the amount without any
objection. While the Arbitrator has considered the fact that the appellant had
realised the differential amount of Rs.17, 95, 710/- from the respondent
against indigenous supply, it cannot be said to mean that the value of
indigenous supply had gone up from Rs.50 lacs to Rs.67, 95, 710/- as according
to the terms of the contract the value of indigenous supply remained at Rs.67,
95, 710/- and the appellant realised the differential amount of Rs.17, 95,
710/- against indigenous supply. Accordingly the Arbitrator was justified in
holding that the said sum of Rs.17, 95, 710/- was on account of expenses that
might have been incurred by the respondent in executing the contract.
In the case of Trustees of the Port of Madras Vs. Engineering Construction
Corporation Ltd. Â 0, while this Court dealing
with a situation when an award can be set aside under Section 30 of the Arbitration Act, 1940 held as under:
"The above decisions make it clear that the error apparent on the face
of the award contemplated by Section 16 (I) (c) as well as Section 30(c) of the
Arbitration Act, 1940 is an error of law apparent on
the face of the award and not an error of fact. It is equally clear that an
error of law on the face of the award means an error of law which can be
discovered from the award itself or from a document actually incorporated
therein. A note of clarification may be appended viz., where the parties choose
to refer a question of law as a separate and distinct matter, then the Court
cannot interfere with the award even if the award lays down a wrong proposition
of law or decides the question of law referred to it in an erroneous fashion.
Otherwise, the well settled position is that an arbitrator "cannot ignore
the law or mis-apply it in order to do what he thinks is just and
reasonable." (See Thawardas Perumal v. Union of India, (1955)'-) SCR 48:
 1955 AIR(SC) 468."
12.03.2007
(In Paragraph 20 Of The Said Decision This Court Also Held That The Proposition That Emerges Is That In The Case Of A Reasoned Award, The Court Can Interfere If The Award Is Based Upon A Proposition Of Law Which Is Unsound In Law and That The Erroneous Proposition Of Law Must Be Established To Have Vitiated The Decision. It Has Also Been Held In That Decision That The Error Of Law Must Appear From The Award Itself Or From Any Document Or Note Incorporated In It Or Appended To It. This Court Also Held That It Was Not Permissible To Travel and Consider Materials Not Incorporated Or Appended To The Award. So Far As The Facts Of The Present Case Are Concerned, We Do Not Think That The Award Of The Arbitrator Can At All Be Interfered With As The Award Was Not Based Upon Either A Proposition Of Law Which Is Unsound Or An Erroneous Proposition Of Law Was Established To Have Vitiated The Decision. As Noted Herein Earlier, The Arbitrator Had Considered All Aspects Of The Matter Including The Terms Of The Contract and All The Materials On Record and The Statement Of Claim and Has Come To A , JJ)conclusion of fact. Such being the position, we cannot but hold that the award was not based upon a proposition of law which is unsound or an error of law must have appeared from the award itself or from any document or note incorporated in the award or appended to it.
That apart, according to the Arbitrator, this figure was nothing but a mark up
which the parties agreed to keep in the contract for rendering of service
towards importation of plant components from Japanese supplies. The appellant
had realized this difference amount of Rs. 17 lacs from the respondent against
indigenous supplies. Therefore, it was not the case that the arbitrator had
misconducted himself in passing the award by ignoring to consider material
documents, which had thrown light on the controversy raised by the parties. As
noted herein earlier, the arbitrator had looked into the terms of the contract,
arbitration clause and the statement of claim of the respondent disputed by the
appellant. It was not the case that the arbitrator had decided erroneously a
question of law referred to him but on consideration of the terms of contract
and statement of claim came to a conclusion that Claim No. 9 of the respondent
should be awarded in its favour. Such being the position, we do not find any
reason to interfere with the award of the arbitrator which was passed on
consideration of all material put on record. In this view of the matter, it is
not open to the court to set aside the award on the ground that the learned
Arbitrator had, while continuing with the proceeding, acted beyond his
jurisdiction and violated the contract while awarding Rs. 17, 95, 710/- in the
form of Award No.9. In our view, this cannot be said to have an award,
which is contrary to the contract entered into by the parties. It is also not
the case where the learned Arbitrator had failed to consider material documents
produced by the parties for arriving at a right decision. On the other hand as
noted herein earlier, we are of the considered view that the Learned Arbitrator
had duly considered the statement of claim and the terms and conditions of the
contract and the material documents produced by the parties, which were
available on record, and came to a conclusion rightly in favour of the
respondent. The Learned Arbitrator also came to a conclusion that the aforesaid
figure of Rs. 17, 95, 710/-, was included as lump sum contract price as
consideration payable to the respondent for service rendered by them for
importation of plants and components. In any view of the matter, when the
Arbitrator had taken a plausible view on interpretation of contract, it is not
open to the court to set aside the award on the ground that the Arbitrator had
misconducted himself in the proceedings and therefore, the award was liable to
be set aside.
In Indu Engineering and Textile Limited vs. Delhi Development Authority Â
this court laid down a principal when the court could set aside an award in the
exercise of its powers under Section 30 of the Act. This court in the said
decision held that when a plausible view had been taken by the arbitrator and
unless the award of the arbitrator was vitiated by a manifest error on the face
of the award or was wholly improbable or perverse, it was not open to the court
to interfere with the award within the statutory interpretation set out in
Section 30 of the Act.
That apart, the amount of Rs.17, 95, 710/- was recovered by the appellant under
the bill issued against indigenous supplies and amount were paid without any
objection by the respondent. Such being the position we are unable to agree
with Mr. Sorabjee that the award was liable to be set-aside on the aforesaid
ground. We, therefore, do not find any merit in this appeal. The appeal is
dismissed without any order as to costs.