SUPREME COURT OF INDIA
Messrs Arvind Constructions Company Private Limited
Vs
Messrs Kalinga Mining Corporation and Others
(Tarun Chatterjee and P. K. Balasubramanyan, JJ)
17.05.2007
JUDGMENT
P. K. BALASUBRAMANYA, J.
1. Leave granted.
2. M/s Kalinga Mining Corporation, a partnership firm bearing registration No.
71/1949, came into existence on 10.12.1949. During the years from 1973 to 1980,
the firm obtained three mining leases from the State Government. The
partnership firm was reconstituted in the year 1980, taking in some additional
partners, again in the year 1991 and yet again in the year 1994.
3. On 14.3.1991, the firm entered into an agency agreement with the appellant,
a private limited company for a term of 10 years. Thereby, the appellant was
engaged as a raising contractor in respect of the mines for which the firm had
obtained leases from the State Government. On 25.3.1991, the firm executed an
irrevocable Power of Attorney in favour of the appellant authorizing it to
administer the mines and sell the iron ore extracted therefrom.
4. On 13.3.2001, the term of 10 years fixed in the agency agreement expired.
New terms were negotiated between the parties and on 22.9.2001, the agreement
was extended for a period of three years commencing from 14.3.2001. The term
was to end with 31.3.2003. Again, on 3.9.2003, the term of the agreement was
extended for a further period of three years commencing from 1.4.2003. Thereby,
the period was to end with 31.3.2006.
5. The appellant sought a further extension of the term of the agency
agreement. Apparently, the firm was not willing for an extension. Certain
disputes thus arose and by letter dated 19.11.2005, the appellant-company
sought resolution of the said disputes. The appellant- company followed this up
by a letter dated 9.12.2005 invoking the arbitration clause in the agency
agreement and nominating Mr. Sanjeev Jain as its arbitrator in terms of the
arbitration agreement.
6. It is seen that the respondent firm, for reasons best known to itself,
sought for and got a fresh registration on 24.12.2005 and a firm having the
same name was again registered and assigned registration No. 595/2005. Prima
facie, this was unwarranted and the excuse put forward was that the partners,
some of whom were partners even originally, could not trace the papers relating
to the registration of the firm in the year 1949. Be that as it may, on receipt
of the communication in that behalf from the appellant-company nominating an
arbitrator, the firm in its turn named an arbitrator. In terms of the
arbitration clause, the arbitrators had to name the Presiding Arbitrator. In
spite of lapse of time, the arbitrators did not meet and nominate a Presiding
Arbitrator. In that context, the appellant-company filed a petition under
Section 11(4)(b) of the Arbitration and Conciliation Act,
1996 (hereinafter referred to as, "the Act") requesting the
Chief Justice of the High Court of Orissa to appoint the third arbitrator on
the basis that the firm had failed to act in terms of the procedure agreed to
by the parties. The said application is said to be pending.
7. The appellant-company also moved an application under Section 9 of the Act
before the District Court, Cuttack seeking interim relief essentially to permit
it to continue to carry on the mining operations and to restrain the respondent
firm from interfering with it. According to the appellant, the agreement
between the parties was co-terminus with the subsistence of the mining lease
granted by the State in favour of the respondent firm and since the leases
continue to subsist, the appellant-company was entitled to an extension of the
period of the contract and what remained was only a negotiation regarding the
terms at which the agreement has to be worked by the appellant-company. The
appellant further pleaded that it had made all the investments for the purposes
of carrying on the mining operations and had brought in the requisite machinery
for that purpose. All the necessary investments had been made by it and in that
situation, the balance of convenience was in favour of the grant of an interim
order as sought for by the appellant. The respondent firm resisted the
application, inter alia, contending that the agreement between the parties was
essentially an agency agreement. Such an agreement could not be specifically
enforced. On the expiry of the term, the appellant- company had no subsisting
right or status to carry on mining and in that situation the injunction sought
for could not be granted. It was also contended that going by Section 14 and
Section 41 of the Specific Relief Act, 1963, such a
contract is unenforceable. Therefore the injunction prayed for could not be
granted.
8. The District Court, while entertaining the application had made an order on
8.3.2006 directing the parties to maintain the status quo. After hearing the
parties, the District Court took the view that it would be just and appropriate
to maintain the order of status quo until the disputes are referred to the
Arbitral Tribunal and the Tribunal takes seisin of the dispute. Thus, the order
of status quo originally granted was directed to continue until the Arbitral
Tribunal was constituted to take up the disputes between the parties. Feeling
aggrieved, the respondent firm --- there is a plea that the appeal was filed by
the firm of 2005 and not by the firm of 1949 which we shall deal with --- filed
an appeal before the High Court of Orissa. The High Court took the view that
the District Court was in error in granting an order to maintain the status quo
since prima facie the agreement between the parties was not a specifically
enforceable one in terms of the Specific Relief Act, 1963
and since the term of the agreement had expired it was not appropriate to grant
an interim order as granted by the District Court. Thus, the High Court
reversed the decision of the District Court and dismissed the application filed
by the appellant-company under Section 9 of the Act.
9. Feeling aggrieved by the said decision, the appellant-company has filed this
appeal. It is contended on its behalf that the appeal filed before the High
Court was not by the firm bearing registration No. 71/1949 with which the
appellant-company had the agreement. The arbitration clause, which the
appellant-company had invoked, was in relation to that agreement and hence the
appeal before the High Court, at the instance of the firm bearing registration
No. 595/2005, was not maintainable. It was further contended that since the
agreement relied upon by the appellant in the light of the irrevocable Power of
Attorney was co-terminus with the mining lease granted to the respondent firm
by the State Government, the same could not be terminated and would not come to
an end by efflux of time. The entire approach made by the High Court to find
otherwise was erroneous. It was further submitted that this was a case in which
the agreement could be specifically enforced in the light of Sections 10 and 42
of the Specific Relief Act, 1963. It was also
faintly suggested that the powers under Section 9 of the Act were independent
of any restrictions placed by the Specific Relief Act, 1963
and viewed in that manner, nothing stood in the way of the appellant-company
being granted an order of injunction or at least an order to maintain status
quo until the Arbitral Tribunal decided the dispute.
10. On behalf of the respondent firm, it was contended that it was only a case
of reconstitution of the 1949 firm. It was a mistake to have the firm
registered again in the year 2005 under a different registration number. Steps
have been taken to rectify the mistake in that regard. It was further submitted
that the appeal before the High Court was filed by the firm represented by its
partner, who was also a partner in the firm registered in the year 1949. The
appellant-company had impleaded in its application under Section 9 of the Act
all those who were presently partners of the firm and there was no grace in the
contention of the appellant-company that the appeal in the High Court was not
filed by the firm which was a party to the contract with the appellant. On
merits, it was submitted that the agreement was for a specific term, there was
no irrevocability in the agency agreement and an agreement like the one entered
into between the parties by way of a raising contract, could not be
specifically enforced as rightly held by the High Court. It was also pointed
out that the respondent firm had lost confidence in the appellant-company and
in such a situation, the appellant-company cannot claim to continue as an agent
of the respondent firm since the creation or continuation of an agency
arrangement depends on the confidence reposed by the principal on the agent. It
was also pointed out that subsequent to the expiry of the term, a tripartite
agreement had been entered into with a labour union and it contained a
recognition that the period of the contract between the respondent firm and the
appellant- company had come to an end. It could be seen therefrom that the
appellant-company had taken over, directly, the liability in respect of the
labourers who were being employed by the appellant-company during the
subsistence of the raising contract. It was also submitted that the respondent
firm had started mining operations on its own and the balance of convenience
was not in favour of grant of any interim order as was done by the District
Court. At best, the damages, if any, suffered by the appellant-company was
determinable in terms of money and this was a case in which no injunction to
perpetuate the agreement could be granted, especially as it involved
supervision of minute details which the court would not normally undertake. It
was also pointed out that grant of any injunction in favour of the
appellant-company would put the respondent firm in danger of being exposed to
prosecutions and other liabilities under law since it was the mining agency
under the State Government. It was therefore submitted that the
appellant-company had no prima facie case for an injunction as sought for.
11. The objection that the appeal filed before the High Court was not competent
need not detain us much. It was the appellant who filed the application under
Section 9 of the Act impleading the firm and its partners. The said firm
represented by a partner, who even admittedly was a partner of the firm as constituted
in the year 1949 and was also a party to the agreement with the
appellant-company itself, had filed the appeal before the High Court. There is
no case that the firm registered in the year 1949 had been dissolved. On the
other hand, we find that it was being reconstituted from time to time.
Therefore, the fact that, foolishly or otherwise, a firm in the same name was
again registered in the year 2005, does not affect the status of the firm with
which the appellant-company had a contract and the filing of the appeal by that
firm represented by its partner. It was brought to our notice that the
respondent firm had sought a rectification of the register realizing the
mistake that was made in having the same firm registered all over again, and
that the said matter is pending. Considering the circumstances, we are of the
view that the argument that the appeal before the High Court was not competent,
it not having been filed by the firm with which the appellant- company had the
contract, is unsustainable. The said contention is therefore overruled.
12. The effect of the agreement dated 14.3.1991 and the Power of Attorney dated
25.3.1991 admittedly executed between the parties and the rights and
obligations flowing therefrom are really matters for decision by the Arbitral
Tribunal. We do not think that it is for us, at this interlocutory stage, to
consider or decide the validity of the argument raised on behalf of the
appellant-company that the agreement between the parties was co-terminus with
the mining leases and the respondent firm could not terminate the agreement so
long as the mining leases in its favour continued to be in force. Nor do we
think it proper to decide the sustainability of the argument on behalf of the
respondent firm that it was mainly an agency agreement for a fixed term and on
the expiry of the term, no right survives in the appellant-company unless of
course the respondent firm agreed to an extension of the period. We leave that
question open for decision by the Arbitral Tribunal.
13. Prima facie, it is seen that the mining lessee had entered into an
agreement with the appellant-company for the purpose of raising the iron ore
from the area covered by the mining lease. The term of the original agreement
expired and this was followed by two extensions for three years each.
Thereafter, the respondent firm had refused to extend the agreement and claims
that it wants to do the mining itself. Prima facie, it is not possible to say
that the High Court was wrong in thinking that it may be a case where an
injunction could not be granted in view of the provisions of the Specific Relief Act, 1963. Here again, we do not think
that we should pronounce on that question since that again will be a question
for the arbitrator to pronounce upon. Suffice it to say that the position is
not clear enough for us to assume for the purpose of this interlocutory
proceeding that the appellant is entitled to specifically enforce the agreement
dated 14.3.1991 read in the light of the Power of Attorney dated 25.3.1991. Of
course, this aspect will be again subject to the contention raised by the
appellant-company that the agreement created in his favour was co-terminus with
the mining lease itself. But, as we have stated, these are the aspects to be
considered by the Arbitral Tribunal. We refrain from pronouncing on them at
this stage.
14. We think that adequate grounds are not made out by the appellant at this
interlocutory stage for interfering with the order of the High Court. In that
view alone, we consider it proper to decline to interfere with the order of the
High Court and leave the parties to have their disputes resolved in terms of
the arbitration agreement between the parties.
15. The argument that the power under Section 9 of the Act is independent of
the Specific Relief Act, 1963 or that the
restrictions placed by the Specific Relief Act, 1963
cannot control the exercise of power under Section 9 of the Act cannot prima
facie be accepted. The reliance placed on Firm Ashok Traders & Anr. Vs.
Gurumukh Das Saluja & Ors. Â in that behalf does not also help much,
since this Court in that case did not answer that question finally but prima
facie felt that the objection based on Section 69 (3) of the Partnership Act
may not stand in the way of a party to an arbitration agreement moving the
court under Section 9 of the Act. The power under Section 9 is conferred on the
District Court. No special procedure is prescribed by the Act in that behalf.
It is also clarified that the Court entertaining an application under Section 9
of the Act shall have the same power for making orders as it has for the
purpose and in relation to any proceedings before it. Prima facie, it appears
that the general rules that governed the court while considering the grant of
an interim injunction at the threshold are attracted even while dealing with an
application under Section 9 of the Act. There is also the principle that when a
power is conferred under a special statute and it is conferred on an ordinary
court of the land, without laying down any special condition for exercise of
that power, the general rules of procedure of that court would apply. The Act
does not prima facie purport to keep out the provisions of the Specific Relief Act, 1963 from consideration. No doubt, a
view that exercise of power under Section 9 of the Act is not controlled by the
Specific Relief Act, 1963 has been taken by the
Madhya Pradesh High Court. The power under Section 9 of the Act is not
controlled by Order XVIII Rule 5 of the Code Of Civil
Procedure, 1908 is a view taken by the High Court of Bombay. But, how
far these decisions are correct, requires to be considered in an appropriate
case. Suffice it to say that on the basis of the submissions made in this case,
we are not inclined to answer that question finally. But, we may indicate that
we are prima facie inclined to the view that exercise of power under Section 9
of the Act must be based on well recognized principles governing the grant of
interim injunctions and other orders of interim protection or the appointment
of a receiver.
16. It Is Seen That In Spite Of The Parties Naming Their Respective
Arbitrators, In Terms Of The Arbitration Agreement, More Than One Year Back,
The Arbitrators So Appointed Had Not Been Able To Nominate A Presiding Arbitrator
In Terms Of The Arbitration Agreement. We Therefore Put It To Counsel On Both
Sides As To Why We Shall Not Constitute An Arbitral Tribunal In View Of Their
Failure To Constitute The Arbitral Tribunal In Terms Of The Arbitration
Agreement and In View Of The Urgency Involved In Resolving The Disputes Between
The Parties. Counsel On Both Sides Agreed That This Court May Appoint Either A
Presiding Arbitrator Or A Sole Arbitrator For The Purpose Of Resolving The
Disputes Between The Parties. A Panel Of Names Was Furnished. Having Considered
The Names Shown Therein and Taking Note Of The Submissions At The Bar, We Think
That It Would Be Appropriate and Just To Both The Parties To Appoint Mr.
Justice Y.K. Sabharwal, Former Chief Justice Of India As The Sole Arbitrator
For Deciding All The Disputes Between The Parties. We Therefore Appoint Mr.
Justice Y.K. Sabharwal former Chief Justice of India as the sole arbitrator to
decide on the disputes between the parties springing out the agreement dated
14.3.1991 and the Power of Attorney dated 25.3.1991. The arbitrator would be
free to fix his terms in consultation with the parties. We would request the
arbitrator to expeditiously decide the dispute on entering upon the reference
and to give his award as early as possible.
17. In the result, we decline to interfere with the order of the High Court and
dismiss this appeal. While doing so, we revoke the nomination made by the
parties of two arbitrators. We appoint Mr. Justice Y.K. Sabharwal, former Chief
Justice of India as the sole arbitrator to decide the dispute between the
parties. The parties are directed to suffer their respective costs.