SUPREME COURT OF INDIA
Adhunik Steels Limited
Vs
Orissa Manganese and Minerals Private Limited
(H. K. Sema and P. K. Balasubramanyan)
10.07.2007
JUDGMENT
P. K. BALASUBRAMANYAN, J.
1. These Cross Appeals by Special Leave challenge the order passed by the High Court of Orissa in an appeal under Section 37(1)(a) of the Arbitration and Conciliation Act, 1996. The said appeal was one filed by the respondent in C.A. No. 6569 of 2005 which is the appellant in C.A. No. 6570 of 2005 challenging an order of the District Court at Sundargarh in a petition under Section 9 of the Act filed by the appellant in C.A. No. 6569 of 2005 and the respondent in C.A. No. 6570 of 2005. For convenience, the parties will hereinafter be referred to as "Adhunik Steels" and "O.M.M. Private Limited". Adhunik Steels it was, that filed the application under Section 9 of the Act.
2. O.M.M. Private Limited obtained a mining lease from the Government of Orissa
for mining manganese ore from certain extents of land situate in Sundargarh
district in the State of Orissa. For reasons of its own, O.M.M. Private Limited
entered into an agreement dated 14.5.2003 with Adhunik Steels for raising the
manganese ore on its behalf. The term of the agreement was 10 years with effect
from 18.5.2003, it conferred on Adhunik Steels an option to seek a renewal for
a further term.
3. According to Adhunik Steels, pursuant to this agreement, it had mobilized
huge resources for carrying on the excavation and extraction of the mineral by
arranging for the necessary labour, staff, equipments, and so on. It had also
incurred expenditure for removing the overburden. On 24.11.2003, O.M.M. Private
Limited issued a notice to Adhunik Steels purporting to terminate the
agreement. The notice also called upon Adhunik Steels to remove their workmen
and equipment from the site. According to O.M.M. Private Limited, it had
realized that the contract it had entered into with Adhunik Steels was one in
violation of Rule 37 of the Mineral Concession Rules, 1960 and since there was
danger of O.M.M. Private Limited itself losing its rights as a lessee, the
contract had to be terminated. Adhunik Steels, alleging that it had incurred
considerable expenditure and had already incurred losses, moved the District
Court at Sundargarh under Section 9 of the Act for an injunction restraining
O.M.M. Private Limited from terminating the contract and from dispossessing
Adhunik Steels from the site of the mines and for other consequential reliefs.
The said application was opposed by O.M.M. Private Limited on various grounds.
Ultimately, by order dated 18.8.2004, the District Court allowed the
application and restrained O.M.M. Private Limited from relying on, acting upon
or giving effect to the letter of termination dated 24.11.2003 and further
restraining O.M.M. Private Limited from dispossessing Adhunik Steels from the
mines in question. The order was to remain in force till the final award that
was to be passed by an Arbitral Tribunal constituted in terms of the arbitration
agreement.
4. We may notice here that prior to approaching the District Court at
Sundargarh, Adhunik Steels had moved the Calcutta High Court under Section 9 of
the Act seeking identical reliefs. O.M.M. Private Limited had raised an
objection to jurisdiction in the Calcutta High Court and the said objection was
upheld by the Calcutta High Court and that had led to Adhunik Steels
approaching the District Court at Sundargarh. We may also notice that it is
contended that Adhunik Steels had thereafter moved the Chief Justice of the
High Court of Orissa under Section 11(6) of the Act for appointment of an
Arbitrator in terms of the arbitration agreement. The application is said to be
pending.
5. The District Court, Sundargarh held that Rule 37 of the Mineral Concession Rules, 1960 cannot be held to be applicable to the working arrangement between the parties which has been termed a raising contract. It further held that the balance of convenience was in favour of the grant of an injunction against O.M.M. Private Limited as sought for by Adhunik Steels, and that if an order of injunction was not granted, the very purpose of initiating the arbitration proceeding would be defeated. Following the decision of the Madhya Pradesh High Court in Nepa Limited Vs. Manoj Kumar Agrawal  1998 Indlaw MP 3, it accepted the principle that there was a distinction between Section 9 and Section 11 of the Act and that the powers under Section 9 are wide and what is relevant to be considered at the stage of a motion under Section 9 of the Act was the existence of an arbitration clause and the necessity of taking interim measures and the court could issue any direction that is deemed appropriate. Rejecting the contention of O.M.M. Private Limited that Adhunik Steels had been dispossessed subsequent to the letter terminating the contract, the court held that in its opinion it would be equitable to grant the orders sought for under Section 9 of the Act. It also stated that an order of injunction would be necessary to preserve the mines in dispute so that the arbitrators at a later point of time can have an effective and proper adjudication of the dispute referred to them. It was thus that the order of injunction was granted.
6. Aggrieved by the order of the District Court, Sundargarh, O.M.M. Private
Limited filed an appeal before the High Court of Orissa. It was argued on
behalf of O.M.M. Private Limited that the contract between the parties was in
violation of Rule 37 of the Mineral Concession Rules, 1960 and hence the agreement
itself was illegal and no right could be founded on such an illegal agreement
by Adhunik Steels. It was alternatively contended that in terms of Section 41
of the Specific Relief Act, no injunction can be granted for continuance of the
contract and the working of the contract involved intrinsic details in its
performance extended over a period of 10 years and the court would not be in a
position to supervise the working of the contract and in such a situation, an
interim injunction ought not to be granted. It was also contended that in terms
of Section 14 of the Specific Relief Act, the agreement was not specifically
enforceable as it was terminable and in any event, since Adhunik Steels could
be compensated in terms of money, even if its claim was ultimately Appeal
(Civil) 6569 of 2005 (C.A. No. 6570 of 2005)
(Upheld, It Was Not A Case For Grant Of An Interim Injunction In Terms Of Section 14(3) Of The Specific Relief Act. The Learned Judge Of The High Court Came To The Prima Facie Conclusion That Rule 37 Of The Mineral Concession Rules, 1960 Had No Application To The Facts Of The Case. The Learned Judge Also Held That In View Of Clause 8.2 Of The Agreement, Section 14(1)(C) Of The Specific Relief Act Was Not Attracted. But The Learned Judge Upheld The Contention On Behalf Of O.M.M. Private Limited That The Loss, If Any, That May Be Sustained By Adhunik Steels, Could Be Calculated In Terms Of Money and In View Of That and In The Light Of Section 14(3)(C) Of The Specific Relief Act, An Injunction As Prayed For By Adhunik Steels Could Not Be Granted. The Court Did Not Go Into The Question Of Balance Of Convenience In Granting An Order Of Injunction In The Light Of Its Conclusion That This Is Not A Fit Case For Grant Of An Interim Injunction., JJ)
7. Thus, the High Court allowed the appeal filed by O.M.M. Private Limited and
set aside the order of injunction passed by the District Court, Sundargarh.
Feeling aggrieved thereby, Adhunik Steels has filed its appeal. Feeling
aggrieved by the finding that Rule 37 of Mineral Concession Rules, 1960 does
not hit the contract in question and the finding that Section 14(1)(c) of the
Specific Relief Act did not stand in the way of injunction being granted,
O.M.M. Private Limited has come up with its appeal.
8. There was considerable debate before us on the scope of Section 9 of the
Act. According to learned counsel for Adhunik Steels, Section 9 of the Act
stood independent of Section 94 and Order XXXIX of the Code
Of Civil Procedure, 1908 and the exercise of power thereunder was also
not trammeled by anything contained in the Specific Relief Act. Learned counsel
contended that by way of an interim measure, the court could pass an order for
the preservation or custody of the subject matter of the arbitration agreement
irrespective of whether the order that may be passed was in a mandatory form or
was in a prohibitory form. The subject matter of arbitration in the present
case was the continued right of Adhunik Steels to mine and lift the ore to the
surface on behalf of O.M.M. Private Limited and until the arbitrator decided on
whether O.M.M. Private Limited was entitled to breach the agreement or
terminate the agreement and what would be its consequences, the court had not
only the power but the duty to protect the right of Adhunik Steels conferred by
the contract when approached under Section 9 of the Act. Learned counsel
emphasized that what was liable to be protected in an appropriate case was the
subject matter of the arbitration agreement. Learned counsel referred to 'The
Law and Practice of Commercial Arbitration in England' by Mustill and Boyd and
relied on the following passage therefrom:
"(b) Safeguarding the subject matter of the dispute:
The existence of a dispute may put at risk the property which forms the subject
of the reference, or the rights of a party in respect of that property. Thus,
the dispute may prevent perishable goods from being put to their intended use,
or may impede the proper exploitation of a profit-earning article, such as a
ship. If the disposition of the property has to wait until after the award has
resolved the dispute, unnecessary hardship may be caused to the parties. Again,
there may be a risk that if the property is left in the custody or control of
one of the parties, pending the hearing, he may abuse his position in such a
way that even if the other party ultimately succeeds in the arbitration, he
will not obtain the full benefit of the award. In cases such as this, the Court
(and in some instances the arbitrator) has power to intervene, for the purpose
of maintaining the status quo until the award is made. The remedies available
under the Act are as follows:-
(i) The grant of an interlocutory injunction.
(ii) The appointment of a receiver
(iii) The making of an order for the preservation, custody or sale of the
property.
(iv) The securing of the amount in dispute."
Learned counsel also relied on 'International Commercial Arbitration in
UNCITRAL Model Law Jurisdictions' by Dr. Peter Binder, wherein it is stated:
"It is not incompatible with an arbitration agreement for a party to
request, before or during arbitral proceedings, from a court an interim measure
of protection and for a court to grant such measure."
It is further stated:
"In certain circumstances, especially where the arbitral tribunal has
not yet been established, the issuance of interim measures by the court is the
only way assets can be saved for a future arbitration. Otherwise, the claimant
could end up with a worthless arbitral award due to the fact that the losing
party has moved his attachable assets to a "safe" jurisdiction where
they are out of reach of the claimant's seizure. The importance of such a
provision in an arbitration law is therefore evident, and a comparison of the
adopting jurisdictions shows that all jurisdictions include some kind of
provision on the issue, all granting the parties permission to seek
court-ordered interim measures."
9. Learned counsel for O.M.M. Private Limited submitted that Section 9 leaves
it to a party to approach the court for certain interim measures and it enables
the court to pass orders by way of interim measures of protection in respect of
the matters enumerated therein. Neither this Section nor the Act elsewhere has
provided the conditions for grant of such interim protection leaving it to the
court to exercise the jurisdiction vested in it as a court to adjudge whether
any protective measure is called for. In that context, neither the provisions
of the Code of Civil Procedure nor the provisions of the Specific Relief Act
can be kept out while the court considers the question whether on the facts of
a case, any order by way of interim measure of protection should be granted.
So, the court had necessarily to consider the balance of convenience, the
question whether at least a triable issue arises if not the establishment of a
prima facie case by the applicant before it and the other well known
restrictions on the grant of interim orders, like the principle that a contract
of personal service would not be specifically enforced or that no injunction
would be granted in certain circumstances as envisaged by Section 14 and
Section 41 of the Specific Relief Act. Thus, it was contended that grant of an
injunction by way of interim measure to permit Adhunik Steels to carry on the
mining operations pending the arbitration proceedings notwithstanding the
termination of the contract by O.M.M. Private Limited was not permissible in
law.
10. It is true that Section 9 of the Act speaks of the court by way of an
interim measure passing an order for protection, for the preservation, interim
custody or sale of any goods, which are the subject matter of the arbitration
agreement and such interim measure of protection as may appear to the court to
be just and convenient. The grant of an interim prohibitory injunction or an
interim mandatory injunction are governed by well known rules and it is
difficult to imagine that the legislature while enacting Section 9 of the Act
intended to make a provision which was de hors the accepted principles that
governed the grant of an interim injunction. Same is the position regarding the
appointment of a receiver since the Section itself brings in, the concept of
'just and convenient' while speaking of passing any interim measure of
protection. The concluding words of the Section, "and the court shall have
the same power for making orders as it has for the purpose and in relation to
any proceedings before it" also suggest that the normal rules that govern
the court in the grant of interim orders is not sought to be jettisoned by the
provision. Moreover, when a party is given a right to approach an ordinary
court of the country without providing a special procedure or a special set of
rules in that behalf, the ordinary rules followed by that court would govern
the exercise of power conferred by the Act. On that basis also, it is not
possible to keep out the concept of balance of convenience, prima facie case,
irreparable injury and the concept of just and convenient while passing interim
measures under Section 9 of the Act.
11. The power and jurisdiction of courts in arbitral matters has been the
subject of much discussion. The relationship between courts and arbitral
tribunals have been said to swing between forced co-habitation and true
partnership. The process of arbitration is dependant on the underlying support
of the courts who alone has the power to rescue the system when one party seeks
to sabotage it. The position was stated by Lord Mustil in Coppee Levalin NV vs.
Ken-Ren Fertilisers and Chemicalsb (1994 (2) Lloyd's Report 109 at 116):
"There is plainly a tension here. On the one hand the concept of
arbitration as a consensual process reinforced by the ideas of transnationalism
leans against the involvement of the mechanisms of state through the medium of
a municipal court. On the other side there is a plain fact, palatable or not,
that it is only a Court possessing coercive powers which could rescue the
arbitration if it is in danger of foundering."
In Conservatory and Provisional Measures in International Arbitration, 9th
Joint Colloquium, Lord Mustill in "Comments and Conclusions"
described the relationship further:
"Ideally, the handling of arbitral disputes should resemble a relay
race. In the initial stages, before the arbitrators are seized of the dispute,
the baton is in the grasp of the court; for at that stage there is no other
organization which could take steps to prevent the arbitration agreement from
being ineffectual. When the arbitrators take charge they take over the baton
and retain it until they have made an award. At this point, having no longer a
function to fulfil, the arbitrators hand back the baton so that the court can
in case of need lend its coercive powers to the enforcement of the award."
It is in the above background that one has to consider the power of the court
approached under the Arbitration Act for interim relief or interim protection.
12.Professor Lew in his 'Commentary on Interim and Conservatory Measures in ICC
Arbitration Cases', has indicated:
"The demonstration of irreparable or perhaps substantial harm is also
necessary for the grant of a measure. This is because it is not appropriate to
grant a measure where no irreparable or substantial harm comes to the movant in
the event the measure is not granted. The final award offers the means of
remedying any harm, reparable or otherwise, once determined."
The question was considered in Channel Tunnel Group Ltd. and another vs.
Balfour Beatty Construction Ltd. Â 1993 AC 334. The trial judge in that
case took the view that he had the power to grant an interim mandatory
injunction directing the continuance of the working of the contract pending the
arbitration. The Court of Appeal thought that it was an appropriate case for an
injunction but that it had no power to grant injunction because of the
arbitration. In further appeal, the House of Lords held that it did have the
power to grant injunction but on facts thought it inappropriate to grant one.
In formulating its view, the House of Lords highlighted the problem to which an
application for interim relief like the one made in that case may give rise.
The House of Lords stated at page 367:
"It is true that mandatory interlocutory relief may be granted even
where it substantially overlaps the final relief claimed in the action; and I
also accept that it is possible for the court at the pre-trial stage of the
dispute arising under a construction contract to order the defendant to
continue with a performance of the works. But the court should approach the
making of such an order with the utmost caution and should be prepared to act
only when the balance of advantage plainly favours the grant of relief. In the
combination of circumstances which we find in the present case, I would have
hesitated long before proposing that such an order should be made, even if the
action had been destined to remain in the High Court."
13. Injunction is a form of specific relief. It is an order of a court
requiring a party either to do a specific act or acts or to refrain from doing
a specific act or acts either for a limited period or without limit of time. In
relation to a breach of contract, the proper remedy against a defendant who
acts in breach of his obligations under a contract, is either damages or
specific relief. The two principal varieties of specific relief are, decree of
specific performance and the injunction (See David Bean on Injunctions). The Specific Relief Act, 1963 was intended to be "An Act
to define and amend the law relating to certain kinds of specific
reliefs." Specific Relief is relief in specie. It is a remedy which aims
at the exact fulfilment of an obligation. According to Dr. Banerjee in his
Tagor Law Lectures on Specific Relief, the remedy for the non performance of a
duty are (1) compensatory, (2) specific. In the former, the court awards
damages for breach of the obligation. In the latter, it directs the party in
default to do or forbear from doing the very thing, which he is bound to do or
forbear from doing. The law of specific relief is said to be, in its essence, a
part of the law of procedure, for, specific relief is a form of judicial
redress. Thus, the Specific Relief Act, 1963
purports to define and amend the law relating to certain kinds of specific
reliefs obtainable in civil courts. It does not deal with the remedies
connected with compensatory reliefs except as incidental and to a limited
extent. The right to relief of injunctions is contained in part-III of the
Specific Relief Act. Section 36 provides that preventive relief may be granted
at the discretion of the court by injunction temporary or perpetual. Section 38
indicates when perpetual injunctions are granted and Section 39 indicates when
mandatory injunctions are granted. Section 40 provides that damages may be
awarded either in lieu of or in addition to injunctions. Section 41 provides
for contingencies when an injunction cannot be granted. Section 42 enables,
notwithstanding anything contained in Section 41, particularly clause (e)
providing that no injunction can be granted to prevent the breach of a contract
the performance of which would not be specifically enforced, the granting of an
injunction to perform a negative covenant. Thus, the power to grant injunctions
by way of specific relief is covered by the Specific Relief
Act, 1963.
14.In Nepa Limited Vs. Manoj Kumar Agrawal  1998
Indlaw MP 3, a learned judge of the Madhya Pradesh High Court has
suggested that when moved under Section 9 of the Act for interim protection,
the provisions of the Specific Relief Act cannot be made applicable since in
taking interim measures under Section 9 of the Act, the court does not decide
on the merits of the case or the rights of parties and considers only the
question of existence of an arbitration clause and the necessity of taking
interim measures for issuing necessary directions or orders. When the grant of
relief by way of injunction is, in general, governed by the Specific Relief
Act, and Section 9 of the Act provides for an approach to the court for an
interim injunction, we wonder how the relevant provisions of the Specific
Relief Act can be kept out of consideration. For, the grant of that interim
injunction has necessarily to be based on the principles governing its grant
emanating out of the relevant provisions of the Specific Relief Act and the law
bearing on the subject. Under Section 28 of the Act of 1996, even the arbitral
tribunal is enjoined to decide the dispute submitted to it, in accordance with
the substantive law for the time being in force in India, if it is not an
international commercial arbitration. So, it cannot certainly be inferred that
Section 9 keeps out the substantive law relating to interim reliefs.
15. The approach that at the initial stage, only the existence of an arbitration
clause need be considered is not justified. In The Siskina  1977 Indlaw CA 30, Lord Diplock explained the position:
"A right to obtain an interlocutory injunction is not a cause of
action. It cannot stand on its own. It is dependent upon there being a
pre-existing cause of action against the defendant arising out of an invasion,
actual or threatened by him, of a legal or equitable right of the plaintiff for
the enforcement of which the defendant is amenable to the jurisdiction of the
court. The right to obtain an interlocutory injunction is merely ancillary and
incidental to the pre-existing cause of action. It is granted to preserve the
status quo pending the ascertainment by the court of the rights of the parties
and the grant to the plaintiff of the relief to which his cause of action
entitles him, which may or may not include a final injunction."
He concluded:
"To come within the sub-rule the injunction sought in the action must
be part of the substantive relief to which the plaintiff's cause of action
entitles him; and the thing that it is sought to restrain the foreign defendant
from doing in England must amount to an invasion of some legal or equitable
right belonging to the plaintiff in this country and enforceable here by a
final judgment for an injunction."
16.Recently, in Fourie Vs. Le Roux  2007 (1) WLR 320, the House of Lords
speaking through Lord Scott of Foscote stated:
"An interlocutory injunction, like any other interim order, is intended
to be of temporary duration, dependent on the institution and progress of some
proceedings for substantive relief." and concluded:
"Whenever an interlocutory injunction is applied for, the judge, if
otherwise minded to make the order, should, as a matter of good practice, pay
careful attention to the substantive relief that is, or will be, sought. The
interlocutory injunction in aid of the substantive relief should not place a
greater burden on the respondent than is necessary. The yardstick in section
37(1) of the 1981 Act, "just and convenient", must be applied having
regard to the interests not only of the claimant but also of the
defendant."
17. No special condition is contained in Section 9 of the Act. No special
procedure is indicated. In American Jurisprudence, 2nd Edition it is stated:
"In judicial proceedings under arbitration statutes ordinary rules of
practice and procedure govern where none are specified; and even those
prescribed by statute are frequently analogous to others in common use and are
subject to similar interpretation by the courts."
18. It is true that the intention behind Section 9 of the Act is the issuance
of an order for preservation of the subject matter of an arbitration agreement.
According to learned counsel for Adhunik Steels, the subject matter of the
arbitration agreement in the case on hand, is the mining and lifting of ore by
it from the mines leased to O.M.M. Private Limited for a period of 10 years and
its attempted abrupt termination by O.M.M. Private Limited and the dispute
before the arbitrator would be the effect of the agreement and the right of
O.M.M. Private Limited to terminate it prematurely in the circumstances of the
case. So viewed, it was open to the court to pass an order by way of an interim
measure of protection that the existing arrangement under the contract should
be continued pending the resolution of the dispute by the arbitrator. May be,
there is some force in this submission made on behalf of the Adhunik Steels.
But, at the same time, whether an interim measure permitting Adhunik Steels to
carry on the mining operations, an extraordinary measure in itself in the face
of the attempted termination of the contract by O.M.M. Private Limited or the
termination of the contract by O.M.M. Private Limited, could be granted or not,
would again lead the court to a consideration of the classical rules for the
grant of such an interim measure. Whether an interim mandatory injunction could
be granted directing the continuance of the working of the contract, had to be
considered in the light of the well-settled principles in that behalf.
Similarly, whether the attempted termination could be restrained leaving the
consequences thereof vague would also be a question that might have to be
considered in the context of well settled principles for the grant of an
injunction. Therefore, on the whole, we feel that it would not be correct to
say that the power under Section 9 of the Act is totally independent of the
well known principles governing the grant of an interim injunction that
generally govern the courts in this connection. So viewed, we have necessarily
to see whether the High Court was justified in refusing the interim injunction
on the facts and in the circumstances of the case.
19. No doubt, there is considerable dispute as to whether Rule 37 of the
Mineral Concession Rules, 1960 has application. The District Court and the High
Court have prima facie come to the conclusion that the said Rule has no
application. Whether the said Rule has application, is one of the aspects to be
considered by the arbitrator or the Arbitral Tribunal that may be constituted
in terms of the arbitration agreement between the parties. We do not think that
it is proper for us at this stage to pronounce on the applicability or
otherwise of Rule 37 of the Mineral Concession Rules, 1960 and its impact on
the agreement entered into between the parties. We therefore leave open that
question for being decided by the arbitrator. The attempt made by O.M.M. Private
Limited to rely upon some other arbitral award in support of its claim that
Rule 37 of the Mineral Concession Rules, 1960 would apply, is neither here nor
there. We are concerned with what the arbitrator who may be appointed will hold
in the present case and not what some other arbitrator held in some other
arbitration and some other contract even if it be between the same parties.
Moreover, in our adjudication, we cannot be bound by what an arbitrator might
have held in an arbitration proceeding unless it be that the said award
operates as a bar between the parties barring either of them from raising a
plea in that behalf.
20. The question here is whether in the circumstances, an order of injunction
could be granted restraining O.M.M. Private Limited from interfering with
Adhunik Steels' working of the contract which O.M.M. Private Limited has sought
to terminate. Whatever might be its reasons for termination, it is clear that a
notice had been issued by the O.M.M. Private Limited terminating the arrangement
entered into between itself and Adhunik Steels. In terms of Order XXXIX Rule 2
of the Code of Civil Procedure, an interim injunction could be granted
restraining the breach of a contract and to that extent Adhunik Steels may
claim that it has a prima facie case for restraining O.M.M. Private Limited
from breaching the contract and from preventing it from carrying on its work in
terms of the contract. It is in that context that the High Court has held that
this was not a case where the damages that may be suffered by Adhunik Steels by
the alleged breach of contract by O.M.M. Private Limited could not be
quantified at a future point of time in terms of money. There is only a
mention of the minimum quantity of ore that Adhunik Steels is to lift and there
is also uncertainty about the other minerals that may be available for being
lifted on the mining operations being carried on. These are impoundables to
some extent but at the same time it cannot be said that at the end of it, it
will not be possible to assess the compensation that might be payable to
Adhunik Steels in case the claim of Adhunik Steels is upheld by the arbitrator
while passing the award.
21. But, in that context, we cannot brush aside the contention of the learned
counsel for Adhunik Steels that if O.M.M. Private Limited is permitted to enter
into other agreements with others for the same purpose, it would be unjust when
the stand of O.M.M. Private Limited is that it was canceling the agreement
mainly because it was hit by Rule 37 of the Mineral Concession Rules, 1960.
Going by the stand adopted by O.M.M. Private Limited, it is clear that O.M.M.
Private Limited cannot enter into a similar transaction with any other entity
since that would also entail the apprehended violation of Rule 37 of the Mineral
Concession Rules, 1960, as put forward by it. It therefore appears to be just
and proper to direct O.M.M. Private Limited not to enter into a contract for
mining and lifting of minerals with any other entity until the conclusion of
the arbitral proceedings.
22. At the same time, we see no justification in preventing O.M.M. Private
Limited from carrying on the mining operations by itself. It has got a mining
lease and subject to any award that may be passed by the arbitrator on the
effect of the contract it had entered into with Adhunik Steels, it has the
right to mine and lift the minerals therefrom. The carrying on of that activity
by O.M.M. Private Limited cannot prejudice Adhunik Steels, since ultimately
Adhunik Steels, if it succeeds, would be entitled to get, if not the main
relief, compensation for the termination of the contract on the principles well
settled in that behalf. Therefore, it is not possible to accede to the
contention of learned counsel for Adhunik Steels that in any event O.M.M.
Private Limited must be restrained from carrying on any mining operation in the
mines concerned pending the arbitral proceedings.
23. We think that we should refrain from discussing the various issues at great
length since we feel that any discussion by us in that behalf could prejudice
either of the parties before the arbitrator or the arbitral tribunal. We have
therefore confined ourselves to making such general observations as are
necessary in the context of the elaborate arguments raised before us by learned
counsel.
24. We therefore dismiss the appeal filed by O.M.M. Private Limited leaving
open the questions raised by it for being decided by the arbitrator or Arbitral
Tribunal in accordance with law. We also substantially dismiss the appeal filed
by Adhunik Steels except to the extent of granting it an order of injunction
restraining O.M.M. Private Limited from entering into a transaction for mining
and lifting of the ore with any other individual or concern making it clear
that it can, on its own, carry on the mining operations in terms of the mining
lease.
25. We think that the arbitration proceedings must be expedited. We are told
that the application for appointment of an arbitrator made before the Chief
Justice of the Orissa High Court under Section 11(6) of the Act is pending for
over two years without orders. Normally, we would have requested the Chief
Justice of the Orissa High Court or his nominee to take up and dispose of the
application under Section 11(6) of the Act expeditiously. But we put it to the
parties that it would be more expedient if we appoint an arbitrator in this
proceeding itself, so that further delay can be avoided. The parties have
agreed to that course. We therefore think that it would be in the interests of
justice if we appoint here and now a sole arbitrator to adjudicate on the
dispute between the parties. Hence we appoint Mr. Justice R.C. Lahoti, former
Chief Justice of India as the sole arbitrator to decide the dispute between the
parties. The arbitrator will be free to fix his terms in consultation with the
parties. We confidently expect the sole arbitrator to enter upon the reference
and pronounce his award expeditiously.
26. The appeals are disposed of as above. We make no order as to costs. J