SUPREME COURT OF INDIA
Mahatma Gandhi Sahakra Sakkare Karkhane
Vs
National Heavy Engineering Co-Operative Limited and Another
(Tarun Chatterjee and B. S. Reddy, JJ)
11.07.2007
JUDGMENT
B. SUDERSHAN REDDY, J.
Leave granted.
The appellant herein is a Co-operative Society registered under the provisions
of the Karnataka Co-operative Societies Act, 1959. It has established a sugar
factory at Hunji, Balki Taluk, Bidar District, and Karnataka with a capacity of
2500 TCD per day with a provision to expand the same upto 4000 TCD per day. The
appellant had undertaken expansion of its sugar factory from 2500 TCD to 4000
TCD crushing capacity per day and accordingly invited tenders. The offer of the
first respondent which is also a Co-operative Society registered under the Multi-State Co-Operative Societies Act, 1984 which is
involved in supply, erection and commissioning of Sugar Plants was accepted in
the meeting of the State Level Advisory Committee held on 10th August, 2000.
The first respondent undertook to design, procure manufacture, supply transport
and deliver at the site and to do the supervision of erection and commissioning
of the Sugar Plant and Machinery in conformity with the agreed specifications
vides agreement dated 1st November, 2000. The clauses of the agreement dated
1st November, 2000 which are relevant to be noticed are reproduced as under:
"Clause 5: Supply, Delivery and Supervision of Erection and
Commissioning.
Clause 5.1 : The Seller agrees to supply plant and machinery so that the supply
and erection of the plant and machinery is completed in all respects and to the
satisfaction of the Purchaser and the Sugar Plant and Machinery is Commissioned
and made ready for commercial production and use by 11th December, 2001.
8.0 TRIALS AND TAKE OVER :
8.1 As soon as the Plant is ready for commissioning after completion of the
supply of plant and machinery and erection of the same to the satisfaction of
the purchasers, the sellers on getting information from the erection contractor
shall notify in writing to the purchasers specifying the date and time, at
least 30 days before the sellers intend to carry out steam and water trials to
enable the purchasers to arrange for boiler feed water, fuel, operational staff
and workmen and other facilities. Unless otherwise agreed by the purchasers and
the sellers, the sellers shall begin the said trial on the date and time so
notified.
Provided that the water, steam and vacuum trials shall be conducted by the
sellers for a period of one month before the commissioning of the plant and
machinery after complete delivery and erection to the entire satisfaction of
the purchasers.
8.2 After the said steam, water and vacuum trials have been completed to the
entire satisfaction of the purchasers and on their furnishing a certificate to
the effect that all the plant and machinery mentioned in Annexure I to III have
been inspected and approved by the Inspection Agency, delivered as per detailed
parts list of materials referred to above, erected and commissioned under the
supervision of the sellers according to the terms and conditions of this
agreement, the sellers guarantees given in pursuance of clause 17.2 shall be
deemed to have been fulfilled."
Bank guarantees were required to be furnished by the respondent in terms of the
agreement. The case of the appellant is that the first respondent failed to
commission the plant in terms of the agreement. The appellant sent a notice
dated 26th April, 2003 duly putting the respondent on notice of its failure to
commission the plant by the scheduled date i.e. 11th February, 2001 and other
revised dates, i.e., 26th January, 2002, 25th November, 2002, 28th February,
2003 and 25th April, 2003. Thereafter, a meeting was held between the parties
at the intervention of the Government of Karnataka on 1st July, 2003 where both
the parties had agreed as hereunder:
i) 1st respondent shall furnish bank guarantee for Rs.92.40 lakhs towards
delivery and commissioning of the plant valid upto 28.02.2004.(Clause 1).
ii) Simultaneously, with the receipt of the aforesaid bank guarantee, the
petitioner shall release Rs.140.41 lakhs to the 1st respondent (Clause 4)
iii) 1st respondent will start trial run to crush 500-1000 tonnes of sugarcane
within 20 days from the date of receipt of Rs.140.41 lakhs as aforesaid (Clause
6).
iv) The plant will be fully commissioned by November/December 2003 (Clause 7).
The first respondent in terms of the agreement reached between the parties
furnished a bank guarantee for a sum of Rs. 92.40 lakhs dated 4th July, 2003.
The appellant on its part released Rs. 140.41 lakhs on 5th July, 2003.
The case of the appellant is that the trial crushing did not start even as on
28th / 29th July, 2003; no doubt, the trial crushing commenced on 26th November,
2003 but the same had to be stopped on 22nd December, 2003 due to defects in
the turbo alternator. The appellant addressed letter dated 27th December, 2003
to the respondent regarding non-supply, defective erection and
non-commissioning of the plant by the first respondent. It is not necessary to
notice further details in this regard as there is any amount of controversy
between the parties as regards non-compliance with the terms and conditions of
the agreement. Each is accusing the other of breach of terms of agreement. The
appellant, however, relied upon the detailed report dated 16th January, 2004
furnished by National Federation of Co-operative Sugar Factories Ltd., the
consultants to the project, in support of the plea that the trial run was unsuccessful
and incomplete. The appellant stated on account of the teething problems the
appellant could not undertake the crushing of sugarcane leading to heavy
losses.
Be it as it may, the Board of Directors of the appellant Society resolved in its
meeting dated 13th March, 2004 to invoke the bank guarantee of Rs. 92.40
furnished by the first respondent. The appellant accordingly sent a letter
requesting the Commissioner of Cane Development and Director of Sugar to
counter sign the invocation letter on the ground that the respondent herein had
failed to commission the plant as agreed.
The case of the respondent in nut shell is that the project fell into rough
weather purely on account of the inability of the appellant Society to arrange
the requisite funds. It is however admitted that after exchange of several
acrimonious letters and notices, the parties finally agreed on a final course
with a revised time frame to erect and commission the plant in a meeting held
on 1st July, 2003. It is pursuant to that agreement the respondent furnished
the bank guarantee in question and the appellant released the amount of
Rs.140.41 lakhs on 5th July, 2003 and required the respondent to implement the
trial run by 25th July, 2003. It is submitted that the contract between the
parties envisaged four different kinds of bank guarantees to ensure particular
set of obligations by the respondent. Clauses 16.4 and 17.5 deal with the bank
guarantees for timely delivery of civil drawings and clause 17.6 deals with
bank guarantee for advance payments; for timely delivery and commissioning of
plant is dealt with clauses 8, 16, 16.3, 17.4, 17.9 and for ensuring
performance of the plant is dealt with by clauses 9, 16.2, 17.3 and 17.9.
It is the case of the respondent that the trial run of plant and machinery was
arranged during 25th July, 2003 and 2nd August, 2003 and the trial run was
found satisfactory. The actual commissioning was to take place from 21st July,
2003 but has actually started on 27th November, 2003. According to the
respondent after continuous crushing of the sugarcane for about a month all of
a sudden there was a problem in the working of the machinery which was attended
to on the spot. We do not propose to notice further details in this regard for
each one of the parties is blaming the other. There is any amount of
controversy between the parties in this regard and it would not be proper to
make any comment at this stage since the parties are already before the
Arbitrator who is required to decide the dispute on merits in accordance with
law. The main contention of the respondent is that the appellant raised false
and untenable claims only with a view to avoid or postpone the payment of huge
amount of Rs. 327 lakhs due and payable to the respondent. It is under those
circumstances the respondent got issued notice to the appellant to refer the
dispute for resolution through arbitration. The appellant instead of responding
to the notice resolved to invoke the bank guarantee with a malafide intention
of depriving the respondent of its legitimate right to receive certain amounts.
The case of the respondent is that the bank guarantee is a conditional one and
unless the condition precedent for enforcement of the bank guarantee is
satisfied the appellant cannot be permitted to invoke the bank guarantee. It is
on that ground the respondent filed Misc. Petition Under Section 9 of the Arbitration and Conciliation Act, 1996 seeking injunction
against the appellant restraining it from encashing the bank guarantee No.56/03
dated 4th July, 2005.
The trial court after an elaborate consideration of the matter dismissed the
application filed by the respondent herein and refused to grant any injunction
restraining the appellant from encashing the bank guarantee as prayed for by
the respondent. The trial court came to the conclusion that invocation of the
bank guarantee and its encashment by the appellant cannot be held to be
fraudulent or untenable and further held that the respondent has failed to
prove that there will be irretrievable injustice in case bank guarantee is
invoked.
Being aggrieved by the order passed by the trial court rejecting the injunction
application, the respondent herein filed MFA No.6188/04 challenging the
legality and the correctness of the order passed by the trial court. The High
Court upon reappreciation of the evidence and material available on record
reversed the order passed by the trial court and accordingly granted injunction
restraining the appellant herein from encashing the bank guarantee. The appellate
court has taken the view that the bank guarantee appears to be a conditional
one and "under the documents the guarantor is entitled to know that the
appellant has failed to conduct the trial test and the commissioning of the
project as agreed." The appellate court however also took a strange view
that the invocation of the bank guarantee without informing to the bank as to
the fact of alleged breach of agreement itself amounts to fraud. The Appellate
Court also took the view that the letter invoking the bank guarantee should be
counter signed by the Commissioner of Sugar, Bangalore, but the same has been
signed by some other authority and not by the Commissioner of Sugar.
Being aggrieved by the orders passed by the High court restraining the
appellant from invoking the bank guarantee the present appeal has been
preferred.
Shri S.S. Javali, learned senior counsel, submitted that the bank guarantee
executed by the respondent herein in favour of the appellant is an
unconditional one. The bank giving such a guarantee is bound to own it
irrespective of any dispute raised by the respondent. The appellant's right to
invoke the bank guarantee cannot be questioned except on the ground of fraud or
irreparable injury or on the ground that invoking the bank guarantee would
cause irretrievable injury. The respondent failed miserably to make out any
case for grant of injunction. The High Court's order suffers from incurable
infirmities was the submission.
Shri Jayant Bhushan, learned senior counsel, appearing on behalf of the first
respondent supported the judgment of the High Court and submitted that the bank
guarantee in question was a conditional bank guarantee to ensure test trials
and commissioning within the specified time periods and since these events have
already been ensued the bank guarantees cannot be encashed.
We have carefully considered the rival submissions made during the course of
the hearing of the appeal. We have perused the entire material available on
record including the orders passed by the trial court as well as the High
Court.
The main question that arises for our consideration is whether the bank
guarantee in question is a conditional one or not. Before we proceed further it
would be appropriate to have a look at the relevant clauses of the agreement
dated 1st November, 2000 :
"16.3.1: If the sellers fail to commission the plant according to the
schedule of commissioning which is to be worked out mutually to enable the
commissioning of the plant within the schedule time, fixed or extension allowed
by the purchasers, if any, thereof the sellers shall pay penalty by an amount
equal to =% (Half percent) of the contract price for every completed week of
delay, but not exceeding 3% of the total contract price.
16.3.2: To secure the obligations under clause 16.3.1, the sellers shall
furnish to the purchasers, bank/insurance guarantees in the form set out by the
purchasers as provided in clause 17.4 hereinafter.
17.9 : The bank/insurance guarantee (s) required to be furnished by the sellers
under the provisions hereof to secure the timely delivery, erection,
commissioning, as well as for performance of the plant and machinery supplied
by the sellers or for any other purpose under the provisions hereof shall be in
the form of purchasers after mutual discussions between the purchasers and
sellers which form(s) shall invariably include the provisions that the decision
of the purchasers as to whether there has been any loss or damage or default
and or negligence on the part of the sellers will be final and binding on the
sellers, that the right of the purchasers shall not be affected or suspended by
reasons of the fact that any dispute or disputes have been raised by the
sellers with regard to their liability or that proceedings are pending before
any Tribunal, Arbitrator(s) or court with regard thereto or in connection
therewith, that the Guarantee shall pay to the purchasers the sum under the
guarantee(s) without demur on first demand and without requiring the purchasers
to invoke any legal remedy that may be available to them, that it shall not be
open to the guarantee to know the reasons of or to investigate to go into the
merits of the demand or to question or to challenge the demand or to know any
facts affecting the demand or to require proof of the liability of the sellers
before paying the amount demanded by the purchasers under the guarantee (s). In
case of invocation of any bank guarantee by the purchasers, the same should be
countersigned by the Commissioner for Cane Development and Director of Sugar of
the concerned State Government.
The Bank/Insurance guarantee or guarantees required to be furnished by the
sellers under the provisions hereof to secure timely delivery, erection,
commissioning as well as for performance of the plant and machinery supplied by
the sellers or for any other purpose under the provisions hereof shall be for
such period as may cover the period of complete supply, erection and
commissioning and performance respectively, as the case may be, as stipulated
under the agreement. If however, the period of agreement is extended due to
Force Majeure or sellers not fulfilling their obligations under the agreement
or for any other reasons whatsoever, sellers shall have such guarantees
extended upto the corresponding extended period and failure of the sellers to
do so will amount to a breach of the contract and in no case the extension of
the period of the contract shall be construed as waiver of the right of the
purchasers to enforce the guarantee.
The relevant portion of the bank guarantee is extracted herein below:
"Clause 1 : In consideration of the above premises, the Guarantor
hereby undertakes to pay to the purchasers within 30 days of demand, without
demur such a sum not exceeding Rs. 92, 40, 000/- (Rupees Ninety two lakhs forty
thousand only), representing 3% of the contract price as the purchasers may
demand upon the failure of the supplier to conduct the trial test of the sugar
plant by 24th July, 2003 and also upon the failure of the sellers to commission
the Project (Plant and Machinery) before December 2003. 2.
The Guarantor shall pay to the purchasers on demand the sum without demur and
without requiring the purchasers to invoke any legal remedy that may be
available to them, it being understood and agreed FIRSTLY that the purchasers
shall be the sole judge of and as to whether the amount of bank guarantee has
become recoverable from the sellers or whether the sellers have committed any
breach(es) of the terms and conditions of the said agreement and the extent of
losses, damages, costs, charges and expenses caused to or suffered by or that
may be caused to or suffered by purchaser's from time to time shall be final
and binding to the Guarantor and SECONDLY that the right of the purchasers to
recover from the guarantor any amount due to the purchasers under this
guarantee shall not be affected or suspended by reasons of the fact that any
dispute or disputes have been raised by the sellers with regard to their
liability or that proceedings are pending before any tribunal Arbitrator(s) or
court with regard thereto or in connection therewith and THIRDLY that the
guarantor shall immediately pay the aforesaid guaranteed amount to the
purchasers on demand and it shall not be open to the Guarantor to know the
reasons of or to investigate or to go into the merits of the demands or to
question or challenge the demand or to know any facts affecting the demand, and
LASTLY that it shall not be open to the guarantor to require the proof of the
liability of the sellers to pay the amount, before paying the sum demanded
under clause 1 above.
8. The invocation of this guarantee shall be by a letter as herein, signed by
the purchasers and countersigned by the Commissioner of Sugar, Bangalore,
Karnataka State."
A plain reading of Clauses (1) and (2) of the bank guarantee makes it
abundantly clear that the guarantor had undertaken to pay to the appellant
within 30 days of demand, without demur such an amount not exceeding Rs.92.40
lakhs. The sole discretion is conferred on the purchasers as to whether the
amount of bank guarantee has become recoverable from the sellers or whether the
sellers have committed any breach of the terms and conditions of the said
agreement. The right of the purchaser to recover from the guarantor the
guaranteed amount shall not be affected or suspended by the reasons of the fact
that any dispute or disputes have been raised by the sellers with regard to
their liability or that the proceedings are pending before any tribunal or
court with regard thereto or in connection therewith.
However, Shri Jayant Bhushan, learned senior counsel submitted that the
purchasers were entitled to invoke the bank guarantee and demand the payment of
money only upon the failure of the supplier to conduct the trial test of the
sugar plant by 24th July, 2003 and also upon the failure of the sellers to
commission the project before December, 2003. This condition forms an integral
part of the bank guarantee was the submission. We find it difficult to accept
the submission. The guarantee executed by the guarantor (PNB) in favour of the
purchaser (appellant) cannot be dissected in the manner suggested by the
learned senior counsel for the respondent. Clauses 1 and 2 of the guarantee
executed by the banker in favour of the purchaser are required to be read
together. The respondent cannot be allowed to contend that there is a dispute
as to whether it had failed to conduct the trial test of the sugar plant by
24th July, 2003 and therefore bank guarantee cannot be invoked. The acceptance
of the argument would make Clause 2 of the bank guarantee totally meaningless
and inoperative. The guarantor essentially agreed that the purchasers alone
shall be the sole judge in the matter as to whether the amount of bank
guarantee has become recoverable from the sellers or whether the seller had
committed any breach of the terms and conditions of the agreement. The dispute,
if any, between the parties with regard to the liability in any proceedings
either before the arbitral tribunal or court in no manner affects the right of
the purchaser to invoke the bank guarantee and realise the guaranteed sum from
the guarantor.
In U.P. Cooperative Federation Ltd. Vs. Singh Consultants and Engineers (P)
Ltd. [ Â 1998 (1) SCC 174 ] the respondent therein entered into an agreement
with the appellant for constructing a Vanaspati manufacturing plant for the
latter. The contract required the respondent to furnish two bank guarantees for
proper construction and successful completion of the plant. The Bank of India
executed two bank guarantees in favour of the appellant. Under the terms of
guarantee the bank undertook to make unconditional payments on demand without
reference to the respondent. The guarantees also provided that the appellant
would be the sole judge for deciding whether the respondent had fulfilled the
terms of the contract or not. Disputes arose between the parties as to the
erection and performance of the plant. The seller approached the civil court
seeking injunction restraining the purchaser from invoking the bank guarantee.
The High Court, proceeding on the basis that the injunction was sought not
against the bank but against the appellant, restrained the appellant from
invoking the bank guarantee. This court after elaborate consideration of the
matter held :
"commitments of banks must be honoured free from interference by the
courts. Otherwise, trust in commerce internal and international would be
irreparably damaged. It is only in exception case that is to say in case of
fraud or in case or irretrievable injustice be done, the could should
interfere."
Appeal (Civil) 2952 of 2007; Civil Appeal No. 2952 of 2007 (Arising Out of
Special Leave Petition (C)No.11821 of 2005)(, JJ)
This court relied upon its own earlier decision in United Commercial Bank vs.
Bank of India and others [ Â ] in which it is observed " that a bank
issuing or confirming a letter of credit is not concerned with the underlying
contract between the buyer and seller. Duties of a bank under a letter of
credit are created by the documents itself." In General Electric Technical
Services Company Inc. vs. Punj sons (P) Ltd. and anr. [ Â 6 ] this court observed " if the documentary credits
are irrevocable and independent, the Bank must pay when demand is made. Since
the bank pledges its own credit in involving its reputation, it has no defence
except in the case of fraud. The Bank's obligation of course should not be
extended to protect the unscrupulous party, that is, the party who is
responsible for the fraud. But the banker must be sure of his ground before
declining to pay. The nature of the fraud that courts talk about is fraud of a
"erregious nature as to vitiate the entire underlying transaction."
It is the fraud of the beneficiary not the fraud of somebody else. The bank
cannot be interdicted by the court at the instance of purchaser in the absence
of fraud or special equities in the form of preventing irretrievable injustice
between the parties.
In our considered opinion if the bank guarantee furnished is an unconditional
and irrevocable one, it is not open to the bank to raise any objection
whatsoever to pay the amounts under the guarantee. The person in whose favour
the guarantee is furnished by the bank cannot be prevented by way of an
injunction in enforcing the guarantee on the pretext that the condition for
enforcing the bank guarantee in terms of the agreement entered between the
parties has not been fulfilled. Such a course is impermissible. The seller
cannot raise the dispute of whatsoever nature and prevent the purchaser from
enforcing the bank guarantee by way of injunction except on the ground of fraud
and irretrievable injury.
In U.P. State Sugar Corporation vs. Sumac International Ltd. [ Â 0 ] this court had laid down the principle as to the
enforcement of the bank guarantees as under :
"The law relating to invocation of such Bank Guarantees is by now well
settled. When in the course of commercial dealings an unconditional bank
guarantee in terms is given or accepted, the beneficiary is entitled to realise
such a bank guarantee in terms thereof irrespective of any pending disputes.
The bank giving such a guarantee is bound to honour it as per its terms
irrespective of any dispute raised by its customer. The very purpose of giving
such a bank guarantee would otherwise be defeated. The courts should,
therefore, be slow in granting an injunction to restrain the realization of
such a bank guarantee. The courts have carved out only two exceptions. A fraud
in connection with such a bank guarantee would vitiate the very foundation of
such a bank guarantee. Hence if there is a fraud of which the beneficiary seeks
to take advantage, he can be restrained from doing so. The second exception
relates to cases where allowing the encashment of an unconditional bank
guarantee would result in irretrievable harm or injustice to one of the parties
concerned".
We do not propose to burden this judgment of ours with various other
authoritative pronouncements on this very subject.
In the present case the respondent in its application filed under Section 9 of
the Arbitration and Conciliation Act, 1996 in the
district court, Bidar mostly highlighted as to how the very vital conditions of
the agreement have been breached by the appellant herein by not arranging the
funds at the proper time. It is alleged that the appellant did not even
complete their obligation in respect of providing storage facilities for
valuable goods etc. It is specifically alleged that required funds were not
available with the appellant. On account of non availability of funds there were
two halts of nine months and five months during the execution of the project
from 03.12.2001 to 14.08.2002 and from 14.08.2002 to 10.01.2003. It is further
alleged that the appellant failed to arrange for all the pre-requisites. It is
not necessary for the purpose of disposal of this appeal to notice all the
allegations and averments filed by the respondents except to note that the main
thrust of the allegation relate to alleged breach of the conditions of the
agreement by the appellant. It was further contended that the bank guarantees
were conditional bank guarantees and not unconditional. We have referred to the
substance of the allegations only to highlight that no factual foundation as
such has been laid in the pleadings as regards the allegation of fraud. In fact
there is no serious allegation of any fraud except using the word
"fraud". It is also not stated as to how irreparable loss would be
caused in case the appellant is allowed to encash the bank guarantee. The only
two exceptions, namely fraud and irretrievable injury based on which injunction
could be granted restraining encashment of bank guarantee are singularly absent
in the pleadings. Once it is held that the bank guarantee furnished by the
banker is an unconditional one, the appellant in our considered opinion cannot
be restrained from encashing the bank guarantee on the ground that a serious
dispute had arisen between the parties and on the allegations of breach of
terms and conditions of the agreement entered between the parties.
The High Court in its judgment went to the extent of recording a finding that
it cannot be said that there was no delivery, erection and commissioning of
plant. The High Court also took the view that the appellant has agreed to
invoke the bank guarantee only in case of default on the part of the respondent
in delivery, erection, commissioning of the plant. This view of the High Court
is totally contrary to the terms and conditions of the bank guarantee executed
by the bank in favour of the appellant. It has been specifically agreed by the
banker to pay the guaranteed amount to the appellant on demand and " it
shall not be open to the guarantor to know the reasons of or to investigate or
to go into the merits of the demands or the question or challenge the demand or
to know any facts affecting the demand." The bank guarantee further makes
it clear that it shall not be open to the guarantor to require the proof of the
liability of the seller to pay the amount, before paying the sum demanded. In
the process the High Court made the following observations which in our
considered opinion are totally untenable and unsustainable being contrary to
the terms and conditions incorporated in the bank guarantee. The High Court
observed :
"From the facts and circumstances narrated by the petitioner, it is
clear that the first respondent could not have invoked the bank guarantee when
the setting up of the machinery and commissioning in accordance with the
agreement and all these facts therefore show that the invocation of the bank
guarantee was fraudulent."
It is further held that since the appellant failed to give any information to
the bank as to the fact of any alleged breach of agreement in order to invoke
the bank guarantee itself amounts to fraud. We must however hasten to add that
the learned senior counsel appearing for the respondent did not support this
part of the judgment of the High Court.
However, Shri Jayant Bhushan, learned senior counsel appearing for the
respondents contended that invocation of the bank guarantee relating to
"delivery and commissioning of the plant" was wholly illegal and the
High Court was right in granting the injunction order relating to that
guarantee. It was submitted that the said bank guarantee could be invoked only
on the failure of the respondent to commission the plant according to the
schedule of commissioning in terms of the relevant clauses of the principal
agreement entered into between the parties and since the conditions
contemplated under those clauses did not exist, the invocation of the guarantee
by the appellant itself is bad.
The learned counsel in support of his submission relied upon the decision of
this Court in Hindustan Construction Co. Ltd. Vs. State of Bihar & Ors. [
 This Court in Hindustan Construction Co. (supra) having referred to the
terms of clause (9) of principal contract between the parties therein came to
the conclusion that the bank guarantee specifically refers to the original
contract and postulates that the obligations expressed in the contract, are not
fulfilled by HCCL, the right to claim recovery of the whole or part of the
"advance mobilisation" then alone the bank was liable to pay the
amount due under the guarantee to the Executive Engineer. The court found that
the bank guarantee specifically refers to clause (9) of the principal agreement
and it is under those circumstances came to the conclusion that the amount
covered by the bank guarantee becomes payable and the same could be invoked
only in the circumstances referred to in clause (9) of the principal agreement.
The bank guarantee executed by the bank in the instant case in favour of the
appellant herein does not contain any such clause. Mere fact that the bank
guarantee refers to the principal agreement without referring to any specific
clause in the preamble of the deed of guarantee does not make the guarantee
furnished by the bank to be a conditional one. In the very said judgment this
Court observed that "what is important, therefore, is that the bank guarantee
should be in unequivocal terms, unconditional and recite that the amount would
be paid without demur or objection and irrespective of any dispute that might
have cropped up or might have been pending between the beneficiary under the
bank guarantee or the person on whose behalf the guarantee was furnished. The
terms of the bank guarantee are, therefore, extremely material. Since the bank
guarantee represents an independent contract between the bank and the
beneficiary, both the parties would be bound by the terms thereof. The
invocation, therefore, will have to be in accordance with the terms of the bank
guarantee, or else, the invocation itself would be bad." What is relevant,
therefore, is the terms incorporated in the guarantee executed by the bank. On
careful analysis of the terms and conditions of the guarantee, we find the
guarantee to be an unconditional one. The respondent, therefore, cannot be
allowed to raise any dispute and prevent the appellant from encashing the bank
guarantee.
For all the aforesaid reasons, we hold that the respondent herein did not make
out any case for grant of injunction restraining the appellant herein from
encashing the bank guarantee.
For the reasons stated above, the impugned judgment of the Appellate Court is
set aside and the appeal is allowed.
Before parting with the judgment, it is made clear that the observations, if
any made, in this order shall have no bearing whatsoever upon the dispute
pending before the Arbitrator which is required to be disposed of on its own
merits uninfluenced by the observations, if any, made in this order.
No costs.