IN THE SUPREME COURT OF INDIA

 

                        CIVIL APPELLATE JURISDICTION

 

                        CIVIL APPEAL NO.3353 OF 2005

 

 

 

    M/S ESSAR OIL LTD.                      ... APPELLANT

 

 

                                   VERSUS

 

 

 

 

    HINDUSTAN SHIPYARD LTD. & ORS.        ... RESPONDENTS

 

 

                                    WITH

 

                        CIVIL APPEAL NO.3355 OF 2005

 

 

 

                               J U D G M E N T

 

 

 

 

    ANIL R. DAVE, J.

 

    1.     Being aggrieved by a common judgment dated 29th September, 2004,

    delivered in Appeals Against Order Nos.255 and 624 of 2003 by the  High

    Court of Andhra Pradesh at Hyderabad, these appeals have been filed  by

    M/s Essar Oil Ltd., who had been given  a  sub-contract  by  the  first

    respondent, Hindustan Shipyard Ltd., in respect of a contract which was

    given to it by the Oil and Natural Gas Commission.

 

    2.     The facts giving rise to the present litigation, in a  nutshell,

    are as under:-

 

           The Oil and Natural Gas Commission (hereinafter referred  to  as

    ‘the ONGC’) had given a contract to Hindustan Shipyard  Ltd.  to  carry

    out work of fabrication, skidding, sea fastening,  transportation  etc.

    at various stations located in  the  coastal  areas  of  India.  It  is

    pertinent to note that the contractor, Hindustan Shipyard Ltd., who  is

    respondent no.1 in both  the  appeals,  had  been  permitted  to  avail

    services of any other person for doing the aforestated  work  entrusted

    to it.  In other words, it was open to respondent no.1 to engage a sub-

    contractor for getting  the  work  done.  Other  respondents  in  these

    appeals are the arbitrators, who are formal parties.

 

    3.     In pursuance of the aforestated understanding arrived at and the

    contract entered into between the ONGC and Hindustan Shipyard Ltd. (who

    has been referred to as ‘the respondent’ hereinafter),  the  respondent

    had entered into a contract  with  M/s  Essar  Oil  Ltd.,  who  is  the

    appellant in both these  appeals.   Thus,  the  appellant  was  a  sub-

    contractor in respect of the  contract  which  the  respondent  had  to

    fulfill for the ONGC.

 

    4.     It appears that for the sake of convenience and so as to obviate

    certain financial difficulties of the respondent, certain payments  had

    been made to the appellant directly by the ONGC.  The  appellant,  upon

    getting certain work done  under  the  sub-contract  and  upon  getting

    necessary certificates with regard to the quality and quantity  of  the

    work done from the respondent, had received some payment from the  ONGC

    on the strength of those certificates.

 

    5.     In the process of carrying out the contract, the  appellant  was

    not paid by the respondent for the work done and therefore,  a  dispute

    had arisen between the appellant and the respondent.  Let us  not  look

    at the nature of the dispute or the amount  claimed  or  the  liability

    with regard to making payment to the appellant at this  stage,  suffice

    it to state  that  there  was  an  Arbitration  Agreement  between  the

    appellant and the  respondent  and  therefore,  the  dispute  had  been

    referred to the Arbitral Tribunal.  Respondent nos.2, 3 and 4  are  the

    Arbitrators, who had made the  Award  with  regard  to  which  we  will

    discuss presently.

 

    6.     Thus, the dispute with regard  to  non-payment  and  some  other

    disputes had been referred  to  the  Arbitral  Tribunal  consisting  of

    Respondent nos.2, 3 and 4.   It is pertinent  to  note  here  that  the

    ONGC, who had given a contract to the respondent, was  not  before  the

    Arbitral Tribunal because the ONGC was not a party to  the  Arbitration

    Agreement entered into between the appellant and the  respondent.   The

    question which was involved in the  said  dispute  was  not  only  with

    regard to determination of the amount to be paid to the appellant,  but

    was also with regard to determination of a person  who  was  liable  to

    make payment to the appellant.

 

    7.     After hearing the concerned parties, the Arbitral Tribunal  made

    an Award, but all the three Members of the Tribunal could not  come  to

    the same conclusion.  The majority i.e. two  Members  of  the  Tribunal

    came to the conclusion that there was no privity  of  contract  between

    the appellant and the ONGC; and  the  ONGC  was  not  a  party  to  the

    contract between the appellant and the respondent.   In the aforestated

    circumstances, the ONGC, according to the majority view, could  not  be

    held liable for making payment to the appellant and  the  liability  to

    make payment to the appellant was that of the respondent.  It was  also

    held by the majority that the appellant could not even sue the ONGC for

    the unpaid amount.  Accordingly, the Award was made.  At this stage, we

    are not concerned with the other facts and the amount  awarded  by  the

    majority of the Tribunal.

 

    8.     On the other hand, the dissenting Member, who was  in  minority,

    was of the opinion that there was a contract between the appellant  and

    the ONGC and therefore, the ONGC was liable  to  make  payment  to  the

    appellant,  but  he  expressed  an  opinion  to  the  effect  that  the

    respondent should be directed to make payment to the appellant only  if

    the respondent is paid the  unpaid  amount  by  the  ONGC.   Thus,  the

    minority view was that the liability to make payment to  the  appellant

    was that of the ONGC, but as the  ONGC  was  not  a  party  before  the

    Tribunal,  the  proper  course  open  to  the  appellant  was  to  take

    appropriate legal action against the ONGC for recovery  of  the  amount

    due and payable to the appellant.

 

    9.     The respondent was  aggrieved  by  the  Award  of  the  Arbitral

    Tribunal as according  to  the  majority  view  of  the  Tribunal,  the

    respondent was  liable  to  make  payment  to  the  appellant.  In  the

    circumstances, the respondent filed OP NoS.989 of 2001 and 96  of  2002

    before the Principal District Judge, Visakhapatnam, under Section 34 of

    the Arbitration and Conciliation Act, 1996.

 

    10.    The Principal District Judge, Visakhapatnam,  decided  both  the

    Original Petitions by orders dated 10th October, 2002 and 1st November,

    2002, respectively. The learned Principal District Judge confirmed  the

    award on the issues with which we are concerned, but  he  remanded  the

    matter to the Arbitral Tribunal on the issues regarding  counter  claim

    etc., with which we are not concerned in this case.

 

    11.    Being aggrieved by the aforestated  two  orders  passed  in  two

    Original Petitions, the respondent filed Appeals Against Order  Nos.255

    and 624 of 2003 before the High Court of Andhra Pradesh  and  the  High

    Court allowed the appeals by a common judgment  dated  29th  September,

    2004, validity of which has been challenged before this Court in  these

    appeals.

 

    12.    The High Court came to a conclusion that there was a  tripartite

    agreement among the ONGC, the appellant and the respondent.   The  High

    Court had relied upon some letters written by the appellant to the ONGC

    and therefore, the ONGC was also treated as a party  to  the  contract.

    It also held that as the ONGC was a party to the contract, it ought  to

    have been made a party before the Arbitral Tribunal but as the ONGC was

    not represented before the Arbitral Tribunal, the  Award  made  by  the

    Tribunal was bad in law.  The Award deserved to be  set  aside  by  the

    Principal District Judge but he  did  not  and  therefore,  the  orders

    passed in the Original Petitions filed  before  the  learned  Principal

    District Judge were also bad in law and accordingly the Award  and  the

    orders passed in the Original Petitions were quashed and set aside.

 

    13.    The main issue which is  involved  in  these  appeals  is  about

    ascertainment of a person,  who  is  liable  to  make  payment  to  the

    appellant.  There is no dispute with regard to quality or  quantity  of

    the work done by the appellant at this stage.   It is  not  in  dispute

    that the appellant has not been paid the amount payable to it.   It  is

    also not in  dispute  that  the  appellant  had  been  engaged  by  the

    respondent  in  pursuance  of  a  contract  entered  into  between  the

    respondent and the ONGC and it was open  to  the  respondent  to  avail

    services of any other person for doing the work entrusted to it by  the

    ONGC.   In the light of the aforestated undisputed facts, the  question

    is only with regard to determination of liability of the person who has

    to make payment to the appellant.

 

    14.    The learned counsel appearing for the appellant  had  vehemently

    submitted that the view taken by the majority of the Arbitral  Tribunal

    being correct, the High Court ought not to  have  interfered  with  the

    said view.  So as to substantiate his submission, the  learned  counsel

    had mainly submitted that there was no privity of contract between  the

    appellant and the ONGC.  The appellant had performed the  work  of  the

    ONGC in pursuance of a contract given to it by  the  respondent,  which

    was a sub-contract in nature.   In absence of any contract between  the

    ONGC and the appellant, the appellant could not  have  made  any  claim

    before the ONGC and as there was no contract between them, it was  also

    not possible for the appellant to make the  ONGC  a  party  before  any

    Court or Authority  for  recovery  of  the  amount  payable  to  it  in

    pursuance of the sub-contract given by the respondent.

 

    15.    It had been fairly admitted by the learned counsel appearing for

    the appellant that very often payments were made to  the  appellant  by

    the ONGC.  It had further been submitted that the payments were made by

    the ONGC so as to facilitate the appellant and to get the work  of  the

    contract done smoothly.  Every time when payment was made by  the  ONGC

    to the appellant, the ONGC used to debit the account of the  respondent

    i.e. the amount so paid by the ONGC to the appellant was treated by the

    ONGC as if the said payment was made by the  ONGC  to  the  respondent.

    Thus, so as to obviate a long procedure and to expedite payment to  the

    appellant, who was actually doing the job for the ONGC, instead of  the

    ONGC paying to the appellant  through  the  respondent,  the  ONGC  was

    paying directly to the appellant.

 

    16.    The learned counsel for the  appellant  had  with  great  stress

    submitted that there was not a single contract  between  the  appellant

    and the ONGC and there was no tripartite contract among the  appellant,

    the respondent and the ONGC, whereby the ONGC was made  liable  to  pay

    the appellant in respect of the work done by it.

 

    17.    For the aforestated simple reason, it had been submitted by  the

    learned counsel for  the  appellant  that  the  majority  view  of  the

    Arbitral Tribunal was correct and the  respondent  is  liable  to  make

    payment to the appellant with whom it had entered into the contract. It

    had been further submitted by the learned counsel that in view  of  the

    aforestated factual and legal  position,  the  appeals  deserve  to  be

    allowed and the respondent should be made liable to make payment to the

    appellant.

 

    18.    On the other hand, the learned counsel for  the  respondent  had

    submitted that the ONGC was liable to make payment to the appellant and

    therefore, there is no liability on the part of the respondent to  make

    payment to the appellant.

 

    19.    It had further been submitted by the  learned  counsel  for  the

    respondent that it is not necessary that in each  and  every  case  the

    contract should be in writing. The contract can be very  well  inferred

    by the act or  conduct  of  the  parties,  whereby  impliedly  a  party

    undertakes to make  good  a  liability  to  make  payment  to  someone.

    According to the learned counsel, even in the instant case,  there  was

    an implied contract amongst the appellant, the respondent and the  ONGC

    and therefore, it was the liability of the ONGC to make payment to  the

    appellant.

 

    20.    The learned counsel for the respondents had drawn our  attention

    to correspondence exchanged between the ONGC and the respondent. He had

    specially referred to a letter dated 25th October,  1991  addressed  by

    the respondent to the ONGC, wherein it was stated  that  the  ONGC  had

    desired to make payment directly  to  the  appellant  in  pursuance  of

    meetings convened among the representatives of the respondents and  the

    ONGC.  He had also submitted that some of the letters  written  by  the

    ONGC to the respondent clearly denoted that the ONGC had  accepted  the

    liability to make payment to the appellant and therefore, there was  no

    liability on the part of the respondent to  make  any  payment  to  the

    appellant.   He had further submitted that the  subsequent  conduct  of

    the ONGC of making direct payment to the appellant established the fact

    that the ONGC had undertaken the  liability  to  make  payment  to  the

    appellant.  The aforestated letter dated 25th October, 1991  and  other

    letters which had been exchanged between the respondent  and  the  ONGC

    were placed on record to show that there was  a  contract  between  the

    ONGC and the appellant.

 

    21.    For the aforestated  reasons,  it  had  been  submitted  by  the

    learned counsel for the respondent that the view of the High Court that

    the ONGC was liable to make payment to the  appellant  is  correct  and

    therefore, the appellant should take  appropriate  action  against  the

    ONGC for recovery of  the  unpaid  amount.  The  learned  counsel  had,

    therefore,  submitted  that  the  view  taken  by  the  High  Court  is

    absolutely correct and the respondent is no more  liable  to  make  any

    payment to the appellant.

 

    22.    We have heard the learned counsel for the parties at length  and

    have also considered some judgments cited by  them  and  the  documents

    which had been placed on record and relied upon by them.

 

    23.    Upon hearing the learned counsel and  looking  at  the  contract

    entered into between the appellant and the respondent and upon  perusal

    of other letters, we believe that the view expressed by the High  Court

    cannot be accepted.

 

    24.    It is true that the ONGC  had  made  payment  to  the  appellant

    directly on several occasions.  Upon perusal of the correspondence,  we

    find that some understanding, but not amounting  to  any  agreement  or

    contract, was arrived at between the ONGC and the respondent for making

    direct payment to the appellant, possibly because  the  respondent  was

    not in a position to make prompt payments to the  appellant.   It  also

    appears that  on  account  of  the  delay  in  making  payment  to  the

    appellant, the work of the ONGC was likely to  be  adversely  affected.

    The ONGC was interested in getting its work done promptly  and  without

    any hassles.  In the circumstances, upon perusal of the correspondence,

    which had taken place between the ONGC and the respondent, it is  clear

    that so as to facilitate the respondent, the ONGC had made payments  on

    behalf of the respondent to the appellant directly.

 

    25.    Simply because some payments had been made by the  ONGC  to  the

    appellant, it would not be established that  there  was  a  privity  of

    contract between the ONGC and the appellant and only  for  that  reason

    the ONGC cannot be saddled with a liability to pay the  amount  payable

    to the appellant by the respondent.

 

    26.  It is also pertinent to note that the  Arbitration  Agreement  was

    only between the appellant and the respondent.   The  ONGC  was  not  a

    party to the Arbitration Agreement.  When a dispute had arisen  between

    the appellant and the respondent in relation to payment of  money,  the

    appellant had initiated the arbitration proceedings.  As the  ONGC  was

    not a party to the  Arbitration  Agreement,  it  could  not  have  been

    represented before the Arbitral Tribunal.  If the ONGC was not a  party

    before the Arbitral Tribunal, the Tribunal  could  not  have  made  any

    Award making the ONGC liable to make payment to the appellant.  In  the

    aforestated factual and legal position, the Arbitral Tribunal could not

    have made the ONGC liable in any respect and rightly, the majority view

    of the Arbitral Tribunal was to the effect that the ONGC, not  being  a

    party to any contract or  Arbitration  Agreement  with  the  appellant,

    could not have been made liable to make any payment to the appellant.

 

    27.    We are in agreement with the view expressed by the  majority  of

    the Arbitral Tribunal.  In our opinion, the High Court had committed an

    error by not considering the above facts  and  by  observing  that  the

    appellant will have to take legal action against the ONGC for  recovery

    of the amount payable to it.  If one looks at the relationship  between

    the appellant and the respondent, it is very clear that the  respondent

    had given a sub-contract to the appellant and in the said agreement  of

    sub-contract, the ONGC was not a party and there was  no  liability  on

    the part of the ONGC to make any payment to the appellant. Moreover, we

    could not find any correspondence establishing contractual relationship

    between the ONGC and the appellant.  In  the  circumstances,  the  ONGC

    cannot be made legally liable to make any payment to the appellant.  As

    stated hereinabove, only for the sake of convenience  and  to  get  the

    work of the ONGC done without any hassle, the ONGC had made payment  to

    the appellant  on  behalf  of  the  respondent  without  incurring  any

    liability to make complete payment on behalf of the respondent.

 

    28.    The learned counsel appearing for the appellant failed  to  show

    any document in the nature of  a  contract  entered  into  between  the

    appellant and the ONGC whereby the ONGC had made itself liable to  make

    payment to the appellant.  Even when the payment had been made  by  the

    ONGC, it was very clear that the payments were made on  behalf  of  the

    respondent as the ONGC was debiting the account of  the  respondent  by

    the amount paid to the appellant.  It is important that the payment was

    made to the appellant only upon  certification  of  work  done  by  the

    respondent.  The ONGC had given a contract to the respondent.  The ONGC

    had never entered into any contract with the appellant  and  therefore,

    it did not rely upon any certification or any  statement  made  by  the

    appellant in relation to quantum of work done by the  appellant.   This

    fact also shows that the ONGC was concerned with  the  work  which  had

    been approved by the respondent and instead of making  payment  to  the

    respondent, the ONGC had made payment to the appellant on behalf of the

    respondent, though there was no legal obligation on  the  part  of  the

    ONGC to make such a payment to the appellant.

 

    29.    For the aforestated reasons, we  do  not  agree  with  the  view

    expressed by the High Court and the impugned judgment delivered by  the

    High Court is set aside.  The ONGC shall not be liable to make payment,

    as rightly decided by the Arbitral Tribunal, to the appellant  but  the

    payment shall have to be made by the respondent, who had given  a  sub-

    contract to the appellant.  Majority view of the Arbitral  Tribunal  on

    the above issue is confirmed and the view of  the  High  Court  is  not

    accepted.   The  respondent  shall  accordingly  make  payment  to  the

    appellant.

 

    30.    For the reasons enumerated hereinabove, the appeals are  allowed

    with no order to costs.

 

 

 

 

                                                      …………………………………………………….J

                                   (ANIL R. DAVE)

 

 

 

 

 

 

                                                      …………………………………………………….J

                                     (VIKRAMAJIT SEN)

 

 

 

 

 

 

                                                      …………………………………………………….J

                                         (PINAKI CHANDRA GHOSE)

    NEW DELHI;

    JULY 2, 2015.