2019 INSC 513

Center of Indian Trade Union, A Federation of Registered Trade Unions v. The State of Maharashtra

Neutral Citation
2019 INSC 513
Date
11.04.2019
Year
2019
Source in the index
sci.gov.in neutral-citation

Full text

NON­REPORTABLE

IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION

SPECIAL LEAVE PETITION (C) NO. 7734 OF 1997

CENTER OF INDIAN TRADE UNIONS,
A FEDERATION OF REGISTERED
TRADE UNIONS …PETITIONER(S)
Versus

STATE OF MAHARASHTRA …RESPONDENT(S)

JUDGMENT

Deepak Gupta, J.

1. The petitioner had challenged the execution of the Power

Project Agreement (PPA) and the modified power project

agreements first of which was executed in the year 1993 by the

Maharashtra State Electricity Board (for short ‘the MSEB’) in

favour of Dabhol Power Corporation Limited (for short ‘DPC’)

before the Bombay High Court.

Signature Not Verified

Digitally signed by
DEEPAK GUGLANI

2. Though the High Court came to the conclusion that the
Date: 2019.04.11
16:10:59 IST
Reason:

action of the Board and the Governments concerned was

1

questionable and that everything was not above board, it

dismissed the writ petition(s) on the ground that the petitioner

had not been able to place on record before the Court any

material justifying the allegations as regards corruption, bribery,

fraud and misrepresentation.

3. Thereafter, the petitioner filed the present petition. On

02.05.1997, this Court issued notice only on the following issue:

“(2) The accountability of the State of
Maharashtra (respondent No. 2) in this matter,
particularly, on account of the inconsistent
stand taken by it from time to time.”

4. By the same order, this Court refused leave in so far as the

question of the validity of the project and contract for Dabhol

Power Project was.

5. While the special leave petition was pending, the State of

Maharashtra appointed a Committee headed by Dr. Mahdav

Godbole, former Home Secretary (known as ‘Godbole Committee’)

to go into the matter.

2

6. The Godbole Committee submitted its report to the State of

Maharashtra on 10th April, 2001 indicating serious

illegalities/infirmities in the matter of award of the contract and

processing of approvals, which were prima facie against public

interest. Failure of governance, it was observed, was broad and

across different governments and at both administrative and

political levels. However, there was difference of opinion amongst

members of the Godbole Committee, whether it should

recommend appointment of a judicial commission of inquiry

under the Commission of Inquiry Act, 1952. Whereas 2 members

felt that that a Judicial Commission of Inquiry should be

constituted, 3 members did not agree with the said proposal.

7. On 7th November, 2001, Shri Justice S. P. Kurdukar, a

former Judge, was appointed for thorough investigation into the

aspects of culpability of various public servants.

8. The Union of India filed a suit before this Court (Original

Suit No.2 of 2003 – Union of India vs. State of Maharashtra &

Anr.) and an order was passed in the said suit staying further

proceedings of the Kurdukar commission of inquiry. This suit

3

came to be finally dismissed in the year 2014. Thereafter, the

matter came up before this Court on 18.02.2015 when learned

counsel appearing for the State of Maharashtra prayed for some

time to find out whether Justice Kurdukar would be in a position

to resume the proceedings. No response has been filed. The fact

remains that the Commission has not functioned even after

dismissal of the suit.

9. It appears that nothing much was done and the matter

came up before this Court on 07.03.2018 when this Court

directed the State of Maharashtra to inform the Court whether it

would like the Kurdukar Commission of inquiry to continue or

would they like the case to be argued on merits. The State of

Maharashtra subsequently filed an affidavit that due to long

efflux of time it was no longer useful or feasible to continue with

the judicial commission of inquiry.

10. Therefore, the hearing in this case is limited to the question

as to whether the judicial commission of inquiry should continue

or not.

4

11. Dr. Rajeev Dhawan, learned senior counsel appearing as

amicus curiae, urged that in view of the serious allegations of

corruption and abdication of duties by various authorities and

officials, it would be in the interest of justice to continue with the

commission of inquiry and in case Justice Kurdukar was not able

to continue with the commission of inquiry, the same could be

headed by some other retired Judge of the Supreme Court of

India.

12. Dr. Dhawan drew our attention to the various portions of

the report submitted by Dr. Godbole committee. We may make

reference only to following portion:

“The Committee is troubled with the failure of
governance that seems to have characterised
almost every step of the decision making process
on matters relating to DPC. This failure of
governance has been broad, across different
governments at different points of time, at both
the State and the Central level, and across
different agencies associated with examining the
project, and at both the administrative and
political levels. It strains belief to accept that
such widespread and consistent failure to
execute assigned responsibilities is purely
coincidental. Though the Committee was given
certain additional terms of reference,
specifically, item (3) of Resolution No. PSP
2001/CR3448/NRG­2 dated March 9, 2001, it
has unanimously decided that it is not the
proper forum to investigate such matters to the
degree that would be required. The Committee,

5

in the short time allocated to it, is unable to
determine reasons for the consistent lapses, but
is extremely concerned at it.”

13. The Committee has found serious infirmities in the manner

in which the PPA was executed, the manner in which it was re­

negotiated, the manner in which the tariff was fixed etc.. As per

the Committee, everything was done in a manner which helped

DPC and caused loss to the MSEB and the public at large.

14. It would be pertinent to mention that the foreign company

Enron, which was involved, has abandoned the project. The

project is virtually working at half the capacity and the rate of

production of electricity is so high that the project has become

economically unviable. In these circumstances, Dr. Dhawan

urged that this Court should continue with the commission of

inquiry.

15. We are of the considered view that though normally in such

a case a judicial inquiry should have been conducted but as far

as the present case is concerned, more than a quarter of century

has elapsed since the first PPA was executed. The foreign

corporation and the original project proponents are no longer

6

available. Most of the senior officials would have retired and

virtually no action can be taken against them. Furthermore, the

commission of inquiry even if continued or constituted afresh,

will take its own time and, as opined by 3 Members of the

Godbole Committee, the constitution of such commission of

inquiry would serve no useful purpose. This was the stand in the

year 2001 and has greater force 18 years later.

16. In view of the long delay and in view of the fact that due to

non­availability of many persons involved, no useful purpose

would be served in continuing with the judicial commission of

inquiry, we close the petition in the peculiar facts and

circumstances of the case.

……………………..CJI.
(Ranjan Gogoi)

…………………………J.
(Deepak Gupta)

…………………………J.
(Sanjiv Khanna)

New Delhi
April 11, 2019

7