2026 INSC 828

National Projects Construction Corporation Limited v. Ishvakoo (India) Pvt. Ltd.

Neutral Citation
2026 INSC 828
Date
11.08.2026
Year
2026
Source in the index
sci.gov.in neutral-citation

Full text

2026 INSC 828 REPORTABLE

IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. 5819 OF 2025

National Projects Construction
Corporation Ltd. …….Appellant (s)
Versus

Ishvakoo (India) Pvt. Ltd. ……. Respondent(s)

JUDGMENT

K. V. Viswanathan, J.

1) The present appeal calls in question the correctness of

the order dated 21.05.2019 passed by a Division Bench of the

High Court of Delhi at New Delhi in FAO(OS)(COMM) No.

113/2019. By the said order, the Division Bench dismissed

the appeal filed by the appellant and confirmed the order of

the learned Single Judge dated 05.04.2019 in

OMP(I)(COMM.) No. 57/2019 filed under Section 9 of the
Signature Not Verified

Digitally signed by

Arbitration and Conciliation Act, 1996, (hereinafter referred
NIRMALA NEGI
Date: 2026.08.11
16:34:53 IST
Reason:

to as ‘the 1996 Act’).
Page 1 of 26

2) The respondent filed OMP (I)(COMM.) No. 57/2019

before the High Court seeking the following reliefs:-

“(a) Allow the present application and further direct the
Respondent to immediately refund the amount of
Rs.3,50,00,000/- to the Petitioner (in terms of order dated
20.09.2018) being the amount appropriated by it by
wrongfully encashing the Bank Guarantees in question, along
with interest at the rate of 18% per annum from 14.09.2017 till
the amount is refunded, and
(b) Award costs of the proceedings in favour of the Petitioner
and against the Respondents, and/or … ”

BRIEF FACTS: –
3) On 16.08.2002, the appellant and the respondent

entered into a Memorandum of Understanding (MoU) for the

work of Bus Terminus at Taj Mahal Bus Stand, UPST Bus Stand,

Idgah Bus Stand and development of Taj Trapezium Zone

(TTZ) Heritage Corridor for Agra, Government of Uttar

Pradesh. In December 2002, the respondent was provided

Rs. 3.5 crores as Mobilisation Advance against the bank

guarantees furnished by it.

4) Disputes arose between the parties. The arbitration

clause was invoked by the respondent and an Arbitrator

came to be appointed to adjudicate the disputes.
Page 2 of 26

5) At that stage, a Section 9 application came to be filed in

OMP No. 363/2003 before the High Court, by the respondent.

The prayer made in the application was to restrain the

appellant from invoking Bank Guarantee Nos. 109/2002 to

124/2002 for a total sum of Rs. 3,50,00,000/- issued by the

Canara Bank. The said Section 9 application was disposed of

on 15.12.2005, in the following terms: –

“OMP No. 363/2003
Present petition is filed under Section 9 of the Arbitration
and Conciliation Act, 1996 (in short ‘the Act’) seeking
restraint against the respondent from invoking bank
guarantees No.109 to 124/2002 for a total sum of Rs. 3
crores 50 lacs issued by Canara Bank, H-Block,
Connaught Circus, New Delhi in favour of the respondent.
The arbitration proceedings are underway. On 16th
September, 2003 order was passed recording the
undertaking of the petitioner to renew these bank
guarantees and directing the respondent not to press for
encashment of these bank guarantees during the
extended period of the bank guarantees. This order was
extended from time to time and on 19th August 2004, it
was directed that the bank guarantees shall be kept alive
by the petitioner till the disposal of this petition. Since the
counsel for the petitioner thereafter on 7th July 2005 gave
an undertaking that the bank guarantees shall be kept
alive till the arbitrator gives the award, the learned
counsel for the respondent sought time to have the
instructions in the matter.
Mr. Taneja, learned senior counsel appearing for the
respondent, states on instructions that the respondent
shall not invoke these bank guarantees provided the

Page 3 of 26

bank guarantees are kept alive till the arbitrator gives
the award and further till the award becomes
enforceable as a decree under Section 36 of the Act.
However, it is subject to the condition that if after
adjudication by the arbitrator it is found that the
respondent has to recover the amount from the
petitioner, the respondent will be entitled to recover
such amount by invoking the bank guarantees. This
suggestion is acceptable to learned counsel for the
petitioner. The Managing Director of the petitioner is
present and statement by the learned counsel for the
petitioner is made on instructions from his client.
The petition is accordingly disposed of recording
undertaking of the petitioner to the effect that the bank
guarantees shall be kept alive till the matter is
adjudicated upon by the arbitrator and even thereafter
if petition under Section 34 of the Arbitration Act is
filed till the disposal of the said petition. It is also
made clear that on the award becoming executable if
under the said award the respondent has to recover
the amount, the respondent shall be entitled to encash
the bank guarantees.
IA also stands disposed of”.
(Emphasis supplied)
6) It will be noticed that in the order it is clearly recorded

that the appellant undertook not to invoke the bank

guarantees, provided the bank guarantees were kept alive. It

is further recorded that if after adjudication by the Arbitrator,

it is found that the appellant [referred to as Respondent in the

said Order] had to recover the amount from the Respondent

[referred to as the Petitioner in the said Order], the appellant

Page 4 of 26

shall be entitled to recover the amount by invoking the bank

guarantees.

7) The Arbitrator proceeded with the arbitration and

rendered an Award on 05.12.2017. In the meantime, it

transpires from the record that since the respondent herein

was unable to keep the bank guarantees alive, the appellant

herein invoked the bank guarantees, in and about

September, 2017.

8) Before the Award was pronounced and after the

encashment of bank guarantees, the respondent moved a

petition under Section 9 of the 1996 Act before the High

Court. That petition was disposed of on 01.11.2017 by

holding that since the respondent failed to keep the bank

guarantees alive after September, 2017, there was no fault in

the conduct of the appellant, and no further orders were

required to be made.

9) Before the arbitrator, the respondent herein was the

claimant and the appellant herein was the respondent.

Page 5 of 26

Admittedly, no counter-claim was filed by the appellant. The

arbitrator framed several issues, of which, Issue Nos. 3 and 4

are relevant for our purpose, which read as under:-

“3. Whether the Claimant is entitled to discharge of bank
Guarantees? OPC
4. Whether the Claimant is entitled to Bank Charges of Rs.
77,27,225/- for keeping the Bank Guarantees? OPC”
10) In the Award, the arbitrator dismissed the claims of the

respondent. Dealing with Issue Nos. 3 and 4, the arbitrator

recorded as under: –

“Issues No. 3 and 4
Issues No. 3 and 4 are whether the Claimant is entitled to
discharge of the Bank Guarantee and also whether the
Claimant is entitled to the sum of Rs. 77,27,225/- towards
the bank charges for keeping the Bank Guarantee alive.
230. Without adverting to the submissions made by the
Parties, the Tribunal finds that the High Court of Delhi,
vide Order dated 15.12.2005, passed in O.M.P. No.
363/2003 had disposed of the Petition in the following
terms:
“The Petition is accordingly disposed of with the
undertaking of the petitioner to the effect that the
bank guarantees shall be kept alive till the matter
is adjudicated by the arbitrator and even
thereafter if petition under section 34 of the
arbitration act is filed till the disposal of the said
petition. It is also made clear that on the award
becoming executable if under the said award the
respondent has to recover the amount, the
respondent shall be entitled to encash the bank
guarantees. IA also stands disposed of”.
Page 6 of 26

231. Therefore, it can be seen that by its own undertaking,
the Claimant was bound to keep the BG alive in terms of
the above order.
232.In any event, due to the fraudulent and collusive
conduct of the Claimant, the Respondent cannot be
fastened with any liability and as such the Tribunal is not
inclined to grant any relief in this regard. Respondent is
accordingly, not, liable to pay any bank charges.”

11) The respondent herein filed a Section 34 application. An

order came to be made on 20.09.2018 while permitting the

parties to complete pleadings, to the effect that the appellant

ought to return the amount, equivalent to the bank

guarantees to the respondent, within three weeks.

Thereafter, on 30.10.2018, a further order came to be made

in the Section 34 application. While reiterating that the

appellant herein ought to bring back the money, equivalent

to the amount of bank guarantees, the learned Single Judge,

in the Order of 30.10.2018, after overruling the objection of

the appellant, directed the appellant to remit the amount to

the respondent within 10 days, failing which, the concerned

officer of the appellant was directed to be present in Court.

Page 7 of 26

12) These orders of the learned Single Judge (dated

20.09.2018 and 30.10.2018), were carried in appeal before

the Division Bench in FAO (OS)(COMM) 271/2018, whereby

a consent order dated 29.11.2018 was passed, which reads as

under: –

“The challenge in this appeal is to the orders dated
20.09.2018 and 30.10.2018.
After some hearing in the matter, it is agreed that without
prejudice to the rights and contentions of the parties which
have been raised by them in petition filed under Section 34
of the Arbitration and Conciliation Act, 1996, the impugned
orders may be set aside and the questions raised may be
left open to be decided along with objections filed under
Section 34 of the Arbitration and Conciliation Act, 1996, by
the respondent.
This order will not come in the way of the respondent, in
case the respondent chooses to file a fresh petition under
Section 9 of the Arbitration and Conciliation Act, 1996.
Legal objections of the appellant herein are kept open.
The present appeal is accordingly disposed of, in the above
terms.
All pending applications also stand disposed of.”

13) Pursuant thereto, O.M.P.(I)(COMM) No. 57/2019 came

to be filed (pending the Section 34 application) by the

respondent herein praying for return of the amount

equivalent to the bank guarantees. This petition under

Page 8 of 26

Section 9 came to be disposed of on 05.04.2019 by the

learned Single Judge. The learned Single Judge, while

allowing the Section 9 application, recorded the following

crucial findings: –

“11.3 Before I proceed further, I must note that during the
course of the arguments, Mr. Nandrajog submitted that
the bank guarantees had been issued against mobilization
advance which was not utilized. This submission was
made before me on 30.10.2018 as well. I had, in that
proceeding, put a pointed question to the learned counsel
for the respondent as to whether there was any finding in
the award that the petitioner had failed to utilize the
mobilization advance. I had received a candid answer, on
that date, from Mr. Rajat Arora, the Advocate instructing
Mr. Nandrajog, that there was no such finding.
11.4 Upon a perusal of the award, I noticed that there is no
such finding recorded by the Arbitral Tribunal. Therefore,
this query again was put by me at the hearing held today,
lest I missed something. While Mr. Nandrajog was not
able to show anything which would answer this query, he
did refer to paragraphs 158 to 160 of the Award.
11.5 I have examined the observations made by the
learned Arbitrator in those paragraphs. None of the
observations, however prejudicial they may be, indicate
that the petitioner had contended that the bank
guarantees furnished by the petitioner against
mobilization advance was not utilized by the petitioner.
The observations made in the paragraphs referred to by
Mr. Nandrajog do not answer the query that I posed to the
learned Senior Counsel.
12. Therefore, the question before me is: whether without
a claim, can the respondent, by any stretch of
imagination, hope to keep the money with it. Mr.
Nandrajog points out that Issue No.3 was related to
discharge of bank guarantee while Issue No.4 was related
Page 9 of 26

to the petitioner’s claim for bank charges. According to
the learned Senior Counsel, both the issues were decided
by the learned Arbitrator against the petitioner.
12.1 I tend to disagree with Mr. Nandrajog that Issue No. 3
was, at all, decided by the learned Arbitrator. A careful
perusal of Paragraphs 229 to 232 of the award dated
5.12.2017 would show that the learned Arbitrator did not
decide Issue No. 3 which pertained to discharge of bank
guarantees. The learned Arbitrator after quoting the
order dated 15.12.2005 passed by this Court, had only
stated the following:
“231. Therefore, it can be seen that by its own
undertaking, the Claimant was bound to keep the
bank guarantee alive in terms of the above order.
232. In any event, due to the fraudulent and
collusive conduct of the Claimant, the Respondent
cannot be fastened with any liability and as such,
the Tribunal is not inclined to grant any relief in
this regard. The respondent is accordingly, not
liable to pay any bank charges.”
(emphasis is mine)
12.2 What is plainly evident, when one reads the award, is
that, the learned Arbitrator was unaware of the fact that
the bank guarantees had already been encashed. As a
result, the learned Arbitrator held the view that the bank
guarantees continued to remain in operation on account of
an undertaking to that effect, given by the petitioner, by
which it was bound. In this regard, the obvious reference
of the Arbitral Tribunal was to the order dated 15.12.2005
passed by this Court. More importantly, this observation
was made in the context of Issue No. 4, which required the
Arbitral Tribunal to determine as to who would bear the
financial burden of keeping the bank guarantees alive.
12.3 The Arbitral Tribunal, clearly, failed to deal with the
direction contained in order dated 15.12.2015 which
required the petitioner to keep the bank guarantees alive
only to enable the respondent to encash the bank
guarantees against an executable award, if any, passed in
its favour. In view of the fact that there was no
counterclaim lodged by the respondent, the Arbitral
Page 10 of 26

Tribunal, in my view, had to decide, in the changed
circumstances, whether or not the condition put in place
by this Court via order dated 15.12.2015 would continue
to operate. The Arbitral Tribunal, clearly, did not decide
this aspect of the matter and, thus, Issue No. 3 remain
unaddressed.
12.4 The Arbitral Tribunal, though, for whatever it is
worth, did decide Issue No. 4 which related to “liability”,
purportedly borne by the petitioner on account of bank
charges for keeping the bank guarantees alive.
13. Therefore, I am confronted with two undeniable facts.
First, no counterclaims were filed. Second, however
irrelevant it may be, there is no finding that the bank
guarantees were encashed on account of non-utilization of
mobilisation advance.
14. Given this position, in my view, if I were to permit the
respondent to continue to hold on the money, it would not
only result in the respondent unjustly enriching itself but
would also be contrary to the purpose and object with
which order dated 15.12.2005 was passed by this Court
when arbitration had not commenced. Thus, the argument
that the respondent is good for its money, given the facts
obtaining in this case, is untenable and hence is
rejected.”
15.2 Thus, in view of the fact that I have still not
adjudicated upon the Section 34 petition, equities, to my
mind, would be balanced if an appropriate direction is
issued to the respondent to deposit the money in Court,
which is also the alternative relief that Mr. Verma has
prayed for. This direction appears to be wholesome as
deposit of money in Court will enable accrual of interest
which will ultimately benefit the party which succeeds in
the main matter.”
“17. Thus, for the foregoing reasons, I am inclined, for the
moment, insofar as this petition is concerned, to direct the
respondent to deposit the monies, which, I am told, is an
amount equivalent to a sum of Rs.3.5 Crores with the
registry of this Court. The said amount will be deposited
within two weeks from today. Upon such amount being
deposited with the Registry of this Court, the same shall
Page 11 of 26

be invested in an interest-bearing fixed deposit,
maintained with a nationalized bank.”
It is this Order, which the Division Bench, vide the impugned

order has upheld.

14) We have heard Mr. Rajat Arora, learned counsel for the

appellant and Mr. Ajay Bansal, learned counsel for the

respondent.

CONTENTIONS OF THE APPELLANT: –

15) Learned counsel for the appellant submits that under

Section 9, a Court cannot grant relief which amounts to a final

adjudication of rights that are pending consideration at the

Section 34 stage. It is submitted that post award, Section 9

power is exercised only to protect the fruits of the Award in

aid of its enforcement. It is submitted that a claimant whose

claim has been dismissed in toto holds no Award, has no

adjudicated “amount in dispute” surviving in its favour, and

has no fruits of its own to protect. Learned counsel submitted

that the respondent herein is seeking a mandatory direction

to claw back monies already realised lawfully under the

Page 12 of 26

bank guarantees. It is submitted that the legality of

encashment stands concluded by the order dated

01.11.2017. Learned counsel submits that the High Court has

undertaken a merits review of the Award at the interlocutory

stage, which was illegal. Learned counsel, after referring to

the Award, submitted that the arbitrator had declined the

claim for discharge of bank guarantees and had refused

expressly the relief on account of the respondent’s own

undertaking and its fraudulent and collusive conduct.

Learned counsel submitted that the relief granted to the

respondent is not encompassed within the framework of

Section 9(1)(ii)(e). Learned counsel submitted that the

absence of a counter claim did not make any difference to

the dispute. The dismissal of Claim No. 1 itself removed the

substrata in the case of the respondent to seek the bank

guarantee amounts back. It was submitted that the principles

of Order XXXVIII Rule 5 of the Code of Civil Procedure, 1908,

were not satisfied.

Page 13 of 26

CONTENTIONS OF THE RESPONDENT: –

16) Learned counsel for the respondent contended that no

counter claims were filed by the appellant and further there

is no finding in the Award as to the non-utilization of

mobilization advance. Learned counsel contended that Issue

Nos. 3 before the arbitrator remained unaddressed. Learned

counsel submitted that the finding on collusion against the

respondent is subject matter of challenge in the Section 34

proceedings. Learned counsel reiterated the finding of the

learned Single Judge that permitting the appellant to retain

the amount would only result in unjustly enriching the

appellant. Learned counsel submitted that Section 9 of the

1996 Act confers wide powers to pass orders of the nature

passed by the Single Judge and the Division Bench.

QUESTION FOR CONSIDERATION: –
17) In the above background, the question for consideration

is whether the courts below were justified in directing the

appellant to deposit a sum of Rs. 3.5 crores in the Registry of

Page 14 of 26

the High Court, pending disposal of the Section 34

application filed by the respondent, challenging the Award

of the arbitrator?

ANALYSIS AND DISCUSSION: –
18) This is a case where the Award Debtor has, post the

Award, invoked the jurisdiction under Section 9. Insofar as

the maintainability of a Section 9 application by the Award

Debtor is concerned, the issue is no longer res integra.

Recently, in Home Care Retail Marts Pvt. Ltd. vs. Haresh N.

Sanghavi, 2026 SCC Online SC 670, this Court, speaking

through Manmohan, J., held as under: –

“2. The substantial question of law that arises for
consideration in the present batch of appeals is whether a
petition under Section 9 of the Arbitration and
Conciliation Act, 1996 (hereinafter referred to as ‘the Act’)
at the post-award stage, by a party that has lost in the
arbitral proceedings and has no enforceable award in its
favour, is maintainable in law?

43. Sections 34 as well as 36 provide remedies against an
award or a stay thereof, whereas Section 9 ensures
protection of the subject matter or the amount in dispute.
An unsuccessful party cannot secure protection of its
claim under Section 34 or Section 36. To deny interim
relief under Section 9 would leave such a party
remediless. In fact, if the Court declines to entertain
an application of a losing party for interim relief, there

Page 15 of 26

would be no forum available for protection of the
subject matter, even where the award under challenge
is stayed and potentially liable to be set aside.
Moreover, the ultimate outcome may alter the rights
of parties and, therefore, distinction between a
‘winning’ and a ‘losing’ party cannot govern access to
the remedy under Section 9 of the Act.

49. Even applying the test of purposive interpretation, ‘a
party’ must mean any party to the arbitration agreement.
This Court can envisage situations where a party that has
lost in arbitration may nonetheless require interim
protection. For instance, where an arbitral award has
been rendered without proper notice to a party, or where
a party is able to prima facie demonstrate that the award
has been induced or tainted by fraud or corruption. In
such situations, the Court may not only stay the award but
also grant interim measures under Section 9 of the Act to
balance the equities. Similarly, in certain cases, an
unsuccessful party may have obtained interim
protection during the arbitral proceedings, such as an
order restraining invocation of a bank guarantee.
Upon the rendering of the arbitral award, such interim
protection ordinarily stands vacated. However, the
unsuccessful party may challenge the award under
Section 34 of the Act and obtain a stay on the
enforcement of the arbitral award under Section 36(3)
of the Act. In such circumstances, immediate removal
of interim protection, for example, in relation to a
bank guarantee, may result in irreversible prejudice
to the unsuccessful party whose challenge to the
arbitral award is pending adjudication.

52. Consequently, in rare and compelling cases, it
may be necessary to permit the unsuccessful party to
invoke Section 9 of the Act to seek continuation of the
existing interim protection. This assumes greater
significance, as noted earlier, in light of the decision in
Gayatri Balasamy (supra) which recognises the Court’s
power under Section 34 of the Act to modify an arbitral
award, including the power to sever ‘the “invalid” portion
from the “valid” portion of the award’.

Page 16 of 26

59. Needless to say, the grant of interim relief under
Section 9 of the Act will continue to be guided by well-
established principles, namely, the existence of a
prima facie case, balance of convenience, and
likelihood of irreparable harm or injury. This Court, in
Essar House Private Limited v. Arcellor Mittal Nippon
Steel India Limited, (2022) 20 SCC 178, has held as under:
“47. Section 9 of the Arbitration Act confers wide power
on the Court to pass orders securing the amount in
dispute in arbitration, whether before the commencement
of the arbitral proceedings, during the arbitral
proceedings or at any time after making of the arbitral
award, but before its enforcement in accordance with
Section 36 of the Arbitration Act. All that the Court is
required to see is, whether the applicant for interim
measure has a good prima facie case, whether the
balance of convenience is in favour of interim relief as
prayed for being granted and whether the applicant
has approached the court with reasonable
expedition.”

60. Undoubtedly, the threshold for grant of interim
relief will be higher in the case of an unsuccessful
party in arbitration seeking such relief. In rare and
compelling cases, permitting the unsuccessful party
to invoke Section 9 of the Act would prevent
irreparable prejudice and preserve the efficacy of the
challenge proceedings. However, the rights of such a
party cannot be curtailed merely on the apprehension
of possible misuse of a statutory provision.”
[Emphasis supplied]

19) This Court, while holding the application to be

maintainable, has sounded a note of caution that the

threshold for grant of interim relief will be higher in case the

application is moved by an Award Debtor and that a court

Page 17 of 26

may, in rare and compelling cases, permit the unsuccessful

party to invoke Section 9 to prevent irreparable prejudice

and to preserve the efficacy of the challenge under Section

34.

20) This Court, also reiterated the holding in Essar House

Private Limited vs. Arcellor Mittal Nippon Steel India

Limited., (2022) 20 SCC 178 emphasizing the principle that

the existence of a prima facie case and balance of

convenience have to be seen along with the aspect whether

party has approached the Court with reasonable expedition

or not.

21) In Essar House (supra), this Court laid down the

guiding principles while interpreting Section 9 especially

Clause (ii) (e) which enabled the Court to pass such other

interim measure of protection as may appear to the Court to

be just and convenient.

22) This Court held that while couching a relief under the

“just and convenient” clause, the discretion has to be

Page 18 of 26

exercised judiciously and not arbitrarily and that such an

exercise of power must promote the efficacy of arbitration as

a form of dispute resolution.

23) In Essar House (supra), this Court held as under: –

41. As argued by Mr Kaul, besides the specific power of
securing the amount in dispute, the courts have been
empowered to pass any interim measure of protection,
keeping in view the purpose of the proceedings before it.
The said provision confers a residuary power on the
Court to pass such other interim measures of protection
as may appear to be just and convenient.

44. In Jagdish Ahuja v. Cupino Ltd. [2020 SCC OnLine
Bom 849], the Bombay High Court correctly summarised
the law in para 6 extracted hereinbelow :
“6. As far as Section 9 of the Act is concerned, it cannot
be said that this Court, while considering a relief
thereunder, is strictly bound by the provisions of Order
38 Rule 5. As held by our Courts, the scope of Section
9 of the Act is very broad; the court has a discretion
to grant thereunder a wide range of interim
measures of protection “as may appear to the court
to be just and convenient”, though such discretion
has to be exercised judiciously and not arbitrarily.
The court is, no doubt, guided by the principles
which civil courts ordinarily employ for considering
interim relief, particularly, Order 39 Rules 1 and 2
and Order 38 Rule 5; the court, however, is not
unduly bound by their texts. As this Court held
in Nimbus Communications Ltd. v. BCCI [2012 SCC
OnLine Bom 287] (per D.Y. Chandrachud, J.), as the
learned Judge then was), the court, whilst exercising
power under Section 9, ‘must have due regard to the
underlying purpose of the conferment of the power
under the court which is to promote the efficacy of
arbitration as a form of dispute resolution’. The
Page 19 of 26

learned Judge further observed as follows :
‘24. … Just as on the one hand the exercise of the power
under Section 9 cannot be carried out in an uncharted
territory ignoring the basic principles of procedural law
contained in the Code of Civil Procedure, 1908, the
rigours of every procedural provision in the Code of
Civil Procedure, 1908 cannot be put into place to defeat
the grant of relief which would subserve the paramount
interests of justice. A balance has to be drawn between
the two considerations in the facts of each case.’ ”

47. Section 9 of the Arbitration Act confers wide power on the
Court to pass orders securing the amount in dispute in
arbitration, whether before the commencement of the arbitral
proceedings, during the arbitral proceedings or at any time
after making of the arbitral award, but before its enforcement
in accordance with Section 36 of the Arbitration Act. All that
the Court is required to see is, whether the applicant for
interim measure has a good prima facie case, whether
the balance of convenience is in favour of interim relief
as prayed for being granted and whether the applicant
has approached the court with reasonable expedition.

49. Proof of actual attempts to deal with, remove or dispose of
the property with a view to defeat or delay the realisation of
an impending arbitral award is not imperative for grant of
relief under Section 9 of the Arbitration Act. A strong
possibility of diminution of assets would suffice. To assess
the balance of convenience, the Court is required to
examine and weigh the consequences of refusal of
interim relief to the applicant for interim relief in case of
success in the proceedings, against the consequence of
grant of the interim relief to the opponent in case the
proceedings should ultimately fail.

24) Earlier, this Court in Adhunik Steels Ltd. vs. Orissa

Manganese and Minerals (P) Ltd., (2007) 7 SCC 125,

reiterated how the well-known principles governing the

Page 20 of 26

grant of an interim injunction followed by courts are not alien

to Section 9 of the 1996 Act. This Court held as under: –

11. It is true that Section 9 of the Act speaks of the court by
way of an interim measure passing an order for protection,
for the preservation, interim custody or sale of any goods,
which are the subject-matter of the arbitration agreement and
such interim measure of protection as may appear to the
court to be just and convenient. The grant of an interim
prohibitory injunction or an interim mandatory
injunction are governed by well-known rules and it is
difficult to imagine that the legislature while enacting
Section 9 of the Act intended to make a provision which
was dehors the accepted principles that governed the
grant of an interim injunction. Same is the position
regarding the appointment of a receiver since the section
itself brings in the concept of “just and convenient” while
speaking of passing any interim measure of protection. The
concluding words of the section, “and the court shall have the
same power for making orders as it has for the purpose and
in relation to any proceedings before it” also suggest that the
normal rules that govern the court in the grant of interim
orders is not sought to be jettisoned by the provision.
Moreover, when a party is given a right to approach an
ordinary court of the country without providing a special
procedure or a special set of rules in that behalf, the ordinary
rules followed by that court would govern the exercise of
power conferred by the Act. On that basis also, it is not
possible to keep out the concept of balance of
convenience, prima facie case, irreparable injury and the
concept of just and convenient while passing interim
measures under Section 9 of the Act.”
APPLICATION OF LAW TO THE FACTS: –
25) Did the respondent, in the present case, satisfy the

above yardsticks, is the crucial question that arises for

consideration.
Page 21 of 26

26) An analysis of the facts and the application of the

principles led us to the irresistible conclusion that the

respondent, in fact, did fulfil in ample measure, the

necessary parameters for obtaining relief under Section 9.

We say so for the following reasons: –

(i) Firstly, on 15.12.2005, when OMP No. 363/2003 filed by

the respondent was adjudicated, the High Court directed

that if after adjudication by the Arbitrator, it was found that

the appellant had to recover the amount from the

respondent herein, the appellant herein will be entitled to

recover such amount by invoking the bank guarantees;

(ii) Secondly, no counter-claim was filed by the appellant

before the Arbitrator;

(iii) Thirdly, Issue Nos. 3 and 4 dealt with by the Arbitrator

only concerned the bank charges as to whether

respondent was entitled to the same. The Arbitrator

appears to be oblivious of the fact that prior to the Award,

the bank guarantees were invoked since the respondent

was unable to keep the bank guarantees alive;
Page 22 of 26

(iv) Fourthly, the Section 34 Court is engaged with the

issue whether the Arbitrator has recorded any finding as to

whether the respondent failed to use mobilisation

advance. Though prima facie findings have been recorded

in the current proceedings, to the effect that there is no

such finding by the Arbitrator, it will finally be decided

only in the Section 34 application;

(v) Fifthly, the order dated 01.11.2017 of the learned

Single Judge will not come in the way of the respondent for

the reason that the present proceedings arise out of a

Section 9 application, post Award. In fact, the learned

Single Judge, in the present round, after noticing the order

dated 01.11.2017, observed that the Arbitrator had

reserved the award on 12.12.2016 and pronounced the

Award on 05.12.2017, completely oblivious of the fact of

encashment of bank guarantees. Moreover, the question in

the present round of litigation is really whether in the light

of the contents of the Award, permitting the appellant to

retain the money would tantamount to unjustly enriching
Page 23 of 26

the appellant? It is in that context that the Order of

01.11.2017 has to be viewed;

(vi) Sixthly, since prima facie it is found that there was no

counter claim by the appellant and no finding that the

mobilisation advance against which the bank guarantees

were given was not utilized, the High Court was justified in

observing that permitting the appellant to hold on the

money pending Section 34 application, would be unjustly

enriching the appellant and would also be in teeth of the

order of 15.12.2005 passed by the High Court in OMP No.

363/2003;

(vii) Seventhly, applying the dictum laid down in Home

Care Retail Marts (supra) and Essar House (supra), the

case of the respondent does provide a rare and a

compelling case where even after applying the higher

threshold, the directions, as made by the courts below,

were required to prevent irreparable prejudice and

preserve the efficacy of the challenge in Section 34;

Page 24 of 26

(viii) Eighthly, the High Court could not be said to have

exercised its jurisdiction arbitrarily. It was a judicious

exercise, keeping in mind the parameters of a prima facie

case and balance of convenience and irreparable

prejudice. The respondent did move the court with

reasonable expedition; and,

(ix) Finally, a relief, as the one fashioned by the courts

below, furthers the efficacy of arbitration as a form of

dispute resolution and is in keeping with the purpose and

object of interim measures contemplated under Section 9.

CONCLUSION: –

27) For the reasons stated above, we find no merit in the

appeal. The appeal is, accordingly, dismissed. We grant 4

(four) weeks’ time to the appellant to deposit the amount of

Rs. 3.5 crores with the Registry of the High Court of Delhi.

On deposit, the Registry of the High Court shall keep the

same in a Fixed Deposit (FD), in any Nationalized Bank, on

auto-renewal basis, till the disposal of the Section 34

application. Needless to state that the observations made in
Page 25 of 26

these proceedings are only for the purpose of deciding the

Section 9 petition and the Section 34 application will be

decided on its own merits without being influenced by the

observations in the orders of the courts below or in the

present judgment. No order as to costs.

…………………………….J.
[K. V. VISWANATHAN]

…………………………….J.
[ALOK ARADHE]
New Delhi;
11th August, 2026

Page 26 of 26