2026 INSC 985
Dakschinanchal Vidyut Vitran Nigam Ltd. v. Vidut Lokpal UP.
Full text
2026 INSC 985 NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. 5099 OF 2013
DAKSCHINANCHAL VIDYUT
VITRAN NIGAM LTD. … APPELLANT(S)
VERSUS
VIDUT LOKPAL,
UTTAR PRADESH AND OTHERS … RESPONDENT(S)
JUDGMENT
S.V.N. BHATTI, J.
1. The Appeal arises from the Order dated 06.01.2012 in MASC No. 4237
of 2008 in the High Court of Judicature at Allahabad at Lucknow Bench.
2. The Writ Petitioner is the Appellant. Before the High Court, the
Appellant assailed the Order dated 27.06.2008 passed by the Electricity
Ombudsman in Appeal No. (28/2008) 81 of 2008 and, through a Writ of
Certiorari, sought the quashing of Clause 8 of the U.P. Electricity Regulatory
Commission (Consumer Grievance Redressal Forum and Electricity
Ombudsman) Regulations, 2007 (“Regulation, 2007”) as ultra vires Sections
42(5) and 42(6) of the Electricity Act, 2003 (“Act, 2003”).
3.
Signature Not Verified
The Appellant is the Distribution Licensee. The Respondent No. 3 is the
Digitally signed by
SNEHA DAS
Date: 2026.09.10
Reason: Appellant’s consumer. A few circumstances relevant to the disposal of the
18:30:40 IST
Appeal are as follows.
1
4. The Respondent No. 3 applied for an electricity connection with a 4000
KVA load. Due to contemporaneous limitations, the Appellant agreed to
sanction and release a 2000 KVA load. This led to the execution of an
Agreement dated 24.02.1997 between the Appellant and Respondent No. 3.
According to the Appellant, owing to improved power generation, the
Appellant was in a position to supply the balance 2000 KVA of power applied
for by Respondent No. 3. On 31.01.1998, the Appellant offered to increase the
contract load from 2000 KVA to another 2000 KVA, subject to the Respondent
No. 3 entering into an agreement with the Appellant. In a letter dated
14.09.1998, Respondent No. 3 expressed its lack of interest in accepting the
additional supply load communicated by the Appellant.
5. The above events occurred before the enactment of the Act, 2003. On
13.02.2007, the Appellant demanded Rs.57,74,164/- towards the Minimum
Consumption Guarantee Charges (“MCGC”) for the period from February,
1998 to September, 1998, with respect to the additional 2000 KVA offered to
be supplied by the Appellant. The Appellant assumes that, despite being ready
to supply the additional load of 2000 KVA, Respondent No.3 was not prepared
to avail it, and therefore, the contracted capacity for the period would be 4000
KVA, and hence, Respondent No.3 is under an obligation to pay MCGC.
5.1 Under Section 181(2)(r) and (s) of the Act, 2003, the U.P. Electricity
Regulatory Commission (“UPERC”) promulgated the Regulations, 2007. It is
pertinent here to refer to a few Sections of the Act, 2003, viz., Section 42(5),
which refers to Redressal before the Forum; Section 42(6), which refers to the
remedy before the Ombudsman, and Section 56(2), which stipulates the
2
period of limitation for raising the bills towards consumption and incidental
charges by the Appellant.
6. On 13.02.2007, the Appellant raised a demand of Rs.57,74,164/-
(Rupees Fifty Seven Lakhs Seventy Four Thousand One Hundred Sixty Four)
from Respondent No. 3 towards MCGC, which Respondent No.3 contested
before the Authorities under the Regulations, 2007. Those decisions
ultimately led to the filing of the present Civil Appeal in this Court.
7. Respondent No. 3 first approached the Consumer Grievance Redressal
Forum (“CGRF”) to challenge the demand dated 13.02.2007. It is a matter of
record that the CGRF rendered a split verdict and, for all purposes, did not
redress the consumer’s grievance in respect of the demand dated 13.02.2007.
Respondent No. 3 filed a Representation or Appeal before the Electricity
Ombudsman under Regulation 8.1 of the Regulations, 2007. The Electricity
Ombudsman set aside the demand dated 13.02.2007, and the Ombudsman’s
primary finding was that Respondent No. 3 did not consent to the additional
load offered by letter dated 31.01.1998. There is nothing on record to show
that the Appellant has released the additional 2000 KVA to Respondent No.
3. The demand dated 13.02.2007 is barred by the limitation prescribed under
Section 56(2) of the Act, 2003. The Electricity Ombudsman directed the
adjustment of the amounts deposited pursuant to the demand dated
13.02.2007 against future consumption bills of Respondent No. 3. The
Appellant, assailing the decision of the Electricity Ombudsman, filed a Writ
Petition being numbered as Misc. Single No. 4237 of 2008 before the High
Court.
3
8. The impugned Judgment, in addressing the challenge to Clause 8 as
ultra vires or illegal, held that any decision not favouring the consumer results
in ‘non-redressal of grievance of Consumer’. Section 42(6) of the Act, 2003
allows only a ‘Consumer’ to seek redressal from the Electricity Ombudsman.
If a grievance is redressed, the Distribution Licensee has no remedy under
sub-section (6). The UPERC has no authority under the said provision to
provide a remedy of representation to the Distribution Licensee. To this
extent, Clauses 8.1 and 8.2 of the Regulations, 2007, are ultra vires and
inconsistent with Section 42(6) of the Act, 2003.
8.1 It was held that the bill dated 13.02.2007 was issued after the Act, 2003
took effect. Therefore, the demand ought to have been made under Section
56(2) of the Act, 2003. The reasoning on the limitation period is that, in 1998,
if the consumer had to pay minimum charges, a bill should have been sent
before the completion of another billing cycle. A monthly bill was issued for
consumption under the Agreement dated 24.02.1997. However, no bill was
issued for the additional 2000 KVA along with the regular bills. The amount
fell due when the supplier was entitled to raise the bill. The word ‘due’ must
be read as referring to a specific point in time, not as something uncertain.
Also, no material or pleading shows that the sum has been continuously
treated as recoverable as arrears from Respondent No. 3. Hence, the demand
raised under the bill is barred by limitation. Further, the demand is barred
even under the Limitation Act, 1963, because, at best, the limitation period
could have been three years. In respect of the erstwhile UPSEB, the U.P.
Government Electrical Undertaking (Dues Recovery) Act, 1958, provided
separate provisions, and Section 5-A prescribed a limitation period of six years
4
for filing a Suit. Even if applied, the demand raised for the first time on
13.02.2007 for an event covered by the period February 1998 to September
1998 is barred by limitation.
8.2 The finding of fact recorded regarding the Agreement dated 24.02.1997
is that, although the Agreement was executed on 24.02.1997 for an additional
load of 2000 KVA, the Appellant was not in a state of readiness due to the
non-availability of electricity. The Agreement stipulated that the supplier
would arrange an additional 2000 KVA load within six months. After almost
nine months, on 31.01.1998, the Appellant claims to have sent a letter to
Respondent No. 3 stating that an additional 2000 KVA load was available. The
Consumer was required to convey his consent to release the additional load.
The Consumer’s liability arises only when the agreed quantum of electricity is
released to him, and not before. The Appellant does not contend that any
consent or acceptance was conveyed by the Consumer, or that the additional
load of 2000 KVA was released to him. Therefore, the Writ Petition was
dismissed.
9. Hence, the Civil Appeal.
10. Mr. Rakesh Uttamchandra Upadhyay, learned Advocate on Record
appearing for the Appellant, has not seriously pressed the challenge to
Regulation 8 of the 2007 Regulations. Even otherwise, we have perused the
finding recorded by the High Court, which limited the rejection of the
challenge. Therefore, we are not re-examining the view taken by the impugned
Judgment. The learned Counsel has fairly stated before us a few other
ancillary arguments available to the Appellant on regulations, etc., and that
5
such arguments are watered down by the view taken by this Court in K C
Ninan v. Kerala State Electricity Board & Ors.1 The above considerations lead
us to the legality of the demand dated 13.02.2007 and to whether it conforms
to the period of limitation stipulated under Section 56(2) of the Act, 2003. This
Court has covered the said issue in Assistant Engineer (D1), Ajmer Vidyut
Vitran Nigam Limited and Another v. Rahamatullah Khan Alias Rahamjulla2.
All the relevant paragraphs are excerpted hereunder:
“6.9. The liability to pay arises on the consumption of
electricity. The obligation to pay would arise when the bill is
issued by the licensee company, quantifying the charges to
be paid. Electricity charges would become “first due” only
after the bill is issued to the consumer, even though the
liability to pay may arise on the consumption of electricity.
XXX
7. The next issue is as to whether the period of limitation of
two years provided by Section 56(2) of the Act, would be
applicable to an additional or supplementary demand.
7.4. Sub-section (1) of Section 56 confers a statutory right to
the licensee company to disconnect the supply of electricity,
if the consumer neglects to pay the electricity dues. This
statutory right is subject to the period of limitation of two
years provided by sub-section (2) of Section 56 of the Act.
7.5. The period of limitation of two years would commence
from the date on which the electricity charges became “first
due” under sub-section (2) of Section 56. This provision
restricts the right of the licensee company to disconnect
electricity supply due to non-payment of dues by the
consumer, unless such sum has been shown continuously to
be recoverable as arrears of electricity supplied, in the bills
raised for the past period. If the licensee company were to be
allowed to disconnect electricity supply after the expiry of the
limitation period of two years after the sum became “first
due”, it would defeat the object of Section 56(2).
8. Section 56(2), however, does not preclude the licensee
company from raising a supplementary demand after the
expiry of the limitation period of two years. It only restricts
the right of the licensee to disconnect electricity supply due to
non-payment of dues after the period of limitation of two
years has expired, nor does it restrict other modes of recovery
which may be initiated by the licensee company for recovery
of a supplementary demand.”
1 2023 INSC 560.
2 (2020) 4 SCC 650.
6
11. The above view disentitles the Appellant from raising the demand under
Section 56(2) of the Act, 2003. For the above reasons and discussion, the
Appeal fails and is dismissed.
12. Pending Application(s), if any, shall be disposed of accordingly.
..……….…………………J.
[S.V.N. BHATTI]
……………………………J.
[N. V. ANJARIA]
New Delhi;
September 10, 2026.
7