2026 INSC 1072

Awadhesh Singh Gautam (M/s) v. State of Chhattisgarh

Neutral Citation
2026 INSC 1072
Date
30.09.2026
Year
2026
Source in the index
sci.gov.in neutral-citation

Full text

2026 INSC 1072 NON-REPORTABLE
IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION

CIVIL APPEAL NO. OF 2026
(@ S.L.P. (C) No. 10464 of 2026)

M/S AWADHESH SINGH GAUTAM … APPELLANT
Vs.
STATE OF CHHATTISGARH & ORS. … RESPONDENTS
WITH
CIVIL APPEAL NO. OF 2026
(S.L.P. (C) No. 12766 of 2026)

AND
CIVIL APPEAL NO. OF 2026
(@ S.L.P. (C) No. 12346 of 2026)

JUDGMENT

ALOK ARADHE, J.

1. Leave granted.

2. These three appeals arise out of three orders, each dated

07.01.2026, passed by the High Court1, whereby three writ

petitions instituted by M/s Awadhesh Singh Gautam, a

partnership firm (“the appellant”), were dismissed. Since the

three orders are, in substance, identical and the appeals turn
Signature Not Verified

Digitally signed by
KAPIL TANDON
Date: 2026.09.30
17:41:28 IST
upon a common question arising from a common factual
Reason:

1
High Court of Chhattisgarh at Bilaspur

1

matrix, they were heard together and are disposed of by this

common judgment.

THE FACTUAL MATRIX

3. The controversy has its genesis in three works awarded to the

appellant. Pursuant to notices inviting tenders issued by the

Chhattisgarh Rural Road Development Agency (“CGRRDA”), the

appellant was awarded three packages under the Pradhan

Mantri Gram Sadak Yojana (“PMGSY”), for which work orders

came to be issued on 01.09.2023 and 05.11.2024 (“the

subsequent works”).

4. Having executed approximately 40% of the work under each of

the subsequent works, the appellant raised running bills

aggregating Rs.39,78,500/- (Rupees Thirty-Nine Lakh Seventy-

Eight Thousand Five Hundred only), Rs.45,62,000/- (Rupees

Forty-Five Lakh Sixty-Two Thousand only) and Rs.23,55,000/-

(Rupees Twenty-Three Lakh Fifty-Five Thousand only)

respectively. Reminders followed on 22.09.2025 and

25.09.2025, but the amounts billed remained unreleased.

5. The appellant had earlier, on 03.01.2023, been awarded two

separate contracts for construction of two roads at 10.10%

above the Schedule of Rates, at an approved cost of

2

approximately Rs.437.43 lakhs (“the earlier works”), under

which a substantial part of the contract value had already been

paid.

6. Complaints of irregularity in execution of the earlier works led

the Collector, South Bastar, Dantewada, to constitute a five-

member committee. The committee, by its report dated

09.01.2024, found that although Rs.3,55,82,055/- (Rupees

Three Crore Fifty-Five Lakh Eighty-Two Thousand Fifty Five

only) had been paid to the appellant, the value of work actually

executed was only about Rs.1,54,75,938/- (Rupees One Crore

Fifty-Four Lakh Seventy-Five Thousand Nine Hundred Thirty-

Eight only), disclosing an excess payment of Rs.2,01,06,117/-

(Rupees Two Crore One Lakh Six Thousand One Hundred

Seventeen only). It recommended recovery of the said sum,

blacklisting of the appellant, a probe into its other works, and

departmental action against the concerned officers of the

CGRRDA.

7. Acting on this report, the Collector, by memo dated 03.06.2024,

directed the Tehsildar to recover Rs.2,01,06,117/- (Rupees Two

Crore One Lakh Six Thousand One Hundred Seventeen only)

from the appellant. The Tehsildar accordingly registered a

3

revenue case and issued a demand note dated 16.12.2024

under Section 146 of the Chhattisgarh Land Revenue Code,

1959, calling upon the appellant to pay the amount within ten

days.

8. The demand note was assailed in a writ petition. By order dated

05.03.2025, the High Court quashed it for want of notice or

hearing to the appellant, being violative of natural justice, while

reserving liberty to the respondents to act upon the committee’s

report afresh, in accordance with law and after complying with

the principles of natural justice.

9. In the meanwhile, upon a complaint by an Assistant Engineer

of CGRRDA, a First Information Report came to be registered

against Mr. Awadhesh Singh Gautam, partner of the appellant

firm, and officers of CGRRDA, for offences under Sections 420,

467, 468, 471, 409 and 120-B of the Indian Penal Code, 1860.

A chargesheet was filed on 30.12.2025 upon completion of

investigation.

10. Independently of the criminal proceedings, and drawing upon

the inspection report of the District Level Investigation Team

dated 18.12.2024, the reinspection report of the Departmental

Supervising Engineer dated 28.10.2024, and a final re-

4

evaluation undertaken by the Departmental Sub-Engineer, the

Executive Engineer-cum-Member Secretary, Project

Implementation Unit K-01 (“the Executive Engineer”), passed

an order dated 27.09.2025 (“the recovery order”). By this order,

a sum of Rs.84,17,003/- (Rupees Eighty-Four Lakh Seventeen

Thousand and Three only) was blocked out of amounts

currently payable to the appellant, to be recovered by deduction

from the three subsequent works in the sums of Rs.28,00,000/-

(Rupees Twenty Eight Lakh only), Rs.38,00,000/- (Rupees

Thirty Eight Lakh only) and Rs.18,17,003/- (Rupees Eighteen

Lakh Seventeen Thousand and Three only) respectively.

11. The appellant’s representation dated 09.10.2025 to the

Executive Engineer, pointing out that the deductions were

being made from bills payable under contracts wholly distinct

from the earlier works out of which the alleged liability arose,

and seeking a refund of Rs.84,17,003/- (Rupees Eighty-Four

Lakh Seventeen Thousand and Three only) within fifteen days,

elicited no response.

12. Three writ petitions came to be filed assailing the recovery order

and seeking release of the amounts deducted. By the impugned

common order dated 07.01.2026, the High Court held that the

5

relief claimed was contingent upon adjudication of disputed

questions of fact, which could not be undertaken in proceedings

under Article 226 of the Constitution, and dismissed the writ

petitions, reserving liberty to the appellant to pursue such

alternate remedy as may be available in law.

13. It is in this backdrop that these appeals fall for our

consideration.

RIVAL SUBMISSIONS

14. Mr. Gaurav Agrawal, learned senior counsel for the appellant,

submitted that the recovery order was passed without notice or

opportunity of hearing, in violation of Clause 4.1 of the Special

Conditions of Contract contained in the Standard Bidding

Document (“SBD”), which alone contemplates recovery

consequent upon technical audit and that too after hearing the

contractor. It was urged that appropriation of amounts payable

under one contract towards a liability alleged to arise under an

altogether different contract is impermissible, and that Clauses

43 and 53, dealing respectively with security deposit and

payment upon termination, have no bearing on the recovery in

question. It was highlighted that a sum of Rs.1,07,02,594/-

(Rupees One Crore Seven Lakh Two Thousand Five Hundred

6

Ninety-Four only) remained payable to the appellant under the

very earlier works out of which the alleged liability is said to

arise, yet the respondents chose to recover from three

unconnected and ongoing contracts instead. Reliance was

placed on a decision of this Court2.

15. Mr. Bishwajit Dubey, learned Additional Advocate General for

the State, submitted that the power of cross-contract recovery

flows expressly from the contract. Reliance was placed on

Clause 7(iv) of the Pre-Contract Integrity Pact and Clause 38 of

the Conditions of Contract, both of which, it was submitted,

permit recovery of dues under one contract from sums payable

under another, and on Clauses 44.1 and 53.1(ii) of the General

Conditions of Contract in the SBD. It was submitted that the

allegation against the appellant is not a mere billing

discrepancy but one of manipulation of measurement books to

draw excess payments from public funds, that a contractual

set-off founded on agreement is enforceable on that basis alone,

and that the appellant cannot claim the benefit of the contract

while disowning the burden it places upon it. Reliance in

2 ABL International Ltd. & Anr. v. Export Credit Guarantee Corporation of India Ltd.

& Ors., (2004) 3 SCC 553, paras 26-28

7

support of these submissions was placed on the decisions of

this Court3.

16. We have heard learned counsel for the parties and perused the

record.

POINTS FOR DETERMINATION

17. The following questions arise for determination in these

appeals:

(i) Whether the recovery order dated 27.09.2025 is

traceable to the contractual clauses relied upon by the

respondents?

(ii) Whether, even if so traceable, it satisfies the conditions

that such a clause prescribes and whether the recovery

order has been passed in violation of principles of

natural justice?

(i) WHETHER THE IMPUGNED RECOVERY IS TRACEABLE TO
THE CONTRACT?

18. We deal with the clauses of the General Conditions of Contract,

the Special Conditions of Contract, the Pre-Contract Integrity

3 Caretel Infotech Ltd. v. Hindustan Petroleum Corporation Limited (HPCL) & Ors.,

(2019) 14 SCC 81, para 24; Bharti Airtel Ltd. & Anr. v. Vijaykumar V. Iyer & Ors.,
(2024) 4 SCC 668, paras 15-19; State of Gujarat & Anr. v. Amber Builders, (2020) 2
SCC 540, paras 20-21; H.M. Kamaluddin Ansari and Co. v. Union of India & Ors.,
(1983) 4 SCC 417, paras 29 and 31; Nabha Power Limited (NPL) v. Punjab State Power
Corporation Limited (PSPCL) & Anr., (2018) 11 SCC 508, para 72 and Union of India
& Ors. v. N. Murugesan & Ors., (2022) 2 SCC 25, para 26

8

Pact, and the Conditions of Contract on which the respondents

have placed reliance, to examine whether the recovery order can

be justified by reference to any of them.

19. Clause 44.1 of the General Conditions of Contract in the SBD

reads thus:

“44.1 In the event of failure on part of the
Contractor to achieve timely completion of
the project, including any extension of time
granted under Clause 27, he shall, without
prejudice to any other right or remedy
available under the law to the Employer on
account of such breach, pay as agreed
liquidated damages to the Employer and not
by way of penalty in a sum calculated at the
rate per week or part thereof as stated in the
Contract Data. For the period that the
Completion Date is later than the Intended
Completion Date, liquidated damages at the
same rate shall be withheld if the
Contractors fails to achieve the milestones
prescribed in the Contract Data. However, in
case the Contractor achieved the next
milestone, the amount of the liquidated
damages already withheld shall be restored
to the Contractor by adjustment in the
payment certificate. Both the Parties
expressly agree that the total amount of
liquidated damages shall not exceed 10%
(ten percent) of Initial Contract Price and
that the liquidated damages payable by the
Contractor are mutually agreed genuine pre-
estimated loss and without any proof of
actual damage likely to be suffered and
incurred by the Employer; and the Employer
is entitled to receive the same and are not by
way of penalty.

9

The Employer may, without prejudice to any
other method of recovery, deduct the amount
of such damages from any sum due, or to
become due to the Contractor or from
Performance Security or any other dues from
Government or semi Government bodies
within the state.
The payment or deduction of such damages
shall not relieve the Contractor from his
obligations to complete the Works, or from
any other of his duties, obligations or
responsibilities under the Contract.
The Contractor shall use and continue to use
his best endeavours to avoid or reduce
further delay to the Works, or any relevant
Stages.”
19.1 On a plain reading, this clause is confined to liquidated

damages for delay in achieving completion or contractual

milestones, capped at ten per cent of the initial contract price.

The recovery order has never been founded on a claim,

quantified or otherwise, for liquidated damages for delay; it

proceeds instead from an allegation of overpayment detected on

technical audit, a subject dealt with specifically, and

exclusively, by Clause 4.1 of the Special Conditions of Contract.

Clause 44.1, therefore, furnishes no foundation for the recovery

order.

20. We next consider Clause 53.1(ii) of the General Conditions of

Contract, which reads:

10

“53.1(ii) If the Contract is terminated
because of a fundamental breach of contract
by the Contractor due to non compliance of
the requirements of clause 32 of GCC
regarding defects liability period and routine
maintenance of roads for five years, the
Engineer will assess the cost of having the
defect corrected. If the total amount due to
the Employer exceeds any payment due to
the Contractor, the difference shall be
recovered from the Security Deposit and
Performance Security. If any amount is still
left un-recovered, it will be recovered from
any dues payable to the Contractor from
State PMGSY works, any other State
Government works including State Public
Sector works executed by the Contractor. If
any amount still remains unrecovered, it
shall be recovered as arrears of land
revenue. ”
20.1 This clause is attracted only where a contract is terminated for

the contractor’s fundamental breach of its defects-liability and

five-year maintenance obligations under Clause 32, and only to

the extent the assessed cost of rectification exceeds what can

be recovered from the security deposit and performance

security of that very contract; recourse to dues under other

State works follows only in that residual contingency. There is

nothing on record to show that either the earlier works or the

subsequent works were ever terminated, still less terminated on

the ground of breach of defects-liability or maintenance

obligations under Clause 32. The recovery here rests on an

11

allegation of manipulation of measurement books during

execution, a ground altogether distinct from post-completion

default in defect-liability maintenance. Clause 53.1(ii) is thus

not attracted, and the cross-contract mechanism it contains

cannot be pressed into service to sustain the recovery order.

21. Clause 7(iv) of the Integrity Pact, described as a sanction for its

violation, reads as follows:

“7. SANCTIONS FOR VIOLATIONS
7(iv) To recover all sums already paid by the
BUYER, and in case of the Indian BIDDER
with interest thereon at 2% higher than the
prevailing Prime Lending Rate. While in case
of a BIDDER from a country other than India
with interest thereon at 2% higher than the
LIBOR. If any outstanding payment is due to
the BIDDER from the BUYER in connection
with any other contract such outstanding
payment could also be utilized to recover the
aforesaid sum and interest.”
21.1 This clause does contemplate recovery, with interest, from dues

payable under any other contract; but its invocation necessarily

presupposes a prior determination, arrived at through whatever

process the pact itself prescribes, that the bidder has in fact

violated the pact in relation to the contract in question. The

recovery order neither refers to the Integrity Pact nor records any

finding that it stands violated. It cannot, therefore, be said that

12

the recovery has in fact been made under Clause 7(iv) of the

Integrity Pact.

22. Clause 38 of the Conditions of Contract, reads as follows:

“CONDITIONS FOR CONTRACT

Clause 38- On the breach of any term or
condition of this contract by the contractor
the said Governor shall be entitled to forfeit
the Security deposit or the balance thereof
that may at the time be remaining, and to
realise and retain the same as damages and
compensation for the said breach but
without prejudice to the right of the
Governor to recover further sums as
damages from any sums due or which may
become due to the contractor by Government
or otherwise howsoever.”
22.1 The language of Clause 38 is undoubtedly wide enough, once

validly invoked, to permit recovery of sums payable under other

contracts. But its invocation is conditional upon breach of a term

or condition of the contract being first ascertained, and upon

forfeiture being effected as damages and compensation for that

breach; this in turn obliges the Government to ascertain the

breach and to apprise the contractor of it, so that he may meet

the allegation. The recovery order records no finding of breach,

and no notice preceded it. The action in question cannot,

therefore, be said to have been taken under Clause 38.

13

23. This brings us to Clause 4.1 of the Special Conditions of

Contract, which alone answers the description of what the

respondents purported to do, namely, a technical audit of the

earlier works resulting in a finding of overpayment and

consequential recovery. It reads:

4.1 Technical Examination
“The Government / CGRRDA /C.E. /C.E.O
/S.E./ Engineer-in-charge shall have the
right to cause Audit and Technical Examina-
tion of the works and the final bills of the
contractors including all supporting vouch-
ers, abstracts etc., to be made as per pay-
ments of the final bills and if as a result of
such Audit & Technical Examination any
sum found to have been overpaid in respect
of any work done by the contractor under the
contract or any work claimed by him to have
been done under the contract and found not
to have been executed, the contractor shall
be liable to refund the amount of over pay-
ment and it shall be lawful for the Govern-
ment of Chhattisgarh /CGRRDA/ Engineer-
in-charge to recover the same from the secu-
rity deposit of the contractor or from any
dues payable to the contractor from the En-
gineer-in-Charge account. If it is found that
the contractor was paid lesser than what
was due to him under the contract in respect
any work executed by him under it, the
amount of such under payment shall be duly
paid by the Engineer-in-Charge to the con-
tractor.
In the case of any audit examination and re-
covery consequent on the same the contrac-
tor shall be given an opportunity to explain

14

his case and decision of the government/em-
ployer shall be final binding and conclusive.
In the case of Technical Audit, consequent
on which there is a recovery from the con-
tractor, no recovery should be made without
orders of CEO, CGRRDA whose decision
shall be final. All action under this clause
should be initiated and intimated to the con-
tractor within a period of twelve months from
the date of completion.”

23.1 This clause permits recovery from the security deposit of the

contractor, or from dues payable to the contractor, from the

account pertaining to the very work audited, that is, the earlier

works. It is not in dispute that a sum of about Rs.1.07 crore

remained due to the appellant under the earlier works

themselves, yet the respondents took no step to appropriate that

amount; they chose instead to recover from three unconnected

and ongoing packages. Clause 4.1 further makes it obligatory

that the contractor be given an opportunity to explain his case

before any recovery consequent on audit, and mandates that “no

recovery should be made without orders of CEO, CGRRDA whose

decision shall be final”. It is common ground that no such

opportunity was afforded, and the recovery order, issued by the

Executive Engineer alone, does not disclose that the approval of

the Chief Executive Officer, CGRRDA, was ever obtained. The

clause additionally requires that action be initiated and

15

intimated to the contractor within twelve months of completion

of the audited work, and no material has been placed before us

to establish the date of completion of the earlier works. Clause

4.1, therefore, also cannot sustain the recovery order.

24. It follows that none of the clauses relied upon by the

respondents, whether read singly or cumulatively, authorises

either the deduction of the disputed amount from the three

subsequent contracts, or the manner in which it was effected.

(ii) WHETHER THE RECOVERY ORDER SATISFIES THE
CONDITIONS THAT THE CLAUSE PRESCRIBES AND
WHETHER THE RECOVERY ORDER HAS BEEN PASSED IN
VIOLATION OF PRINCIPLES OF NATURAL JUSTICE?

25. We are not unmindful that the allegations against the appellant

in respect of the earlier works are of a serious character and are

already the subject of departmental inquiry and of criminal

proceedings arising out of Chargesheet No. 87 of 2025; nothing

said in this judgment touches upon their merits. That, however,

does not answer the second question framed above, namely,

whether the manner of recovery satisfies the conditions Clause

4.1 itself prescribes. Clause 4.1 incorporates within itself,

certain principles of natural justice. As already noticed, the

recovery order was passed without notice, consent and sanction,

16

and no other clause, nor any provision of law, permits the

amount said to be due under the earlier works to be adjusted

against sums payable under a separate and subsisting contract

without the contractor’s consent. Until the alleged overpayment

is established in accordance with law, it remains, a disputed and

unadjudicated claim for damages and not a debt presently due4;

and a party to a contract cannot, merely because it also holds

amounts otherwise payable under it, treat such a claim as

though it were an ascertained debt and appropriate those

amounts in satisfaction of it. Therefore, the recovery effected by

the recovery order was not only in contravention of the

conditions prescribed in the clause but also in flagrant violation

of principles of natural justice.

26. The High Court fell into error on the ground that the relief

claimed was contingent upon resolution of disputed questions of

fact touching the earlier works, which could not be gone into

under Article 226 of the Constitution. The question before it was

whether the respondent-State was justified in appropriating that

very disputed amount from money admittedly payable to the

4 Union of India v. Raman Iron Foundry, (1974) 2 SCC 231

17

appellant under the three subsequent contracts, contracts that

have nothing to do with the earlier works.

27. For the reasons set out above, neither the agreement governing

the contracts consented to by the contractor nor any provision

of law permits such appropriation, and that question turns

entirely on the construction of the contract and compliance with

its terms, not on the resolution of the disputed facts pertaining

to the earlier works.

CONCLUSION AND DIRECTIONS

28. For the foregoing reasons, the recovery order dated 27.09.2025

cannot be sustained in law and is quashed and set aside. The

respondents are directed to release to the appellant the sum of

Rs.84,17,003/- (Rupees Eighty-Four Lakh Seventeen Thousand

and Three only), together with interest thereon at the rate of 6%

per annum from 27.09.2025 till the date of actual payment.

29. We clarify that this judgment shall not preclude the respondents

from taking recourse to appropriate proceedings, in accordance

with law, for recovery of any amount that may ultimately be

found due from the appellant in respect of the earlier works. We

further clarify that the observations contained in this judgment

18

are confined to the legality of the manner in which the impugned

recovery was effected, and shall have no bearing on: (a) the

pending criminal proceedings arising out of Chargesheet No. 87

of 2025; or (b) the correctness or quantum of the alleged

overpayment in respect of the earlier works, both of which shall

be examined and decided independently and strictly on their own

merits.

30. The appeals are allowed in the above terms. There shall be no

order as to costs.

31. Pending application(s), if any, shall stand disposed of.

………………………………………………..J.
[PAMIDIGHANTAM SRI NARASIMHA]

………………………………………………..J.
[ALOK ARADHE]

NEW DELHI;
SEPTEMBER 30, 2026.