IN THE SUPREME COURT OF INDIA

CIVIL ORIGINAL JURISDICTION

ORIGINAL SUIT NO.5 OF 2003

STATE OF ANDHRA PRADESH Plaintiff

VERSUS

STATE OF KARNATAKA & ANR. Defendants

O R D E R

The instant Suit was filed in the year 2003 praying for

following reliefs:

“1. grant injunction restraining Defendant No.1 State
of Karnataka from constructing the Paragodu
Project on the Chitravathi river in Pennar basin
and impounding water therein, till resolution of
the water disputes under the provisions of the
Inter-State River Water Disputes Act, 1956.

2. grant injunction restraining Defendant No.1 State
of Karnataka from constructing, executing,
implementing, giving effect to or impounding
water, till resolution of the water disputes
under the provisions of the Inter-State River
Water Disputes Act, 1956, in the anicut across
Pennar river near Gowribidnur Village, Teeta
Project in Tumkur District, the Tank at
Pasalaparthi village of Bagepalli taluk, Kolar
District, the Nagarkare tank in Gowribidnur
village, the new tank near Muddalodu village in
Gowribidnur taluk, Karivenahalli tank in Pavagada
Signature Not Verified
taluk, several new Irrigation tanks in Papagni
Digitally signed by
BABITA PANDEY
Date: 2022.10.01
basin around Baddipalli village of Kolar
District, the tank across Katnakallu Vanka near
13:51:33 IST
Reason:

M. Gollahalli Village in Gowribidnur taluk of
Kolar District, diversion anicut to feed
Cholasettihalli tank near Cholasettihalli village

2

in Gowribidnur taluk of Kolar District, the new
tank near Jalagondanahalli village in Kolar
District and Nagalamadaka anicut in Tumkur
district.

3. direct Defendant No.2 Government of India to
forthwith take action, in accordance with the
Inter State River Water Disputes Act, 1956, for
settlement/adjudication of disputes, between the
Plaintiff State of Andhra Pradesh and Defendant
No.1 State of Karnataka.

4. pass such further decree or decrees or order or
orders as this Hon’ble Court may deem fit and
proper in the facts and circumstances of the
case, and

5. award costs of these proceedings in faovur of the
plaintiff and against the defendant No.1.”

The plaintiff State also prayed for interim relief as

follows:

“Pending hearing and final disposal of the Suit, the
Defendant No.1 State of Karnataka be restrained by an
order of ad-interim injunction of this Hon’ble Court
form;

a. constructing the Paragodu Project on the
Chitravathi river in Pennar basin and impounding
water therein, till resolution of the water
disputes under the provisions of the Inter-State
River Water Disputes Act, 1956.

b. from constructing, executing, implementing,
giving effect to or impounding water, till
resolution of the water disputes under the
provisions of the Inter-State River Water
Disputes Act, 1956, in the anicus across Pennar
river near Gowribidnur Village, Teeta Project in
Tumkur District, the Tank at Pasalaparthi village
of Bagepalli taluk, Kolar District, on the
Nagarkare tank in Gowribidnur village, the new
tank near Muddalodu village in Gowribidnur taluk,
Karivenahalli tank in Pavagada taluk, several new
Irrigation tanks in Papagni basin around

3

Baddipalli village of Kolar District, the tank
across Katnakallu Vanka near M. Gollahalli
Village in Gowribidnur taluk of Kolar District,
diversion anicut to feed Cholasettihalli tank
near Cholasettihalli village in Gowribidnur taluk
of Kolar District, the new tank near
Jalagondanahalli village in Kolar District and
Nagalamadaka anicut in Tumkur district.”

It is a matter of record that appropriate request for

constituting an Inter-State River Water Disputes Tribunal to

go into the issues has not yet been made by the plaintiff

State. However, the matter has been engaging attention of this

Court principally on the issue of the interim relief to be

granted in the matter.

At this length of time, when 19 years have elapsed, it

will be extremely difficult to consider the matter purely from

the prospective of grant or non-grant of interim relief.

During the last 19 years, various developments, such as

augmentation of water from the concerned river for various

developmental activities including the need of the people in

the Basin, have taken place. At this juncture, the matter

therefore requires to be considered in the light of the

present day situation.

Having considered the entirety of the matter, in our

view, the proper course would be to relegate the plaintiff

State to take appropriate proceedings as are open to it in law

afresh, including approaching the Central Government for

4

constituting Inter-State River Water Disputes Tribunal or for

any other appropriate remedy.

We, therefore, dispose of this Suit giving liberty as

aforesaid to the plaintiff State.

At this stage, Mr. Mahfooz Ahsan Nazki, learned Advocate

appearing for the State brought to our notice that the parties

have exchanged pleadings and evidence was placed on record.

If said pleadings and the evidence are to be relied upon, the

plaintiff State may take appropriate steps in accordance with

law at any given stage.

The Original Suit is disposed of in aforesaid terms

leaving all questions of law open.

……………………….CJI.
(UDAY UMESH LALIT)

……………………….J.
(S. RAVINDRA BHAT)

……………………….J.
(J.B. PARDIWALA)
New Delhi,
September 28, 2022