2026 INSC 977

National Skill Development Corporation v. Surya Wires Private Limited

Neutral Citation
2026 INSC 977
Date
08.09.2026
Year
2026
Source in the index
sci.gov.in neutral-citation

Full text

2026 INSC 977 NON-REPORTABLE

IN THE SUPREME COURT OF INDIA
CIVIL APPELLATE JURISDICTION
CIVIL APPEAL NO. OF 2026
(@ S.L.P. (C) NO.10030 OF 2026)

NATIONAL SKILL DEVELOPMENT
CORPORATION … APPELLANT

VERSUS

SURYA WIRES PRIVATE LIMITED & ORS. … RESPONDENTS

JUDGMENT

ALOK ARADHE, J.

1. Leave granted.

2. The appeal raises a significant question for our

consideration, namely, whether, where parties structure a

single transaction through several interconnected

instruments, an arbitration clause contained in one

instrument can bind a party through another instrument,

expressly integrated with it but not itself containing an

arbitration clause?

3. This appeal is directed against the judgment dated
Signature Not Verified

Digitally signed by
KAPIL TANDON
28.01.2026 rendered by the High Court1 in an Appeal2 under
Date: 2026.09.08
19:19:39 IST
Reason:

1
High Court of Delhi
2
ARB. A. (COMM.) 11 of 2025.

1

Section 37(2)(a) of the Arbitration and Conciliation Act, 1996

(the ‘1996 Act’), whereby the High Court affirmed the order

dated 23.10.2024 passed by the Sole Arbitrator directing the

deletion of respondent nos. 2, 3, 5 and 7 from the array of

parties to the arbitral proceedings, on the finding that they

were non-signatories to the agreements in their personal

capacities. The scope of the present appeal is confined to the

correctness of the order insofar as it concerns respondent

no. 2.

FACTS

4. The facts shorn of unnecessary details, may be stated thus.

5. The Ministry of Skill Development and Entrepreneurship,

decided to establish Model Training Centres in every district

of the country, to be known as “Pradhan Mantri Kaushal

Kendra” (‘PMKK’). The appellant namely, National Skill

Development Corporation, a not-for-profit company that

extends financial assistance to companies and organisations

which provide skill training, was the implementing agency.

The appellant issued a ‘Request for Proposal’ dated

29.07.2016 inviting Technical and Financial proposals for

setting up of PMKK from eligible persons.

2

6. The respondent no. 1, namely, Surya Wires Private Limited

(the ‘Company’) and respondent no. 4, namely, Disha

Education Society (the ‘Society’) submitted the Technical and

Financial proposal to the appellant for its consideration for

the allotment of clusters/districts for jointly setting up

PMKKs. Accordingly, the appellant allotted districts to

respondent nos. 1 and 4 to jointly establish Model Training

Centres. The respondent no. 6 namely, Shanti Finance and

Property Development Private Limited (the ‘Finance

Company’) was the co-borrower providing mortgage security.

Respondent nos. 2 and 3 are the Managing Director/

Authorised Representative and Director respectively of the

Company. Respondent no. 5 is the Authorised

Representative of the Society and respondent no. 7 is

Authorised Representative of the Finance Company.

7. On 20.12.2016, the parties executed a cluster of

contemporaneous agreements: a Service Level Agreement

(SLA), a First Loan Agreement for a sum of Rs. 7,17,63,197/-

, (Rupees Seven Crores Seventeen Lakhs Sixty-Three

Thousand One Hundred Ninety-Seven only) and ancillary

“Facility Agreements”, namely, a Deed of Assignment, Deed

3

of Hypothecation, Irrevocable Power of Attorney,

Undertaking-cum-Declaration, and a Personal Guarantee by

respondent no. 2 in favour of the appellant which was

executed on 27.12.2016.

8. A second, materially identical set of agreements was

executed on 18.08.2017 for an additional loan of Rs.

2,13,83,194/- (Rupees Two Crores Thirteen Lakhs Eighty-

Three Thousand One Hundred Ninety-Four only) including a

second Personal Guarantee by respondent no. 2.

9. Subsequently, defaults occurred in the repayment of the

amounts due under the Loan Agreements which led to

issuance of Loan Recall Notices to the respondents on

29.10.2021. Respondent no. 2 was also served as he was a

signatory to the Personal Guarantees.

10. On 21.06.2022, the appellant initiated arbitral proceedings

before the Indian Council of Arbitration and filed its

Statement of Claim against respondent nos. 1 to 7 for

recovery of the amounts due under the two Loan

Agreements. Respondent nos. 2, 3, 5 and 7 filed an

application under Section 16 of the 1996 Act contending that

the Arbitral Tribunal lacked jurisdiction qua them, they not

4

being signatories to the Loan Agreements in their personal

capacities.

11. By order dated 23.10.2024, the Sole Arbitrator allowed the

application under Section 16 of the 1996 Act, holding that

respondent nos. 2, 3, 5 and 7, being directors and/or

authorized representatives of the borrower companies, are

not signatories to the Loan Agreements in the individual and

personal capacities and are, therefore, not liable to be

retained as parties to the Statement of Claim and

accordingly, their deletion from the array of parties was

directed.

12. Being aggrieved, the appellant carried the matter in appeal

under Section 37(2)(a) of the 1996 Act, confined to deletion

of respondent no. 2 from the array of parties. The High

Court, by the impugned judgment, held that admittedly the

Personal Guarantees dated 27.12.2016 and 18.08.2017

contained no arbitration clause of their own. It was further

held that a mere general reference to a document does not

automatically import an arbitration clause and there must

be conscious acceptance by the parties to make the

arbitration clause part of the secondary contract. It was also

5

held that the jurisdiction of the Arbitral Tribunal cannot be

founded on proximity of transactions or commercial linkage

between the instruments but must be traceable to an

express or validly incorporated arbitral undertaking by the

party sought to be bound. The High Court found that the

appellant failed to provide any material to show that

respondent no. 2 was the “alter ego” of the Company or had

used the corporate form to work fraud which is the high

threshold required to bind a non-signatory. The order of the

Sole Arbitrator was accordingly affirmed.

SUBMISSIONS

13. Mr. J.K. Chaudhary, learned counsel for the appellant,

submitted that a conjoint reading of Clause 11.2 of the Loan

Agreements, together with the definition clauses and

Schedules thereto demonstrates that the arbitration clause

stands incorporated into the Personal Guarantees. It was

further submitted that Personal Guarantees executed by

respondent no. 2 on 27.12.2016 and 18.08.2017 were not

independent or collateral instruments, but mandatory pre-

disbursement conditions under the Loan Agreements,

6

contractually defined as “Facility Agreements” and deemed

to form an integral and inseparable part thereof.

14. It was argued that the High Court fell into error in applying

Section 7(5) of the 1996 Act in an unduly technical and

restrictive manner, contrary to the settled position in law3. It

was urged that where a personal guarantee is expressly

rendered an integral part of the loan agreement, the

arbitration clause contained in the latter must be held to be

incorporated by reference under Section 7(5) of the 1996 Act.

It was also submitted that the addition of respondent no. 2

will not derail or delay the arbitration proceedings. In

support of the aforesaid submissions, reliance has been

placed on the decisions of this Court4.

15. Mr. Sudev Singh Juneja, learned counsel for respondent no.

2, submitted that, of the seven instruments executed

between the parties, only four contained arbitration clauses,

and that the arbitration clause in the loan agreements had,

at no stage, been incorporated into the Personal Guarantee.

It was urged that Clause 11.2 of the Loan Agreement

3
M.R. Engineers and Contractors Private Limited v. Som Datt Builders Limited, (2009) 7 SCC
696.
4
Inox Wind Limited v. Thermocables Limited, (2018) 2 SCC 519 and Cox and Kings v. SAP India
Pvt. Ltd., (2024) 4 SCC 1.

7

confines arbitration to disputes concerning that agreement,

and that the Loan Agreement separately contemplates

enforcement of securities and guarantees in terms of their

respective facility agreements. It was contended that the

instant case is a “two contract case”, involving distinct

parties and instruments not cast in a standard form, and

therefore, the reliance placed on the decision of this Court in

Inox Wind Limited (supra) is misplaced. Learned Counsel

did not dispute the fact that a non-signatory may, in

appropriate case, be bound by an arbitration clause where a

mutual intention to that effect is established, but submitted

that such intention must be gathered from the language

employed in the document and not presumed. In support of

the aforesaid submissions, reliance has been placed on the

decisions of this Court5 and a decision of the High Court of

England & Wales6.

16. We have considered the rival submissions advanced by the

learned counsel for the parties and have perused the record.

5
Industrial Finance Corporation of India Ltd. v. Cannanore Spinning and Weaving Mills Ltd.
and Others, (2002) 5 SCC 54; S.N. Prasad, Hitek Industries (Bihar) Ltd. v. Monnet Finance Ltd.
& Ors., (2011) 1 SCC 320; NBCC (India) Ltd. v. Zillion Infraprojects Pvt. Ltd., (2024) 7 SCC 174
and Adavya Projects Pvt. Ltd. v. Vishal Structures Pvt. Ltd., (2025) 9 SCC 686.
6
Habas Sinai Ve Tibbi Gazlar Isthisal Endustri AS v. Sometal SAL, [2010] EWHC 29 (Comm).

8

SCOPE AND AMBIT OF SECTION 7(5) OF THE 1996 ACT

17. Section 7(5) of the 1996 Act provides that a reference in a

contract to a document containing an arbitration clause

constitutes an arbitration agreement, provided that the

contract is in writing and the reference is such as to make

the arbitration clause part of the contract. A two-Judge

bench of this Court in M.R. Engineers (supra) after

adverting to the relevant passages from Russell on

Arbitration, 23rd Edition (2007) summarised the scope and

intendment of Section 7(5) of the 1996 Act as follows:

“24. The scope and intent of Section 7(5) of
the Act may therefore be summarised thus:
(i) An arbitration clause in another
document, would get incorporated into
a contract by reference, if the following
conditions are fulfilled:

(1) the contract should contain a
clear reference to the documents
containing arbitration clause,

(2) the reference to the other
document should clearly indicate
an intention to incorporate the
arbitration clause into the
contract,
(3) the arbitration clause should
be appropriate, that is capable of
application in respect of disputes
under the contract and should not

9

be repugnant to any term of the
contract.

(ii) When the parties enter into a
contract, making a general reference to
another contract, such general
reference would not have the effect of
incorporating the arbitration clause
from the referred document into the
contract between the parties. The
arbitration clause from another
contract can be incorporated into the
contract (where such reference is
made), only by a specific reference to
arbitration clause.

(iii) Where a contract between the
parties provides that the execution or
performance of that contract shall be in
terms of another contract (which
contains the terms and conditions
relating to performance and a provision
for settlement of disputes by
arbitration), then, the terms of the
referred contract in regard to execution
/performance alone will apply, and not
the arbitration agreement in the
referred contract, unless there is
special reference to the arbitration
clause also.

(iv) Where the contract provides that the
standard form of terms and conditions
of an independent trade or professional
institution (as for example the standard
terms and conditions of a trade
association or architects association)
will bind them or apply to the contract,
such standard form of terms and
conditions including any provision for
arbitration in such standard terms and
conditions, shall be deemed to be
10

incorporated by reference. Sometimes
the contract may also say that the
parties are familiar with those terms
and conditions or that the parties have
read and understood the said terms
and conditions.

(v) Where the contract between the
parties stipulates that the conditions of
contract of one of the parties to the
contract shall form a part of their
contract (as for example the general
conditions of contract of the
Government where the Government is a
party), the arbitration clause forming
part of such general conditions of
contract will apply to the contract
between the parties.”

18. Another two-Judge Bench of this Court in Inox Wind

Limited (supra) while reiterating the ratio laid down in M.R.

Engineers (supra), held that general reference to an earlier

contract does not suffice to incorporate an arbitration clause

into a later contract, whereas a general reference to a

standard form suffices for that purpose.

19. A three-Judge Bench of this Court7 reaffirmed that Section

7(5) of 1996 Act stands satisfied where the reference in a

contract to a document containing an arbitration clause is

7
Shinhan Bank v. Carol Info Services Limited, (2023) 20 SCC 388.

11

such as to make that arbitration clause a part of the

contract.

20. A Constitution Bench of this Court in Cox and Kings

Limited (supra) held that the definition of “parties” under

Section 2(1)(h) read with Section 7 of the 1996 Act includes

both the signatory as well as non-signatory parties; and

conduct of the non-signatory parties could be an indicator of

their consent to be bound by the arbitration agreement. The

Constitution Bench noted Article 4.3 of the UNIDROIT

Principles of International Commercial Contracts, 2016,

which provides that the subjective intention of the parties

could be ascertained by having regard to the following

circumstances: (a) preliminary negotiations between the

parties; (b) practices which the parties have established

between themselves; (c) the conduct of the parties

subsequent to the conclusion of the contract; (d) the nature

and purpose of the contract; (e) the meaning commonly given

to terms and expressions in the trade concerned; and (f)

usages. It was further held that the requirement of a written

arbitration agreement under Section 7 of the 1996 Act does

not exclude the possibility of binding non-signatory parties.

12

It was further held that in case of a composite transaction

involving multiple agreements, it would be incumbent for the

courts and tribunals to assess whether the agreements are

consequential or in the nature of a follow-up to, the principal

agreement.

21. A three-Judge Bench of this Court8, observed that the

intention of the parties to be bound by an arbitration

agreement can be gauged from the circumstances that

surround the participation of the non-signatory party in the

negotiation, performance and termination of the underlying

contract containing such an agreement.

22. Thereafter, a two-Judge Bench of this Court9, held that for

arbitration to remain a viable and effective alternative

mechanism for dispute resolution, it is imperative to ensure

that commercial reality does not outgrow this mechanism.

The mechanisms of arbitration must be sufficiently elastic to

accommodate the complexities of multi-party and multi-

contract arrangements without compromising foundational

principles such as consent and party autonomy. The

8
Ajay Madhusudan Patel and Others v. Jyotrindra S. Patel and Others, (2025) 2 SCC 147.
9
ASF Buildtech Private Limited v. Shapoorji Pallonji and Company Private Limited, (2025) 9
SCC 76.

13

approach of courts and Arbitral Tribunal in particular must

be responsive to the emerging commercial practices and

expectations of the parties who submit themselves to it.

ANALYSIS

23. In the backdrop of the aforesaid well-settled legal principles,

we advert to the facts of the case in hand.

24. It bears notice that respondent no. 2 executed the

instruments dated 20.12.2016 and 18.08.2017 in two

distinct capacities: first, as Managing Director of the

Company, in a representative capacity; and secondly, in his

personal and individual capacity, as guarantor under the

Personal Guarantees. It is in this context that relevant

extracts from clauses of the Loan Agreements fall for

consideration.

Article I Clause 1.1

Sub-clause (b)
“Agreement” shall refer to this Loan
Agreement including all the Schedules and
annexures attached with it.

Sub-clause (l)
“Facility Agreements/Facility Documents”
shall mean and include this Agreement,
Memorandum of Approval and all other
agreements, instruments, undertakings,
deeds and other documents executed or
entered into, or to be executed or entered

14

into by the Borrowers with the Lender in
connection with the Project as detailed in
Schedule IV.

Sub-clause (u)
“Schedule(s)” means the Schedule (s) to this
Agreement and which forms an integral part
of this Agreement.

Interpretation
Sub-clause (xi)-
In case of any inconsistency between any
provision of this Agreement and any other
Facility Documents the relevant provision of
this Agreement shall prevail.

Clause 11.2 Dispute Resolution
(i) All or any dispute, controversy, claim or
disagreement arising out of or touching
upon or in relation to the terms of this
Agreement or its termination, breach,
invalidity, including the interpretation and
validity thereof and the respective rights
and obligations of the Parties hereof that
cannot be amicably resolved by mutual
discussion within 30 (thirty) calendar days
shall be settled as per the provisions of the
Arbitration and Conciliation Act, 1996
which shall be final and binding arbitration.
The proceedings of the arbitration shall be
in accordance with the Rules of Arbitration
of the Indian Council of Arbitration (“ICA”)
which rules are deemed to be incorporated
by reference in this clause and the award
made in pursuance thereof shall be binding
on the parties.
Article XII-Miscellaneous
Clause 12.1

The schedules attached herewith along with
the Annexures and the Facility

15

Agreement(s) shall be deemed to be part of
this Agreement as if the provisions thereof
were set out herein in extension. Any
amendment(s), modification(s), revision(s)
to the Agreement, Facility Agreement(s),
Schedule(s), thereto and other document(s)
shall be in writing between the Parties
which shall form an integral part of this
Agreement without the need to enter into
any supplemental agreement.

Schedule I -Pre-Disbursement Conditions

1. Execution of the Loan Agreement and
other Facility Agreements, if any.

Schedule IV – Facility Agreements as
defined in Definitions Clause in Article I
would include any or all of the
underwritten:

a) Deed of Hypothecation
b) Irrevocable Power of Attorney
c) Personal Guarantee(s)
d) Deed of Assignment
e) Undertaking (s)
f) Memorandum of Entry
g) Deed of Declaration
h) Any other agreement as may be required
for the purpose of this PMKK

25. A conjoint and harmonious reading of the aforesaid clauses

admits of no doubt that the Personal Guarantees constitute

an integral and inseparable part of Loan Agreements. The

Personal Guarantees are expressly enumerated in Schedule

IV as included in the “Facility Agreements”, and sub-clauses

(b) and (u) of Clause 1.1 of Article I declare, in terms, that

16

the “Agreement” includes all Schedules annexed to it. Clause

12.1 of Article XII (Miscellaneous) goes further and stipulates

that facility agreements “shall be deemed to be part of this

agreement as if provisions thereof were set out herein in

extension”. The phrase “as if the provisions thereof were set

out herein in extension” operates as a deeming fiction

internal to the contract, binding every facility agreement,

including the Personal Guarantee, within the same legal and

arbitral framework as the Loan Agreement. The Personal

Guarantees do not, therefore, stand apart from the Loan

Agreements, and are woven into their very fabric.

26. This conclusion finds independent reinforcement in Clause

1 of Schedule I of the Loan Agreements which stipulates the

execution of the Loan Agreement and other facility

agreements as a pre-disbursement condition. The

contemporaneity of execution, with the Personal Guarantees

having been executed on 27.12.2016 and 18.08.2017, in

close proximity to the Loan Agreements dated 20.12.2016

and 18.08.2017 respectively, reinforces the inference that

the parties intended the entire cluster of documents to

constitute a single, composite transaction. Read together,

17

the definition clauses under Article I, Article XII and the

Schedules conclusively establish that the Loan Agreements

and Personal Guarantees were designed to operate not as

isolated or self-contained contracts, but as component parts

of one composite transaction governing a single commercial

arrangement.

27. The intention of the parties to incorporate the Personal

Guarantees into the Loan Agreements is, in these

circumstances, explicit, rather than a matter of inference.

28. The fact that respondent no. 2 did not append his signature

to the Loan Agreements in his personal capacity is not, in

the circumstances of this case, decisive. The Loan

Agreements were not instruments of an ordinary private

bargain, they were the means by which the appellant, a not-

for-profit company disbursed funds to training partners

such as the Company for establishment of Model Training

Centres. Training partners engaged under such a scheme

are frequently thinly capitalized special-purpose entities,

and it is for this reason that personal guarantees of the

individuals controlling them are exacted as a mandatory pre-

disbursement condition under Schedule I, the guarantee

18

being the real, and often the only, assurance that funds

disbursed for the public purpose of skill training will be

accounted for and, if necessary, recovered. Respondent no.

2 furnished precisely such a guarantee, contemporaneously

with and as a condition precedent to each Loan Agreement,

which by its own deeming fiction treats every Facility

Agreement, with the Personal Guarantee included, as set out

“as if … in extension” of the Agreement itself. A guarantee so

defined and so integrated cannot be severed, for purposes of

dispute resolution alone, from the very Clause 11.2 that

governs disputes touching the rights and obligations arising

under that Agreement, while remaining tethered to it for

every other purpose, including the extent of liability.

CONCLUSION

29. For the foregoing reasons, we hold that the arbitration clause

contained in Clause 11.2 of the Loan Agreements stands

incorporated, within the meaning of Section 7(5) of the 1996

Act, into the Personal Guarantees dated 27.12.2016 and

18.08.2017 executed by respondent no. 2, who is

accordingly bound to submit to arbitration in respect of

disputes arising therefrom.

19

30. The judgment dated 28.01.2026 passed by the High Court,

and the order dated 23.10.2024 passed by the Sole

Arbitrator, insofar as the application under Section 16 of the

1996 Act qua respondent no. 2 was allowed, are quashed

and set aside.

31. In the result, the appeal is allowed. There shall be no order

as to costs. Pending applications, if any, stand disposed of.

……………..……………………………….J.
[PAMIDIGHANTAM SRI NARASIMHA]

………………………………………………J.
[ALOK ARADHE]

NEW DELHI;
SEPTEMBER 8, 2026.